Removal of the Drain Tubes [CFML]
TASK 71-71-49-000-802-A
Removal of the Drain Tubes
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 71-71-49-941-054-A
Subtask 71-71-49-020-053-A
[Rev.10 from 2021]
2026.04.02 07:32:20 UTC
Removal of the Drain Tubes
WARNING:
BE CAREFUL WHEN YOU DO WORK ON THE ENGINE PARTS AFTER THE ENGINE SHUTDOWN. USE APPLICABLE THERMAL GLOVES. THE ENGINE PARTS CAN STAY HOT FOR ONE HOUR AFTER SHUTDOWN AND CAN BURN YOU.
ZONE: 400
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 1M(3 FT) |
| No specific | 1 | CONTAINER - STORAGE |
| No specific | AR | WARNING NOTICE(S) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 400 | POWER PLANT, NACELLES AND PYLONS |
| FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1) | |
| 437AL, 438AR, 451AL, 452AR | |
| FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2) | |
| 447AL, 448AR, 461AL, 462AR | |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 71-13-00-010-803-A | Opening of the Fan Cowl Doors |
| TASK 71-71-41-000-802-A | Removal of the Fan Drain Mast |
| TASK 71-71-42-000-802-A | Removal of the Core Drain Mast |
| TASK 78-30-00-040-807-A | Deactivation of the Thrust Reverser System for Nacelle Maintenance (ICU) |
| TASK 78-36-00-010-806-A | Opening of the Thrust Reverser Cowl Doors |
Subtask 71-71-49-941-054-A
A. Safety Precautions
(1) On the center pedestal, on ENG panel 115VU:
(a) Make sure that the ENG/MODE selector switch is in the NORM position.
(b) Make sure that the ENG/MASTER 1(2) control switch was in the OFF position not less than five minutes before you do this procedure.
(c) Put the WARNING NOTICE(S) in position to tell persons not to operate:
(a) Make sure that the ON legend of the FADEC GND PWR/1(2) pushbutton switch is off.
(b) Put the WARNING NOTICE(S) in position to tell persons not to energize FADEC 1(2).
Subtask 71-71-49-010-058-A (1) On the center pedestal, on ENG panel 115VU:
(a) Make sure that the ENG/MODE selector switch is in the NORM position.
(b) Make sure that the ENG/MASTER 1(2) control switch was in the OFF position not less than five minutes before you do this procedure.
(c) Put the WARNING NOTICE(S) in position to tell persons not to operate:
- The ENG/MODE selector switch
- The ENG/MASTER 1(2) control switch.
(a) Make sure that the ON legend of the FADEC GND PWR/1(2) pushbutton switch is off.
(b) Put the WARNING NOTICE(S) in position to tell persons not to energize FADEC 1(2).
B. Get Access
(1) Open the fan cowl doors (Ref. AMM TASK 71-13-00-010-803):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
437AL 438AR
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
447AL 448AR.
(2) Put the ACCESS PLATFORM 1M(3 FT) in position under the right fan cowl cowl door.
Subtask 71-71-49-040-054-A (1) Open the fan cowl doors (Ref. AMM TASK 71-13-00-010-803):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
437AL 438AR
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
447AL 448AR.
(2) Put the ACCESS PLATFORM 1M(3 FT) in position under the right fan cowl cowl door.
C. Deactivation of the Thrust Reverser System for Maintenance
Subtask 71-71-49-010-059-A WARNING:
YOU MUST DEACTIVATE THE THRUST REVERSER BEFORE YOU DO WORK ON OR AROUND IT. IF YOU DO NOT, THE THRUST REVERSER CAN OPERATE ACCIDENTALLY AND CAUSE AN INJURY AND/OR DAMAGE.
(1) Do the deactivation of the thrust reverser system for nacelle maintenance (Ref. AMM TASK 78-30-00-040-807). D. Get Access
(1) Open the thrust reverser cowl-doors (Ref. AMM TASK 78-36-00-010-806):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
451AL 452AR
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
461AL 462AR.
4. Procedure(1) Open the thrust reverser cowl-doors (Ref. AMM TASK 78-36-00-010-806):
(a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
451AL 452AR
(b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
461AL 462AR.
Subtask 71-71-49-020-053-A
A. Removal of the Fan Case Drain Tubes
(1) Put the CONTAINER - STORAGE below the drain hose to catch any fluid remaining in the hose.
(2) Remove tube (27) as follows:
(a) Disconnect the coupling nut (30) from the port (29) on the gearbox (28).
(b) Remove the bolts (22), (31), and (34) that attach the P-clamps (21), (32), (33) to the support brackets (20), (35), and (36).
