Installation of the Collector Tanks of the Seal Drain System
TASK 29-17-11-400-001-A
Installation of the Collector Tanks of the Seal Drain System
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 29-17-11-860-050-A
Subtask 29-17-11-420-050-A
Subtask 29-17-11-942-050-A
[Rev.10 from 2021]
2026.04.01 00:25:29 UTC
Installation of the Collector Tanks of the Seal Drain System
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | CONTAINER - HYDRAULIC FLUID RESISTANT |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 196BB |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 29-00-00-910-002-A | Safety Procedures of the Hydraulic System |
| TASK 32-12-00-010-001-A | Open the Main Gear Doors for Access |
| TASK 32-12-00-410-001-A | Close the Main Gear Doors after Access |
Subtask 29-17-11-860-050-A
A. Aircraft Maintenance Configuration
(2) Make sure that the access door 196BB is open.
(3) Make sure that the right main door of the main gear is open (Ref. AMM TASK 32-12-00-010-001).
(4) Make sure that the CONTAINER - HYDRAULIC FLUID RESISTANT is in position below the location of the collector tank.
4. ProcedureWARNING:
OBEY THE HYDRAULIC SAFETY PROCEDURES.
(1) Obey the hydraulic safety procedures (Ref. AMM TASK 29-00-00-910-002). (2) Make sure that the access door 196BB is open.
(3) Make sure that the right main door of the main gear is open (Ref. AMM TASK 32-12-00-010-001).
(4) Make sure that the CONTAINER - HYDRAULIC FLUID RESISTANT is in position below the location of the collector tank.
Subtask 29-17-11-420-050-A
A. Installation of the Collector Tank
(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Remove the blanking plugs.
(4) Put the collector tank (3) in position.
(5) Engage and close the clamp (2).
(6) Make sure that the hydraulic line end-fittings are serviceable.
(7) Connect the pipe end-fitting (1) to the collector tank (3).
5. Close-up(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Remove the blanking plugs.
(4) Put the collector tank (3) in position.
(5) Engage and close the clamp (2).
(6) Make sure that the hydraulic line end-fittings are serviceable.
(7) Connect the pipe end-fitting (1) to the collector tank (3).
Subtask 29-17-11-942-050-A
A. Remove the container.
Subtask 29-17-11-410-050-A B. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the right main door of the main gear (Ref. AMM TASK 32-12-00-410-001).
(3) Close the access door 196BB.
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the right main door of the main gear (Ref. AMM TASK 32-12-00-410-001).
(3) Close the access door 196BB.
Collector Tank