1. Reason for the Job
Refer to the MPD TASK: ZL-125-02
GENERAL VISUAL INSPECTION OF LATERAL AVIONIC COMPARTMENT (EWIS)
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 05-21-20-010-057-A
Subtask 05-21-20-210-057-A
Subtask 05-21-20-410-057-A
[Rev.10 from 2021]
2026.03.31 22:48:31 UTC
General Visual Inspection of Lateral Avionic Compartment (EWIS)
1. Reason for the Job
Refer to the MPD TASK: ZL-125-02
GENERAL VISUAL INSPECTION OF LATERAL AVIONIC COMPARTMENT (EWIS)
NOTE: This is an EWIS (Electrical Wiring Interconnection System) procedure. EWIS is defined in ESPM 20-33-11.
2. Job Set-up InformationA. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 125 | LATERAL AVIONIC COMPARTMENT |
| 126 | LATERAL AVIONIC COMPARTMENT |
| 812, 822, 824 |
| REFERENCE | DESIGNATION |
|---|---|
Subtask 05-21-20-010-057-A
A. Get Access
(1) For zones 125 and 126:
(a) Put an ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position at zones 125 and 126.
(b) Open access doors 812, 822 and 824.
4. Procedure(1) For zones 125 and 126:
(a) Put an ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position at zones 125 and 126.
(b) Open access doors 812, 822 and 824.
Subtask 05-21-20-210-057-A
A. Inspection
(1) Do a general visual inspection of the lateral avionic compartment.
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are attached correctly.
5. Close-up(1) Do a general visual inspection of the lateral avionic compartment.
(2) Make sure that there are no signs of corrosion, cracks or damage.
(3) Make sure that all the installations (wiring, ducting, piping) are attached correctly.
NOTE: Lift the insulation blankets sufficiently to complete a correct general visual inspection as necessary.
Subtask 05-21-20-410-057-A
Access Doors of the Avionics Compartment (Left Side)