(c) Disconnect the tube (27) from the fan drain mast (26).
(d) Remove the tube (27) from the engine.
(e) Make a record of the location and position of the P-clamps (21), (32), and (33) on the tube (27) to help during installation.
(f) Remove the P-clamps (21), (32), and (33) from the tube (27).
(3) Remove tube (25) as follows:
(a) Disconnect the coupling nut (42) from the port (49) on the gearbox (28).
(b) Remove the two bolts (46) that attach the tube clamp (45) to the support bracket (47).
(c) Disconnect the tube (25) from the fan drain mast (26).
(d) Remove the tube (25) from the engine.
(e) Make a record of the location and position of the tube clamp (45) on the tubes (23), (24), and (25) to help during installation.
(f) Remove the tube clamp (45) from the tubes (23), (24), and (25).
(4) Remove tube (24) as follows:
(a) Disconnect the coupling nut (38) from the port (37) on the gearbox (28).
(b) Remove the bolt (44) that attaches the tube clamp (43) to the support bracket (48).
(c) Remove the bolt (40) that attaches the P-clamp (39) to the support bracket (41).
(d) Disconnect the tube (24) from the fan drain mast (26).
(e) Remove the tube (24) from the engine.
(f) Make a record of the location and position of the tube clamp (43) and P-clamp (39) on the tube (24) to help during installation.
(g) Remove the tube clamp (43) from the tube (24) and tube (23).
(h) Remove the P-clamp (39) from the tube (24).
(5) Remove tube (23) as follows:
(a) Disconnect the coupling nut (51) from the port (50) on the gearbox (28).
(b) Remove the bolts (52), (56), and (58) that attach the P-clamps (54), (55), and (59) to the support bracket (53), (57), and (60).
(c) Disconnect the tube (23) from the fan drain mast (26).
(d) Remove the tube (23) from the engine.
(e) Make a record of the location and position of the P-clamps (54), (55), and (59) on the tube (23) to help during installation.
(f) Remove the P-clamps (54), (55), and (59) from the tube (23).
(6) Remove tube (7) as follows:
(a) Disconnect the coupling nut (8) from the oil tank (9).
(b) Remove the bolts (6), (5), (17), (16), and (14) that attach the P-clamps (2), (4), (18), (11), and (13) to the support brackets (1), (3), (10), (12), and (15).
(c) Disconnect the tube (7) from the fan drain mast (26).
(d) Remove the tube (7) from the engine.
(e) Make a record of the location and position of the P-clamps (2), (4), (18), (11), and (13) on the tube (7) to help during installation.
(f) Remove the P-clamps (2), (4), (18), (11), and (13) from the tube (7).
(7) Remove the fan drain mast (Ref. AMM TASK 71-71-41-000-802).
(8) Install protective covers and protective caps on all open connectors and receptacles.
Subtask 71-71-49-020-054-A (1) Put the CONTAINER - STORAGE below the drain hose to catch any fluid remaining in the hose.
(2) Remove tube (27) as follows:
(a) Disconnect the coupling nut (30) from the port (29) on the gearbox (28).
(b) Remove the bolts (22), (31), and (34) that attach the P-clamps (21), (32), (33) to the support brackets (20), (35), and (36).
(c) Disconnect the tube (27) from the fan drain mast (26).
(d) Remove the tube (27) from the engine.
(e) Make a record of the location and position of the P-clamps (21), (32), and (33) on the tube (27) to help during installation.
(f) Remove the P-clamps (21), (32), and (33) from the tube (27).
(3) Remove tube (25) as follows:
(a) Disconnect the coupling nut (42) from the port (49) on the gearbox (28).
(b) Remove the two bolts (46) that attach the tube clamp (45) to the support bracket (47).
(c) Disconnect the tube (25) from the fan drain mast (26).
(d) Remove the tube (25) from the engine.
(e) Make a record of the location and position of the tube clamp (45) on the tubes (23), (24), and (25) to help during installation.
(f) Remove the tube clamp (45) from the tubes (23), (24), and (25).
(4) Remove tube (24) as follows:
(a) Disconnect the coupling nut (38) from the port (37) on the gearbox (28).
(b) Remove the bolt (44) that attaches the tube clamp (43) to the support bracket (48).
(c) Remove the bolt (40) that attaches the P-clamp (39) to the support bracket (41).
(d) Disconnect the tube (24) from the fan drain mast (26).
(e) Remove the tube (24) from the engine.
(f) Make a record of the location and position of the tube clamp (43) and P-clamp (39) on the tube (24) to help during installation.
(g) Remove the tube clamp (43) from the tube (24) and tube (23).
