Installation of the Integrated Drive Generator (IDG) Control and Anti-Ice Harness [CFMB]


TASK 71-51-43-400-045-A
Installation of the Integrated Drive Generator (IDG) Control and Anti-Ice Harness


WARNING: BE CAREFUL WHEN YOU DO WORK ON THE ENGINE AFTER SHUTDOWN. THE ENGINE CAN STAY HOT FOR A LONG TIME. IF YOU DO NOT OBEY THIS INSTRUCTION, INJURY CAN OCCUR.
WARNING: BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
ZONE: 400
FIN: 4215KS ** ON A/C NOT FOR ALL
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
ACCESS PLATFORM 1M(3 FT)
No specific
1
GROUND AIR-SUPPLY UNIT(HIGH PRESSURE)
No specific
AR
WARNING NOTICE(S)
No specific
Torque wrench: range to between 30 and 25 lbf.in (0.34 and 0.28 m.daN ) T
 B. Consumable Materials
REFERENCE
DESIGNATION
(Material No.CP2740)
tape, hi temp
(Material No.CP5085)
tape, tying, glass fiber
 C. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
400
POWER PLANT, NACELLES AND PYLONS
FOR [1000EM1] (ENGINE-1)
437AL, 438AR
FOR [1000EM2] (ENGINE-2)
447AL, 448AR
 D. Referenced Information
REFERENCE
DESIGNATION
TASK 24-41-00-861-002-A
Energize the Aircraft Electrical Circuits from the External Power
TASK 24-41-00-861-002-A-01
Energize the Aircraft Electrical Circuits from the APU
TASK 24-41-00-861-002-A-02
Energize the Aircraft Electrical Circuits from Engine 1(2)
TASK 24-41-00-862-002-A
De-energize the Aircraft Electrical Circuits Supplied from the External Power
TASK 24-41-00-862-002-A-01
De-energize the Aircraft Electrical Circuits Supplied from the APU
TASK 24-41-00-862-002-A-02
De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2)
TASK 31-60-00-860-001-A
EIS Start Procedure
TASK 31-60-00-860-002-A
EIS Stop Procedure
TASK 70-60-00-910-041-A
Nacelle Maintenance Practices
TASK 71-00-00-710-003-B
Engine Automatic Start
TASK 71-00-00-710-028-B
Engine Shutdown
TASK 71-13-00-010-040-B
Opening of the Fan Cowl Doors
TASK 71-13-00-410-040-B
Closing of the Fan Cowl Doors
3. Job Set-up
Subtask 71-51-43-860-059-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
   (1) On the center pedestal, on the ENG panel 115VU, make sure that a WARNING NOTICE(S) is in position to tell persons not to start the engine.
   (2) On the overhead maintenance panel 50VU, make sure that the ON legend of the ENG/FADEC GND PWR/1(2) pushbutton switch is off. Make sure that a WARNING NOTICE(S) is in position to tell persons not to energize the FADEC 1(2).
   (3) Make sure that the ACCESS PLATFORM 1M(3 FT) is in position.
Subtask 71-51-43-010-069-A ** ON A/C NOT FOR ALL
B. Get Access
   (1) Make sure that the fan cowls are open: (Ref. AMM TASK 71-13-00-010-040)
   (2) FOR [1000EM1] (ENGINE-1)
437AL 438AR
   (3) FOR [1000EM2] (ENGINE-2)
447AL 448AR
