1. Reason for the Job
Refer to the MPD TASK: ZL-195-01
GENERAL VISUAL INSPECTION OF HYDRAULIC COMPARTMENT AND FAIRINGS (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
1
ACCESS PLATFORM 2M (6 FT)
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
195
HYDRAULIC COMPT AND FAIRINGS
196
HYDRAULIC COMPT AND FAIRINGS
195BB, 196BB
 C. Referenced Information
REFERENCE
DESIGNATION
3. Job Set-up
Subtask 05-21-90-010-054-A
A. Get Access
   (1) Put an ACCESS PLATFORM 2M (6 FT) in position at zones 195 and 196.
   (2) Open the hydraulic reservoir pressurization access-door 195BB and the Yellow hydraulic compartment access-door 196BB.
4. Procedure
Subtask 05-21-90-210-054-A
A. Inspection
   (1) Do a general visual inspection of the hydraulic compartment and the fairings.
   (2) Make sure that there are no signs of corrosion damage, cracks or other damage.
   (3) Make sure that all the installations (wiring, ducting, piping) are correctly attached.
5. Close-up
Subtask 05-21-90-410-054-A
A. Close Access
   (1) Close the hydraulic reservoir pressurization access-door 195BB and the Yellow hydraulic compartment access-door 196BB.