(h) Remove the P-clamp (39) from the tube (24).
(5) Remove tube (23) as follows:
(a) Disconnect the coupling nut (51) from the port (50) on the gearbox (28).
(b) Remove the bolts (52), (56), and (58) that attach the P-clamps (54), (55), and (59) to the support bracket (53), (57), and (60).
(c) Disconnect the tube (23) from the fan drain mast (26).
(d) Remove the tube (23) from the engine.
(e) Make a record of the location and position of the P-clamps (54), (55), and (59) on the tube (23) to help during installation.
(f) Remove the P-clamps (54), (55), and (59) from the tube (23).
(6) Remove tube (7) as follows:
(a) Disconnect the coupling nut (8) from the oil tank (9).
(b) Remove the bolts (6), (5), (17), (16), and (14) that attach the P-clamps (2), (4), (18), (11), and (13) to the support brackets (1), (3), (10), (12), and (15).
(c) Disconnect the tube (7) from the fan drain mast (26).
(d) Remove the tube (7) from the engine.
(e) Make a record of the location and position of the P-clamps (2), (4), (18), (11), and (13) on the tube (7) to help during installation.
(f) Remove the P-clamps (2), (4), (18), (11), and (13) from the tube (7).
(7) Remove the fan drain mast (Ref. AMM TASK 71-71-41-000-802).
(8) Install protective covers and protective caps on all open connectors and receptacles.
B. Removal of the Left-Hand Core Drain Tubes
(1) Put the CONTAINER - STORAGE below the drain hose to catch any fluid remaining in the hose.
(2) Remove tubes (77), (80), and (96) as follows:
(a) Disconnect the coupling nut (83) of the tube (77) from the VSV (84).
(b) Disconnect the coupling nut (82) from the tube (80).
(c) Remove the tube (77) from the engine.
(d) Remove the bolt (79) that attaches the P-clamp (78) and the tube (80).
(e) Disconnect the hydraulic coupling (81) from the MTCC and VBV valves.
(f) Disconnect the coupling nut (95) from the tube (96).
(g) Remove the tube (80) from the engine.
(h) Make a record of the location and position of the P-clamp (78) on the tube (80) to help during installation.
(i) Remove the P-clamp (78) from the tube (80).
(j) Remove the bolt (98) that attaches the P-clamp (97) and the tube (96) to the support bracket (102).
(k) Disconnect the coupling nut (117) from the tube (114).
(l) Disconnect the coupling nut (144) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(m) Remove the tube (96) from the engine.
(n) Make a record of the location and position of the P-clamp (97) on the tube (96) to help during installation.
(o) Remove the P-clamp (97) from the tube (96).
(3) Remove tubes (106) and (99) as follows:
(a) Disconnect the coupling nut (109) of the tube (106) from the A-Sump drain.
(b) Remove the bolts (107) and (104) that attach the P-clamps (108) and (105).
(c) Disconnect the coupling nut (103).
(d) Remove the tube (106) from the engine.
(e) Make a record of the location and position of the P-clamps (108) and (105) on the tube (106) to help during installation.
(f) Remove the P-clamps (108) and (105) from the tube (106).
(g) Remove the bolt (101) that attaches the P-clamp (100) and the tube (99) to the support bracket (102).
(h) Disconnect the coupling nut (143) of the tube (99) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(i) Remove the tube (99) from the engine.
(j) Make a record of the location and position of the P-clamp (100) on the tube (99) to help during installation.
(k) Remove the P-clamp (100) from the tube (99).
(4) Remove tubes (129) and (134) as follows:
(a) Disconnect the hydraulic connection (126) of the tube (129) from the B-Sump drain.
(b) Disconnect the coupling nut (128) of the tube (129) from the B-Sump drain.
(c) Remove the bolts (133) and (131) that attach the P-clamps (132) and (130) to the support bracket (127).
(d) Disconnect the coupling nut (135).
(e) Remove the tube (129) from the engine.
(f) Make a record of the location and position of the P-clamps (132) and (130) on the tube (129) to help during installation.
(g) Remove the P-clamps (132) and (130) from the tube (129).
(h) Disconnect the tube (134) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(i) Remove the tube (134) from the engine.
(5) Remove tubes (72), (110), (166), and (114) as follows:
(a) Disconnect the coupling nut (73) from the HPTACC (71).
(b) Remove the bolts (86), (88), and (90) that attach the P-clamps (85), (87), and (89).
(c) Disconnect the coupling nut (91) from the tube (110).
(d) Remove the tube (72) from the engine.
(e) Make a record of the location and position of the P-clamps (85), (87), and (89) on the tube (72) to help during installation.