Subtask 71-51-43-865-066-A ** ON A/C NOT FOR ALL
WARNING: OPEN THE PROBE HEATER CIRCUIT-BREAKERS 1DA1(2), 3DA1(2,3), 4DA1(2,3) AND 5DA1(2,3) BEFORE ENG1(2)FADEC A and EIU 1(2) C/B'S 2KS1 AND 2KS2. IF YOU DO NOT OBEY THIS SEQUENCE:
  • THE PROBES WILL BECOME TOO HOT.
  • THIS CAN CAUSE DAMAGE TO EQUIPMENT AND INJURY TO MAINTENANCE PERSONNEL.
C. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
49VUCOM/CVR/SPLY2RKE14
49VUCOM/CVR/CTL4RKE13
** ON A/C NOT FOR ALL
49VUENGINE/1 AND 2/IGN/SYS A1JHA03
49VUANTI ICE/PROBES/AOA/14DA1D04
49VUANTI ICE/PROBES/PITOT/13DA1D02
** ON A/C NOT FOR ALL
49VUANTI ICE/RAIN/RPLNT/CAPT1DB1D01
** ON A/C NOT FOR ALL
49VUCOM/CVR/SPLY23RKE14
49VUCOM/CVR/CTL26RKE13
** ON A/C NOT FOR ALL
121VURCDR/DFDR7TUK16
121VUHYDRAULIC/HYD POWER/Y3803GXN30
122VUANTI ICE/WINDOWS/R4DG2W14
122VUANTI ICE/WINDOWS/L4DG1X14
122VUANTI ICE/PROBES/2/PITOT3DA2Y14
122VUANTI ICE/PROBES/2/AOA4DA2Y13
122VUANTI ICE/PROBES/2/STATIC5DA2Y11
122VUANTI ICE/PROBES/3/PITOT3DA3Z16
122VUANTI ICE/PROBES/3/AOA4DA3Z15
122VUANTI ICE/PROBES/3/STATIC5DA3Z14
122VUANTI ICE/PROBES/1/STATIC5DA1Z13
** ON A/C NOT FOR ALL
122VUANTI ICE/RAIN/RPLNT/F/O1DB2W11
** ON A/C NOT FOR ALL
123VUY HYD/ELEC/PUMP3802GXAB06
123VUY HYD/ELEC/ELEC PUMP/NORM3801GXAB03
FOR FIN: 1000EM1 (ENGINE1)
49VUENGINE/1/FIRE DET/LOOP A7WD1A06
49VUENGINE/1/FADEC A/AND EIU 12KS1A04
121VUENGINE/IGN/ENG1/SYS B3JH1P41
121VUENGINE/IGN/ENG1/SYS A BAT2JH1P39
121VUENGINE/ENG1 AND 2 FIRE EXTIG/BTL1/SQUIB/B2WE1Q44
121VUENGINE/ENG1 AND 2 FIRE EXTIG/BTL1/SQUIB/A1WE1Q43
121VUENGINE/ENG1/FIRE DET/LOOP B8WD1Q38
121VUENGINE/ENG1/FADEC B/AND EIU 14KS1R41
122VUELEC/GCU/12XU1T26
FOR FIN: 1000EM2 (ENGINE2)
49VUENGINE/2/FIRE DET/LOOP B8WD2A07
49VUENGINE/2/FADEC A/AND EIU 22KS2A05
121VUENGINE/IGN/ENG2/SYS B3JH2P42
121VUENGINE/IGN/ENG2/SYS A BAT2JH2P40
121VUENGINE/ENG1 AND 2 FIRE EXTIG/BTL2/SQUIB/B2WE2Q42
121VUENGINE/ENG1 AND 2 FIRE EXTIG/BTL2/SQUIB/A1WE2Q41
121VUENGINE/ENG2/FADEC B4KS2Q40
121VUENGINE/ENG2/FIRE DET/LOOP A7WD2Q39
122VUELEC/GCU/22XU2T27
4. Procedure
Subtask 71-51-43-420-055-A ** ON A/C NOT FOR ALL
A. Installation of the IDG Control and Anti-Ice Harness
For the recommended procedure for the installation of the wire harness (Ref. AMM TASK 70-60-00-910-041).
NOTE: To tighten the flip-lock clamps and line blocks, you can turn the captive screws or captive bolts 1/4 turn clockwise to engage the cam nuts.
   (1) Remove the COVER - PROTECTION from the electrical connectors.
   (2) Put the electrical harness (5) in position on the engine.
   (3) Connect the electrical connectors 401VC-A, 404VC-A and 405VC-A to the pylon junction box.
   (4) Connect the electrical connector 4005VC-A to the connector on the left harness at flange station 174.

