Zonal Inspection as far as Visible from the Ground of the Power Plant, the Nacelles and the Pylons
TASK 05-24-00-200-001-A
Zonal Inspection as far as Visible from the Ground of the Power Plant, the Nacelles and the Pylons
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
3. Job Set-up
Subtask 05-24-00-869-050-A
Subtask 05-24-00-210-050-A
[Rev.10 from 2021]
2026.03.31 22:49:47 UTC
Zonal Inspection as far as Visible from the Ground of the Power Plant, the Nacelles and the Pylons
ZONE: 400
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 400 | POWER PLANT, NACELLES AND PYLONS |
Subtask 05-24-00-869-050-A
A. Not Applicable
4. ProcedureSubtask 05-24-00-210-050-A
A. Inspection
(1) Do a general visual inspection of the power plant, the nacelles and the pylons from the ground during the aircraft walkaround.
(2) Make sure that there is no deterioration (damage, corrosion, leakage, cracks or chafing).
(1) Do a general visual inspection of the power plant, the nacelles and the pylons from the ground during the aircraft walkaround.
(2) Make sure that there is no deterioration (damage, corrosion, leakage, cracks or chafing).