(f) Remove the P-clamps (85), (87), and (89) from the tube (72).
(g) Disconnect the coupling nut (165) of the tube (110) from the LPTACC tube (166).
(h) Remove the bolt (112) that attaches the P-clamp (111) to the support bracket (122).
(i) Disconnect the coupling nut (113) of the tube (110) from the tube (114).
(j) Remove the tube (110) from the engine.
(k) Make a record of the location and position of the P-clamp (111) on the tube (110) to help during installation.
(l) Remove the P-clamp (111) from the tube (110).
(m) Remove the bolts (119) and (116) that attach the P-clamps (120) and (115) to the support bracket (121) and (118).
(n) Remove the tube (114) from the engine.
(o) Make a record of the location and position of the P-clamps (120) and (115) on the tube (114) to help during installation.
(p) Remove the P-clamps (120) and (115) from the tube (114).
(6) Remove tubes (70), (150), and (137) of the LHS pylon drain line as follows:
(a) Disconnect the coupling nut (75) of the tube (70) from the pylon drain (76).
(b) Remove the bolt (171) that attaches the P-clamp (170) to the support bracket (175).
(c) Remove the bolt (173) that attaches the P-clamp (172) to the support bracket (174).
(d) Remove the bolt (159) that attaches the P-clamp (158) to the support bracket (164).
(e) Disconnect the coupling nut (161) of the tube (150) from the tube (70).
(f) Remove the tube (70) from the engine.
(g) Make a record of the location and position of the P-clamps (170), (172), and (158) on the tube (70) to help during installation.
(h) Remove the P-clamps (170), (172), and (158) from the tube (70).
(i) Remove the bolt (163) that attaches the P-clamp (162) and the tube (150).
(j) Remove the bolt (149) that attaches the P-clamp (148) and the tube (150) to the support bracket (151).
(k) Disconnect the coupling nut (152) of the tube (150) from the tube (137).
(l) Remove the tube (150) from the engine.
(m) Make a record of the location and position of the P-clamps (162) and (148) on the tube (150) to help during installation.
(n) Remove the P-clamps (162) and (148) from the tube (150).
(o) Remove the bolts (154) and (139) that attach the P-clamps (153) and (138) and the tube (137) to the support brackets (155) and (136).
(p) Disconnect the coupling nut (140) of the tube (137) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(q) Remove the tube (137) from the engine.
(r) Make a record of the location and position of the P-clamps (153) and (138) on the tube (137) to help during installation.
(s) Remove the P-clamps (153) and (138) from the tube (137).
(7) Install protective covers and protective caps on all open connectors and receptacles.
Subtask 71-71-49-020-055-A (1) Put the CONTAINER - STORAGE below the drain hose to catch any fluid remaining in the hose.
(2) Remove tubes (77), (80), and (96) as follows:
(a) Disconnect the coupling nut (83) of the tube (77) from the VSV (84).
(b) Disconnect the coupling nut (82) from the tube (80).
(c) Remove the tube (77) from the engine.
(d) Remove the bolt (79) that attaches the P-clamp (78) and the tube (80).
(e) Disconnect the hydraulic coupling (81) from the MTCC and VBV valves.
(f) Disconnect the coupling nut (95) from the tube (96).
(g) Remove the tube (80) from the engine.
(h) Make a record of the location and position of the P-clamp (78) on the tube (80) to help during installation.
(i) Remove the P-clamp (78) from the tube (80).
(j) Remove the bolt (98) that attaches the P-clamp (97) and the tube (96) to the support bracket (102).
(k) Disconnect the coupling nut (117) from the tube (114).
(l) Disconnect the coupling nut (144) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(m) Remove the tube (96) from the engine.
(n) Make a record of the location and position of the P-clamp (97) on the tube (96) to help during installation.
(o) Remove the P-clamp (97) from the tube (96).
(3) Remove tubes (106) and (99) as follows:
(a) Disconnect the coupling nut (109) of the tube (106) from the A-Sump drain.
(b) Remove the bolts (107) and (104) that attach the P-clamps (108) and (105).
(c) Disconnect the coupling nut (103).
(d) Remove the tube (106) from the engine.
(e) Make a record of the location and position of the P-clamps (108) and (105) on the tube (106) to help during installation.
(f) Remove the P-clamps (108) and (105) from the tube (106).
(g) Remove the bolt (101) that attaches the P-clamp (100) and the tube (99) to the support bracket (102).
(h) Disconnect the coupling nut (143) of the tube (99) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(i) Remove the tube (99) from the engine.
(j) Make a record of the location and position of the P-clamp (100) on the tube (99) to help during installation.
