W DOC AIRBUS | AMM A320F

Installation of the Retainer/Gasket Assembly


TASK 56-12-11-400-004-A
Installation of the Retainer/Gasket Assembly


ZONE: 211
ZONE: 212
1. Reason for the Job
This procedure is applicable:
  • to the acrylic windows (GKN (formerly LUCAS/ACT) supplier, P/N NH...)
  • to the glass windows (PPG supplier, P/N NP...).
2. Job Set-up Information
 A. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
211
COCKPIT
212
COCKPIT
 B. Expendable Parts
FIG.ITEM
DESIGNATION
IPC-CSN
2
SEAL
AIPC 56-12-11-01-063
2
SEAL
AIPC 56-12-11-01-064
3
SEAL RETAINING RING
AIPC 56-12-11-01-065
3
SEAL RETAINING RING
AIPC 56-12-11-01-066
1
RETAINER/GASKET
AIPC 56-12-11-01-067
1
RETAINER/GASKET
AIPC 56-12-11-01-069
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 56-12-11-400-002-A
Installation of the Sliding Window Panel
TASK 56-12-11-400-002-A-01
Installation of the Sliding Window Panel
3. Job Set-up
Subtask 56-12-11-860-053-A
A. Make sure that the aircraft is in the same configuration as for the removal task.
4. Procedure
Subtask 56-12-11-420-070-A
A. Installation of the Retainer/Gasket Assembly
   (1) Install the new retainer/gasket assembly on the sliding window panel:
5. Close-up
Subtask 56-12-11-420-071-A