W DOC AIRBUS | AMM A320F

Special Detailed Inspection of Frame 42 Upper Splicing at Y0


TASK 57-10-00-280-803-A
Special Detailed Inspection of Frame 42 Upper Splicing at Y0


WARNING: BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
ZONE: 240
1. Reason for the Job
Refer to the MPD TASK: 571205-01
SPECIAL DETAILED INSPECTION (HFEC) OF FRAME 42 UPPER SPLICING AT Y0.
NOTE: The effectivity of this task is "ALL". To know if this task is applicable to your aircraft, refer to the MPD task applicability.
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
1
SCRAPER - NON METALLIC
 B. Consumable Materials
REFERENCE
DESIGNATION
(Material No.08BAA9)
Non Aqueous Cleaner-General - -
(Material No.14SBA1)
Textile-Lint free Cotton -
 C. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
240
MID PASSENGER COMPARTMENT
 D. Referenced Information
REFERENCE
DESIGNATION
TASK 25-23-41-000-001-A
Removal of the Ceiling Panels
TASK 25-23-41-400-001-A
Installation of the Ceiling Panels
TASK 25-80-00-000-001-A
Removal of the Insulation Blankets
TASK 25-80-00-400-001-A
Installation of the Insulation Blankets
SRM 511100
SRM 512200
SRM 512300
SRM 512400
NTM 571205
TASK 06-41-53-00
FUSELAGE-DESCRIPTION AND OPERATION
3. Job Set-up
Subtask 57-10-00-010-111-A
A. Get Access
   (1) Remove the applicable ceiling panel(s) (Ref. AMM D/O 06-41-53-00) (Ref. AMM TASK 25-23-41-000-001).
   (2) Remove the applicable insulation blanket(s) (Ref. AMM TASK 25-80-00-000-001).
Subtask 57-10-00-110-099-A
B. Preparation of the Inspection Area
   (1) Make sure that the inspection area is sufficiently clean to do a satisfactory inspection of the area.
   (2) If the inspection area is not sufficiently clean, clean it with the Non Aqueous Cleaner-General - - (Material No.08BAA9) and the Textile-Lint free Cotton - (Material No.14SBA1) .
   (3) If sealant or paint is applied on the inspection area:
  • Remove the sealant with the SCRAPER - NON METALLIC.
  • Remove the paint.
4. Procedure
Subtask 57-10-00-280-054-A
A. Inspection
   (1) Do a special detailed inspection of the upper splice of frame 42 at Y0 for damage or discontinuities NTM 571205.
   (2) Refer to the NTM inspection report and do the applicable step:
     (a) Corrosion:
If you find corrosion, refer to the Structural Repair Manual SRM 512200 for the corrosion types, inspection, removal and subsequent corrosion protection.
     (b) Other damage (scratches, cracks, gouges, dents, creases):
If you find this type of damage, refer to the Structural Repair Manual SRM 511100 for the damage types, classification and corrective action.
Subtask 57-10-00-910-057-A
B. Sealant or paint application
   (1) If you removed the sealant and/or paint from the inspection area, apply sealant SRM 512400 or paint SRM 512300 on the inspection area.
5. Close-up
Subtask 57-10-00-410-112-A
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Install the removed insulation blanket(s) (Ref. AMM TASK 25-80-00-400-001).
   (3) Install the removed ceiling panel(s) (Ref. AMM TASK 25-23-41-400-001).
[Rev.10 from 2021] 2026.04.02 06:30:29 UTC