1. Reason for the Job
Refer to the MPD TASK: 533138-01
DETAILED INSPECTION OF LOWER SKIN OF LONGITUDINAL LAP JOINT AT STRINGER 18 LH AND STRINGER 18 RH, IN RUNOUT AREA AT FR 42, INTERNAL

2. Job Set-up Information
 A. Consumable Materials
REFERENCE
DESIGNATION
(Material No.08BAA9)
Non Aqueous Cleaner-General - -
(Material No.14SBA1)
Textile-Lint free Cotton -
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
241
CENTER PASSENGER COMPARTMENT
242
CENTER PASSENGER COMPARTMENT
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 24-42-00-862-001-A
De-energize the Ground Service Network Supplied from the External Power
TASK 25-23-43-000-001-A
Removal of the Upper Sidewall Panel
TASK 25-23-43-400-001-A
Installation of the Upper Sidewall Panel
TASK 25-80-00-000-001-A
Removal of the Insulation Blankets
TASK 25-80-00-400-001-A
Installation of the Insulation Blankets
SRM 53001102
(for corrective action)
SRM 53001302
(for corrective action)
SRM 53311101
(for corrective action)
3. Job Set-up
Subtask 53-31-00-861-055-A
A. Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
Subtask 53-31-00-010-083-A
B. Get Access
   (1) Remove the necessary upper sidewall panels (Ref. AMM TASK 25-23-43-000-001).
   (2) Remove the necessary insulation blankets (Ref. AMM TASK 25-80-00-000-001).
Subtask 53-31-00-110-072-A
C. Cleaning Procedure
WARNING: BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
   (1) Clean the inspection area with Non Aqueous Cleaner-General - - (Material No.08BAA9) and a Textile-Lint free Cotton - (Material No.14SBA1) , if necessary. Make sure the area is dry before you continue.
4. Procedure
Subtask 53-31-00-210-074-A
A. Detailed Visual Inspection Procedure
   (1) Do a detailed visual inspection of the internal lower skin of the longitudinal lap joint at stringers 18LH and 18RH, in the runout area at FR42, for cracks.
NOTE: If required, for information on allowable damage and repair procedures for cracks, refer to the following ASRM's:

5. Close-up
Subtask 53-31-00-410-081-A
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Install the insulation blankets (Ref. AMM TASK 25-80-00-400-001).
   (3) Install the upper sidewall panels (Ref. AMM TASK 25-23-43-400-001).
Subtask 53-31-00-862-055-A
B. De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).