1. Reason for the Job
Self Explanatory
2. Job Set-up Information
 A. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
160
BULK CARGO COMPARTMENT AFT BULKHEAD OF AFT CARGO COMPARTMENT TO AFT BULKHEAD OF BULK CARGO COMPARTMENT
 B. Referenced Information
REFERENCE
DESIGNATION
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 52-30-00-860-001-A
Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump
TASK 52-30-00-860-006-A
Open the Bulk Cargo-Compartment Door
TASK 53-42-17-000-001-A
Removal of the Bulk Cargo-Compartment Floor-Panels
3. Job Set-up
Subtask 53-42-17-861-050-A
A. Aircraft Maintenance Configuration
   (1) Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
Subtask 53-42-17-010-053-A ** ON A/C NOT FOR ALL
B. Get Access
   (1) Open the aft cargo-compartment door (Ref. AMM TASK 52-30-00-860-001).
Subtask 53-42-17-010-053-B ** ON A/C NOT FOR ALL
B. Get Access
   (1) Open the bulk cargo-compartment door (Ref. AMM TASK 52-30-00-860-006).
4. Procedure
Subtask 53-42-17-020-052-A
A. Removal of the Floor Panel Seal
   (1) If necessary, remove the floor panel (1) adjacent to the applicable seal (2) (Ref. AMM TASK 53-42-17-000-001).
   (2) Remove the floor panel seal (2).