(k) Remove the P-clamp (100) from the tube (99).
(4) Remove tubes (129) and (134) as follows:
(a) Disconnect the hydraulic connection (126) of the tube (129) from the B-Sump drain.
(b) Disconnect the coupling nut (128) of the tube (129) from the B-Sump drain.
(c) Remove the bolts (133) and (131) that attach the P-clamps (132) and (130) to the support bracket (127).
(d) Disconnect the coupling nut (135).
(e) Remove the tube (129) from the engine.
(f) Make a record of the location and position of the P-clamps (132) and (130) on the tube (129) to help during installation.
(g) Remove the P-clamps (132) and (130) from the tube (129).
(h) Disconnect the tube (134) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(i) Remove the tube (134) from the engine.
(5) Remove tubes (72), (110), (166), and (114) as follows:
(a) Disconnect the coupling nut (73) from the HPTACC (71).
(b) Remove the bolts (86), (88), and (90) that attach the P-clamps (85), (87), and (89).
(c) Disconnect the coupling nut (91) from the tube (110).
(d) Remove the tube (72) from the engine.
(e) Make a record of the location and position of the P-clamps (85), (87), and (89) on the tube (72) to help during installation.
(f) Remove the P-clamps (85), (87), and (89) from the tube (72).
(g) Disconnect the coupling nut (165) of the tube (110) from the LPTACC tube (166).
(h) Remove the bolt (112) that attaches the P-clamp (111) to the support bracket (122).
(i) Disconnect the coupling nut (113) of the tube (110) from the tube (114).
(j) Remove the tube (110) from the engine.
(k) Make a record of the location and position of the P-clamp (111) on the tube (110) to help during installation.
(l) Remove the P-clamp (111) from the tube (110).
(m) Remove the bolts (119) and (116) that attach the P-clamps (120) and (115) to the support bracket (121) and (118).
(n) Remove the tube (114) from the engine.
(o) Make a record of the location and position of the P-clamps (120) and (115) on the tube (114) to help during installation.
(p) Remove the P-clamps (120) and (115) from the tube (114).
(6) Remove tubes (70), (150), and (137) of the LHS pylon drain line as follows:
(a) Disconnect the coupling nut (75) of the tube (70) from the pylon drain (76).
(b) Remove the bolt (171) that attaches the P-clamp (170) to the support bracket (175).
(c) Remove the bolt (173) that attaches the P-clamp (172) to the support bracket (174).
(d) Remove the bolt (159) that attaches the P-clamp (158) to the support bracket (164).
(e) Disconnect the coupling nut (161) of the tube (150) from the tube (70).
(f) Remove the tube (70) from the engine.
(g) Make a record of the location and position of the P-clamps (170), (172), and (158) on the tube (70) to help during installation.
(h) Remove the P-clamps (170), (172), and (158) from the tube (70).
(i) Remove the bolt (163) that attaches the P-clamp (162) and the tube (150).
(j) Remove the bolt (149) that attaches the P-clamp (148) and the tube (150) to the support bracket (151).
(k) Disconnect the coupling nut (152) of the tube (150) from the tube (137).
(l) Remove the tube (150) from the engine.
(m) Make a record of the location and position of the P-clamps (162) and (148) on the tube (150) to help during installation.
(n) Remove the P-clamps (162) and (148) from the tube (150).
(o) Remove the bolts (154) and (139) that attach the P-clamps (153) and (138) and the tube (137) to the support brackets (155) and (136).
(p) Disconnect the coupling nut (140) of the tube (137) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(q) Remove the tube (137) from the engine.
(r) Make a record of the location and position of the P-clamps (153) and (138) on the tube (137) to help during installation.
(s) Remove the P-clamps (153) and (138) from the tube (137).
(7) Install protective covers and protective caps on all open connectors and receptacles.
C. Removal of the Right-Hand Core Drain Tubes
(1) Put the CONTAINER - STORAGE below the drain hose to catch any fluid remaining in the hose.
(2) Remove the tube (270) of the pylon drain as follow:
(a) Disconnect the coupling nut (271) of the tube (270) from the pylon.
(b) Disconnect the coupling nut (269) from the tube (192).
(c) Remove the tube (270) from the engine.
PRE-SPOL BD-EBU-17003 AND PRE SB BD70CR71-031
(3) Remove the tubes (196) and (213) of the RHS pylon drain line as follows:
(a) Disconnect the coupling nut (193) of the tube (192) from the tube (196).
(b) Remove the bolt (195) that attaches the P-clamp (194).
(c) Remove the bolt (217) that attaches the P-clamp (218) to the support bracket (216).
