W DOC AIRBUS | AMM A320F

Detailed Inspection of Fuselage Internal Structure, between Cabin Floor Panels and Cargo Compartment Floor, including Cabin Floor Structure, from FR 47 to FR 65


TASK 53-41-00-210-825-A
Detailed Inspection of Fuselage Internal Structure, between Cabin Floor Panels and Cargo Compartment Floor, including Cabin Floor Structure, from FR 47 to FR 65


WARNING: BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
ZONE: 151
ZONE: 152
ZONE: 161
ZONE: 162
1. Reason for the Job
Refer to the MPD TASK: 534120-01
DETAILED INSPECTION OF FUSELAGE INTERNAL STRUCTURE, BETWEEN CABIN FLOOR PANELS AND CARGO COMPARTMENT FLOOR, INCLUDING CABIN FLOOR STRUCTURE, FROM FR 47 TO FR 65
2. Job Set-up Information
 A. Consumable Materials
REFERENCE
DESIGNATION
(Material No.08BAA9)
Non Aqueous Cleaner-General - -
(Material No.12ABC1)
Corrosion Preventive Compound_Water Displacing Soft Film -
(Material No.14SBA1)
Textile-Lint free Cotton -
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
151
AFT CARGO COMPARTMENT
152
AFT CARGO COMPARTMENT
161
BULK CARGO COMPARTMENT
162
BULK CARGO COMPARTMENT
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 25-55-11-000-001-A
Removal of the Aft Cargo-Compartment Partition at FR47
TASK 25-55-11-000-002-A
Removal of the Ceiling Panels in the Aft Cargo-Compartment - FR47/FR59
TASK 25-55-11-000-003-A
Removal of the Sidewall Panels in the Aft Cargo Compartment - FR47/FR59
TASK 25-55-11-400-001-A
Installation of the Aft Cargo-Compartment Partition at FR47
TASK 25-55-11-400-002-A
Installation of the Ceiling Panels in the Aft Cargo-Compartment - FR47/FR59
TASK 25-55-11-400-003-A
Installation of the Sidewall Panels in the Aft Cargo Compartment - FR47/FR59
TASK 25-55-12-000-001-A
Removal of the Aft Cargo-Compartment Partition at FR65
TASK 25-55-12-000-002-A
Removal of the Ceiling Panels in the Aft Cargo Compartment at FR59/FR65
TASK 25-55-12-000-003-A
Removal of the Sidewall Panels in the Aft Cargo Compartment - FR59/FR65
TASK 25-55-12-400-001-A
Installation of the Aft Cargo-Compartment Partition at FR65
TASK 25-55-12-400-002-A
Installation of the Ceiling Panels in the Aft Cargo Compartment at FR59/FR65
TASK 25-55-12-400-003-A
Installation of the Sidewall Panels in the Aft Cargo Compartment - FR59/FR65
TASK 25-80-00-000-001-A
Removal of the Insulation Blankets
TASK 25-80-00-400-001-A
Installation of the Insulation Blankets
TASK 28-11-27-000-001-A
Removal of the Additional Center Tank (ACT)
TASK 28-11-27-400-001-A
Installation of the Additional Center Tank (ACT)
TASK 51-78-00-916-001-A
Application of Temporary Protection System (TPS)
TASK 52-30-00-860-001-A
Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump
TASK 52-30-00-860-004-A
Close the FWD or Aft Cargo-Compartment Door with the Hand Pump
SRM 511100
SRM 512200
3. Job Set-up
Subtask 53-41-00-010-160-A ** ON A/C NOT FOR ALL Subtask 53-41-00-110-108-A ** ON A/C NOT FOR ALL
B. Preparation of the Inspection Area
   (1) Make sure that the inspection areas is sufficiently clean to do a satisfactory inspection of the area.
   (2) If not, clean the inspection area with Non Aqueous Cleaner-General - - (Material No.08BAA9) and the Textile-Lint free Cotton - (Material No.14SBA1) .
   (3) If there is a TPS layer and if it does not let you do a satisfactory inspection, remove the TPS layer (Ref. AMM TASK 51-78-00-916-001).
4. Procedure
Subtask 53-41-00-210-127-A ** ON A/C NOT FOR ALL
A. Inspection
   (1) Do a detailed inspection of the fuselage internal structure, between cabin floor panels and cargo compartment floor, including cabin floor structure, from FR47 to FR65 for damage or discontinuities.
   (2) Make sure that there is no:
     (a) Corrosion damage:
If you find corrosion, refer to the Structural Repair Manual ( SRM 512200) for the corrosion types, inspection, removal and subsequent corrosion protection.
     (b) Other damage (scratches, cracks, gouges, dents, creases):
If you find this type of damage, refer to the Structural Repair Manual ( SRM 511100) for the damage types, classification and corrective action.
Subtask 53-41-00-916-116-A ** ON A/C NOT FOR ALL
B. Check and Application of the TPS layer
   (1) If the TPS was removed at the "Preparation of the Inspection Area", apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) (Ref. AMM TASK 51-78-00-916-001).
   (2) If the TPS was not removed at the "Preparation of the Inspection Area", do a check of the condition and integrity of the TPS layer (Ref. AMM TASK 51-78-00-916-001).
   (3) If the TPS layer has local damage, remove the damaged TPS layer and apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) (Ref. AMM TASK 51-78-00-916-001).
5. Close-up
Subtask 53-41-00-410-157-A ** ON A/C NOT FOR ALL
A. Close Access
   (1) Install the insulation blankets (Ref. AMM TASK 25-80-00-400-001).
   (2) Install the linings (Ref. AMM TASK 25-55-11-400-001), (Ref. AMM TASK 25-55-12-400-001), (Ref. AMM TASK 25-55-11-400-002), (Ref. AMM TASK 25-55-11-400-003), (Ref. AMM TASK 25-55-12-400-002) and (Ref. AMM TASK 25-55-12-400-003).
   (3) If removed, install the applicable ACT(s) (Ref. AMM TASK 28-11-27-400-001), (Ref. AMM D/O 28-11-27-40), (Ref. AMM D/O 28-11-27-40), (Ref. AMM TASK 28-11-27-400-004).
   (4) Make sure that the work area is clean and clear of tools and other items.
   (5) Close the aft cargo-compartment door (Ref. AMM TASK 52-30-00-860-004).
[Rev.10 from 2021] 2026.04.02 06:29:18 UTC