BEFORE SPIB NO. CFM02255MW1

   (5) Put the harness (5) into the flip-lock clamps (10), (20), (25) and (55).
   (6) Put the harness (5) into the rubber supports of the line blocks (15), (30) and (35). Put the rubber supports in the line blocks.

CONFIG-1

   (7) Put the harness (5) into the rubber supports of the line block (40). Put the rubber support into the line block.

CONFIG-2
(Detail B)

   (8) Put the clamp (50) on the harness (5). Use the bolt (45) to attach the clamps (50) and (75) to the bracket at flange station 167.

END CONFIG-2

   (9) Make sure that the harness (5) is correctly installed on the engine.
   (10) Close the line blocks (15), (30), (35) and if installed the line block (40) and tighten the captive screws.
   (11) Tighten the captive bolts on the flip-lock clamps (10), (20), (25) and (55).

AFTER SPIB NO. CFM02255MW1
   (12) Put the harness (5) into the flip-lock clamps (10).
   (13) Put the bolts and clamps (17) and (27), and the bolts, clamps and anti-rotation lugs (32) on the harness (5) and attach the harness to the engine brackets:
     (a) Do not torque the bolts at this time.
   (14) Put the bolts and clamps (57), and the bolts, clamps and anti-rotation lugs (59) on the harness (5) and attach the harness to the engine brackets:
     (a) Do not torque the bolts at this time.
   (15) Put the bolts and clamps (22) on the harness (5) and attach the harness to the engine brackets:
     (a) Do not torque the bolts at this time.
   (16) Put the harness (5) into the rubber supports of the line block (35) at the flange station 158. Put the rubber supports in the line blocks.

CONFIG-1

   (17) Put the harness (5) into the rubber supports of the line block (40). Put the rubber supports in the line blocks.

CONFIG-2

(Detail B)

   (18) Put the clamps (50) on the harness (5). Use the bolt (45) to attach the clamps (50) and (75) to the bracket at flange station 167.

END CONFIG-2

   (19) Make sure that the harness (5) is correctly installed on the engine.
   (20) Close the line blocks (35) and if installed, line block (40) and tighten the captive screws.
   (21) Tighten the captive bolts on the flip-lock clamps (10).
   (22) TORQUE the bolts (17), (22), (27), (32), (57) and (59) to between 30 and 25 lbf.in (0.34 and 0.28 m.daN ) T.

END SPIB NO. CFM02255MW1

   (23) As required, tie the ground wires together with fiberglass tie tape to prevent cross wires. See the sheet 3 of the figure:
   (24) Connect the ground wires to the ground studs with the nuts (60), the lockwashers (65) and the washers (70).
WIRE
GROUND
GD9965DC/1
GD9965DC
GD9965DC/2
GD9965DC
GD9966DC/1
GD9966DC
GD9966DC/2
GD9966DC
GD9967DC/1
GD9967DC
GD9968DC/1
GD9968DC
GD9969DC/1
GD9969DC
GD9970DC/1
GD9970DC
GD9970DC/2
GD9970DC
   (25) Connect the electrical connectors 4000XU-A, 4000XU-B and 4000XU-C to the IDG.
NOTE: The wire harness for connectors 4000XU-A and 4000XU-B may touch as shown on the figure.
   (26) Connect the electrical connector 4000DN-A to the anti-ice valve.
   (27) Connect the electrical connector 4001VC-A to the interphone jack disconnect on the aft bulkhead of the inlet cowl.
   (28) Make sure that the harness (5) is correctly installed on the engine.
   (29) Examine the harness installation and make sure that all the flip-lock clamps and line blocks are installed correctly.

POST SB RA32071-135

   (30) Apply the tape:
CAUTION: IF THE TWO HARNESSES TOUCH, YOU MUST WIND THEM WITH TAPE (CP2740). IF YOU DO NOT OBEY THIS INSTRUCTION, DAMAGE TO THE HARNESSES CAN OCCUR.
     (a) Wind CP2740tape, hi temp on the two harnesses in the areas shown:
       1 Wind the tape so that each wind overlaps the last wind by half the width of the tape.
   (31) Apply the tape:
CAUTION: YOU MUST WIND THE TWO HARNESSES WITH TAPE (CP2740) AND ATTACH THE HARNESSES TOGETHER WITH TYING TAPE (CP5085). IF YOU DO NOT OBEY THIS INSTRUCTION, DAMAGE TO THE HARNESSES CAN OCCUR.
     (a) Wind CP2740tape, hi temp on the two harnesses in the areas shown:
       1 Wind the tape so that each wind overlaps the last wind by half the width of the tape.
     (b) Attach the two harnesses together with CP5085tape, tying, glass fiber:
       1 Make a clove hitch tie around the two harnesses and pull tight with a firm steady pull.
       2 Make a square knot with an extra loop to finish the tie.