(d) Disconnect the coupling nut (211) of the tube (196) from the tube (213).
(e) Remove the tube (196) from the engine.
(f) Make a record of the location and position of the P-clamps (194) and (218) on the tube (196) to help during installation.
(g) Remove the P-clamps (194) and (218) from the tube (196).
(h) Remove the bolt (214) that attaches the P-clamp (215) to the support bracket (212).
(i) Remove the bolt (260) that attaches the P-clamp (261) to the support bracket (262).
(j) Disconnect the coupling nut (259) of the tube (213) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(k) Remove the tube (213) from the engine.
(l) Make a record of the location and positions of the P-clamps (215) and (261) on the tube (213) to help during installation.
(m) Remove the P-clamps (215) and (261) from the tube (213).
END OF PRE SPOL BD-EBU-17003 AND PRE SB BD70CR71-031
POST SPOL BD-EBU-17003 AND POST SB BD70CR71-031
(4) Remove the tube (196) of the RHS pylon drain line as follows:
(a) Disconnect the coupling nut (193) of the tube (192) from the tube (196).
(b) Remove the bolt (195) that attaches the P-clamp (194).
(c) Remove the bolt (217) that attaches the P-clamp (218) to the support bracket (216).
(d) Remove the P-clamps (194) and (218) from the tube (196).
(e) Remove the bolt (214) that attaches the P-clamp (215) to the support bracket (212).
(f) Remove the bolt (260) that attaches the P-clamp (261) to the support bracket (262).
(g) Disconnect the coupling nut (259) of the tube (196) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(h) Remove the tube (196) from the engine.
(i) Make a record of the location and positions of the P-clamps (194), (218), (215) and (261) on the tube (196) to help during installation.
(j) Remove the P-clamps (215) and (261) from the tube (196).
END OF POST SPOL BD-EBU-17003 AND POST SB BD70CR71-031
(5) Remove the tube (185) of the SBV-BAI drain line as follows:
(a) Disconnect the coupling nut (186) of the tube (185) from the SBV (189).
(b) Remove the bolt (237) that attaches the P-clamp (238).
(c) Disconnect the coupling nut (222) of the tube (185) from tube (187).
(d) Remove the tube (185) from the engine.
(e) Make a record of the location and position of the P-clamp (238) on the tube (185) to help during installation.
(f) Remove the P-clamp (238) from the tube (185).
PRE-SPOL BD-EBU-17008
(6) Remove the tubes (224), (275), (231), (246) and (249) of the VSV, MTC and VBV RHS drain lines as follows:
(a) Disconnect the coupling nut (226) of tube (224) from the VSV drain.
(b) Disconnect the connection (225) of tube (224) from the VSV drain.
(c) Disconnect coupling nut (266) that connects tube (224) to tube (275).
(d) Remove the bolt (230) that attaches the P-clamp (229).
(e) Disconnect the coupling nut (223) of tube (275) from tube (231).
(f) Remove the tube (224) and tube (275) from the engine.
(g) Make a record of the location and position of the P-clamp (229) on the tube (275) to help during installation.
(h) Remove the P-clamp (229) from the tube (275).
(i) Disconnect the coupling nut (242) of the tube (246) from the VBV drain.
(j) Remove the bolt (244) that attaches the P-clamp (243) to the support bracket (245).
(k) Disconnect the coupling nut (247) of the tube (246) from tube (231).
(l) Remove the tube (246) from the engine.
(m) Make a record of the location and position of the P-clamp (243) on the tube (246) to help during installation.
(n) Remove the P-clamp (243) from the tube (246).
(o) Remove the bolts (252) and (250) that attach the P-clamps (253) and (251) on the tube (231).
(p) Disconnect the coupling nut (248) of the tube (249) from tube (231).
(q) Remove the tube (231) from the engine.
(r) Make a record of the location and position of the P-clamps (253) and (251) on the tube (231) to help during installation.
(s) Remove the P-clamps (253) and (251) from the tube (231).
(t) Remove the bolt (264) that attaches the P-clamp (265) on the tube (249) to the support bracket (255).
(u) Remove the bolt (257) that attaches the P-clamp (256) on the tube (249).
(v) Disconnect the coupling nut (258) of the tube (249) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(w) Remove the tube (249) from the engine.
(x) Make a record of the location and position of the P-clamps (265) and (256) on the tube (249) to help during installation.
(y) Remove the P-clamps (265) and (256) from the tube (249).
END OF PRE-SPOL BD-EBU-17008
POST-SPOL BD-EBU-17008
(7) Remove the tubes (224), (231), (246) and (249) of the VSV and VBV RHS drain lines as follows:
(a) Disconnect the coupling nut (226) of the tube (224) from the VSV drain.
