General Visual Inspection of Stabilizers and Cone/Rear Fuselage
TASK 05-23-00-200-002-A
General Visual Inspection of Stabilizers and Cone/Rear Fuselage
Refer to the MPD TASK: ZL-300-02
GENERAL VISUAL INSPECTION OF STABILIZERS AND CONE/REAR FUSELAGE
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 05-23-00-010-050-A
Subtask 05-23-00-210-051-A
Subtask 05-23-00-410-050-A
[Rev.10 from 2021]
2026.03.31 22:49:25 UTC
General Visual Inspection of Stabilizers and Cone/Rear Fuselage
ZONE: 300
1. Reason for the JobRefer to the MPD TASK: ZL-300-02
GENERAL VISUAL INSPECTION OF STABILIZERS AND CONE/REAR FUSELAGE
NOTE: This is an alternative method for the general visual inspection of the stabilizers and the cone/rear fuselage.
For the other method, refer to the relevant task in this page block.
2. Job Set-up InformationFor the other method, refer to the relevant task in this page block.
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 12M (40 FT) - ADJUSTABLE |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 300 | STABILIZERS AND TAIL UNIT |
| REFERENCE | DESIGNATION |
|---|---|
Subtask 05-23-00-010-050-A
A. Get Access
(1) Put the ACCESS PLATFORM 12M (40 FT) - ADJUSTABLE in position at zone 300.
4. Procedure(1) Put the ACCESS PLATFORM 12M (40 FT) - ADJUSTABLE in position at zone 300.
Subtask 05-23-00-210-051-A
A. Inspection
(1) Do a general visual inspection of the stabilizers and cone/rear fuselage.
(2) Make sure that there are no signs of corrosion, cracks or damage.
5. Close-up(1) Do a general visual inspection of the stabilizers and cone/rear fuselage.
(2) Make sure that there are no signs of corrosion, cracks or damage.
Subtask 05-23-00-410-050-A
A. Close Access
(1) Remove the access platform(s).
(1) Remove the access platform(s).
Inspection of the Stabilizers and the Cone/Rear Fuselage