END SB RA32071-135

Subtask 71-51-43-865-067-A ** ON A/C NOT FOR ALL
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
49VUCOM/CVR/SPLY2RKE14
49VUCOM/CVR/CTL4RKE13
** ON A/C NOT FOR ALL
49VUENGINE/1 AND 2/IGN/SYS A1JHA03
49VUANTI ICE/PROBES/AOA/14DA1D04
49VUANTI ICE/PROBES/PITOT/13DA1D02
** ON A/C NOT FOR ALL
49VUANTI ICE/RAIN/RPLNT/CAPT1DB1D01
** ON A/C NOT FOR ALL
49VUCOM/CVR/SPLY23RKE14
49VUCOM/CVR/CTL26RKE13
** ON A/C NOT FOR ALL
121VURCDR/DFDR7TUK16
121VUHYDRAULIC/HYD POWER/Y3803GXN30
122VUANTI ICE/WINDOWS/R4DG2W14
122VUANTI ICE/WINDOWS/L4DG1X14
122VUANTI ICE/PROBES/2/PITOT3DA2Y14
122VUANTI ICE/PROBES/2/AOA4DA2Y13
122VUANTI ICE/PROBES/2/STATIC5DA2Y11
122VUANTI ICE/PROBES/3/PITOT3DA3Z16
122VUANTI ICE/PROBES/3/AOA4DA3Z15
122VUANTI ICE/PROBES/3/STATIC5DA3Z14
122VUANTI ICE/PROBES/1/STATIC5DA1Z13
** ON A/C NOT FOR ALL
122VUANTI ICE/RAIN/RPLNT/F/O1DB2W11
** ON A/C NOT FOR ALL
123VUY HYD/ELEC/PUMP3802GXAB06
123VUY HYD/ELEC/ELEC PUMP/NORM3801GXAB03
FOR FIN: 1000EM1 (ENGINE1)
49VUENGINE/1/FIRE DET/LOOP A7WD1A06
49VUENGINE/1/FADEC A/AND EIU 12KS1A04
121VUENGINE/IGN/ENG1/SYS B3JH1P41
121VUENGINE/IGN/ENG1/SYS A BAT2JH1P39
121VUENGINE/ENG1 AND 2 FIRE EXTIG/BTL1/SQUIB/B2WE1Q44
121VUENGINE/ENG1 AND 2 FIRE EXTIG/BTL1/SQUIB/A1WE1Q43
121VUENGINE/ENG1/FIRE DET/LOOP B8WD1Q38
121VUENGINE/ENG1/FADEC B/AND EIU 14KS1R41
122VUELEC/GCU/12XU1T26
FOR FIN: 1000EM2 (ENGINE2)
49VUENGINE/2/FIRE DET/LOOP B8WD2A07
49VUENGINE/2/FADEC A/AND EIU 22KS2A05
121VUENGINE/IGN/ENG2/SYS B3JH2P42
121VUENGINE/IGN/ENG2/SYS A BAT2JH2P40
121VUENGINE/ENG1 AND 2 FIRE EXTIG/BTL2/SQUIB/B2WE2Q42
121VUENGINE/ENG1 AND 2 FIRE EXTIG/BTL2/SQUIB/A1WE2Q41
121VUENGINE/ENG2/FADEC B4KS2Q40
121VUENGINE/ENG2/FIRE DET/LOOP A7WD2Q39
122VUELEC/GCU/22XU2T27
Subtask 71-51-43-861-052-A ** ON A/C NOT FOR ALL
C. Energize the aircraft electrical circuits (Ref. AMM TASK 24-41-00-861-002)
Subtask 71-51-43-860-060-A ** ON A/C NOT FOR ALL
D. Aircraft Maintenance Configuration
   (1) Do the EIS start procedure (for the lower display of the ECAM system only). (Ref. AMM TASK 31-60-00-860-001).
   (2) Pressurize the aircraft pneumatic system with a GROUND AIR-SUPPLY UNIT(HIGH PRESSURE) or through the APU.
Subtask 71-51-43-710-051-A ** ON A/C NOT FOR ALL
E. Do this test
   (1) Start the engine. Let it become stable at the idle speed. (Ref. AMM TASK 71-00-00-710-003).
   (2) On the ECAM control panel, get the ELEC page. On the lower display unit of the ECAM system:
     (a) make sure that the voltage and frequency are correct.
   (3) Stop the engine. (Ref. AMM TASK 71-00-00-710-028).
5. Close-up
Subtask 71-51-43-860-061-A ** ON A/C NOT FOR ALL
A. Do the EIS stop procedure (Ref. AMM TASK 31-60-00-860-002)
Subtask 71-51-43-862-052-A ** ON A/C NOT FOR ALL
B. De-energize the aircraft circuits (Ref. AMM TASK 24-41-00-862-002)
Subtask 71-51-43-869-052-A ** ON A/C NOT FOR ALL
C. Depressurize the pneumatic system.
Subtask 71-51-43-410-055-A ** ON A/C NOT FOR ALL
D. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Close the fan cowl doors: (Ref. AMM TASK 71-13-00-410-040)
     (a) FOR [1000EM1] (ENGINE-1)
437AL 438AR
     (b) FOR [1000EM2] (ENGINE-2)
447AL 448AR
   (3) Remove the access platform(s).
   (4) Remove the WARNING NOTICE(S).