(b) Remove the bolt (230) that attaches the P-clamp (229).
(c) Disconnect the coupling nut (223) of the tube (224) from tube (231).
(d) Remove the tube (224) from the engine.
(e) Make a record of the location and position of the P-clamps (229) on the tube (224) to help during installation.
(f) Remove the P-clamps (229) from the tube (224).
(g) Disconnect the coupling nut (242) of the tube (246) from the VBV drain.
(h) Remove the bolt (244) that attaches the P-clamp (243) to the support bracket (245).
(i) Disconnect the coupling nut (247) of the tube (246) from tube (231).
(j) Remove the tube (246) from the engine.
(k) Make a record of the location and position of the P-clamp (243) on the tube (246) to help during installation.
(l) Remove the P-clamp (243) from the tube (246).
(m) Remove the bolts (252) and (250) that attach the P-clamps (253) and (251) on the tube (231).
(n) Disconnect the coupling nut (248) of the tube (249) from tube (231).
(o) Remove the tube (231) from the engine.
(p) Make a record of the location and position of the P-clamps (253) and (251) on the tube (231) to help during installation.
(q) Remove the P-clamps (253) and (251) from the tube (231).
(r) Remove the bolt (264) that attaches the P-clamp (265) on the tube (249) to the support bracket (255).
(s) Remove the bolt (257) that attaches the P-clamp (256) on the tube (249).
(t) Disconnect the coupling nut (258) of the tube (249) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(u) Remove the tube (249) from the engine.
(v) Make a record of the location and position of the P-clamps (265) and (256) on the tube (249) to help during installation.
(w) Remove the P-clamps (265) and (256) from the tube (249).
END OF POST-SPOL BD-EBU-17008
(8) Remove the core drain mast (Ref. AMM TASK 71-71-42-000-802).
(1) Put the CONTAINER - STORAGE below the drain hose to catch any fluid remaining in the hose.
(2) Remove the tube (270) of the pylon drain as follow:
(a) Disconnect the coupling nut (271) of the tube (270) from the pylon.
(b) Disconnect the coupling nut (269) from the tube (192).
(c) Remove the tube (270) from the engine.
PRE-SPOL BD-EBU-17003 AND PRE SB BD70CR71-031
(3) Remove the tubes (196) and (213) of the RHS pylon drain line as follows:
(a) Disconnect the coupling nut (193) of the tube (192) from the tube (196).
(b) Remove the bolt (195) that attaches the P-clamp (194).
(c) Remove the bolt (217) that attaches the P-clamp (218) to the support bracket (216).
(d) Disconnect the coupling nut (211) of the tube (196) from the tube (213).
(e) Remove the tube (196) from the engine.
(f) Make a record of the location and position of the P-clamps (194) and (218) on the tube (196) to help during installation.
(g) Remove the P-clamps (194) and (218) from the tube (196).
(h) Remove the bolt (214) that attaches the P-clamp (215) to the support bracket (212).
(i) Remove the bolt (260) that attaches the P-clamp (261) to the support bracket (262).
(j) Disconnect the coupling nut (259) of the tube (213) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(k) Remove the tube (213) from the engine.
(l) Make a record of the location and positions of the P-clamps (215) and (261) on the tube (213) to help during installation.
(m) Remove the P-clamps (215) and (261) from the tube (213).
END OF PRE SPOL BD-EBU-17003 AND PRE SB BD70CR71-031
POST SPOL BD-EBU-17003 AND POST SB BD70CR71-031
(4) Remove the tube (196) of the RHS pylon drain line as follows:
(a) Disconnect the coupling nut (193) of the tube (192) from the tube (196).
(b) Remove the bolt (195) that attaches the P-clamp (194).
(c) Remove the bolt (217) that attaches the P-clamp (218) to the support bracket (216).
(d) Remove the P-clamps (194) and (218) from the tube (196).
(e) Remove the bolt (214) that attaches the P-clamp (215) to the support bracket (212).
(f) Remove the bolt (260) that attaches the P-clamp (261) to the support bracket (262).
(g) Disconnect the coupling nut (259) of the tube (196) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(h) Remove the tube (196) from the engine.
(i) Make a record of the location and positions of the P-clamps (194), (218), (215) and (261) on the tube (196) to help during installation.
(j) Remove the P-clamps (215) and (261) from the tube (196).
END OF POST SPOL BD-EBU-17003 AND POST SB BD70CR71-031
(5) Remove the tube (185) of the SBV-BAI drain line as follows:
(a) Disconnect the coupling nut (186) of the tube (185) from the SBV (189).
(b) Remove the bolt (237) that attaches the P-clamp (238).
(c) Disconnect the coupling nut (222) of the tube (185) from tube (187).
(d) Remove the tube (185) from the engine.
(e) Make a record of the location and position of the P-clamp (238) on the tube (185) to help during installation.
(f) Remove the P-clamp (238) from the tube (185).
PRE-SPOL BD-EBU-17008
(6) Remove the tubes (224), (275), (231), (246) and (249) of the VSV, MTC and VBV RHS drain lines as follows:
(a) Disconnect the coupling nut (226) of tube (224) from the VSV drain.
(b) Disconnect the connection (225) of tube (224) from the VSV drain.
(c) Disconnect coupling nut (266) that connects tube (224) to tube (275).
(d) Remove the bolt (230) that attaches the P-clamp (229).
(e) Disconnect the coupling nut (223) of tube (275) from tube (231).
(f) Remove the tube (224) and tube (275) from the engine.
(g) Make a record of the location and position of the P-clamp (229) on the tube (275) to help during installation.
(h) Remove the P-clamp (229) from the tube (275).
(i) Disconnect the coupling nut (242) of the tube (246) from the VBV drain.
(j) Remove the bolt (244) that attaches the P-clamp (243) to the support bracket (245).
(k) Disconnect the coupling nut (247) of the tube (246) from tube (231).
(l) Remove the tube (246) from the engine.
(m) Make a record of the location and position of the P-clamp (243) on the tube (246) to help during installation.
(n) Remove the P-clamp (243) from the tube (246).
(o) Remove the bolts (252) and (250) that attach the P-clamps (253) and (251) on the tube (231).
(p) Disconnect the coupling nut (248) of the tube (249) from tube (231).
(q) Remove the tube (231) from the engine.
(r) Make a record of the location and position of the P-clamps (253) and (251) on the tube (231) to help during installation.
(s) Remove the P-clamps (253) and (251) from the tube (231).
(t) Remove the bolt (264) that attaches the P-clamp (265) on the tube (249) to the support bracket (255).
(u) Remove the bolt (257) that attaches the P-clamp (256) on the tube (249).
(v) Disconnect the coupling nut (258) of the tube (249) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(w) Remove the tube (249) from the engine.
(x) Make a record of the location and position of the P-clamps (265) and (256) on the tube (249) to help during installation.
(y) Remove the P-clamps (265) and (256) from the tube (249).
END OF PRE-SPOL BD-EBU-17008
POST-SPOL BD-EBU-17008
(7) Remove the tubes (224), (231), (246) and (249) of the VSV and VBV RHS drain lines as follows:
(a) Disconnect the coupling nut (226) of the tube (224) from the VSV drain.
(b) Remove the bolt (230) that attaches the P-clamp (229).
(c) Disconnect the coupling nut (223) of the tube (224) from tube (231).
(d) Remove the tube (224) from the engine.
(e) Make a record of the location and position of the P-clamps (229) on the tube (224) to help during installation.
(f) Remove the P-clamps (229) from the tube (224).
(g) Disconnect the coupling nut (242) of the tube (246) from the VBV drain.
(h) Remove the bolt (244) that attaches the P-clamp (243) to the support bracket (245).
(i) Disconnect the coupling nut (247) of the tube (246) from tube (231).
(j) Remove the tube (246) from the engine.
(k) Make a record of the location and position of the P-clamp (243) on the tube (246) to help during installation.
(l) Remove the P-clamp (243) from the tube (246).
(m) Remove the bolts (252) and (250) that attach the P-clamps (253) and (251) on the tube (231).
(n) Disconnect the coupling nut (248) of the tube (249) from tube (231).
(o) Remove the tube (231) from the engine.
(p) Make a record of the location and position of the P-clamps (253) and (251) on the tube (231) to help during installation.
(q) Remove the P-clamps (253) and (251) from the tube (231).
(r) Remove the bolt (264) that attaches the P-clamp (265) on the tube (249) to the support bracket (255).
(s) Remove the bolt (257) that attaches the P-clamp (256) on the tube (249).
(t) Disconnect the coupling nut (258) of the tube (249) from the core drain mast (142) (Ref. AMM TASK 71-71-42-000-802).
(u) Remove the tube (249) from the engine.
(v) Make a record of the location and position of the P-clamps (265) and (256) on the tube (249) to help during installation.
(w) Remove the P-clamps (265) and (256) from the tube (249).
END OF POST-SPOL BD-EBU-17008
(8) Remove the core drain mast (Ref. AMM TASK 71-71-42-000-802).
Fan Drain Tubes