Installation of the Floor Panel Seal on the Forward Cargo Compartment
TASK 53-22-14-400-802-A
Installation of the Floor Panel Seal on the Forward Cargo Compartment
Self Explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
C. Work Zones and Access Panels
D. Referenced Information
3. Job Set-up
Subtask 53-22-14-860-053-A
Subtask 53-22-14-420-053-A
Subtask 53-22-14-410-053-A
[Rev.10 from 2021]
2026.04.02 06:29:02 UTC
Installation of the Floor Panel Seal on the Forward Cargo Compartment
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
ZONE: 130
1. Reason for the JobSelf Explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | SCRAPER - NON METALLIC |
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.06AAC1) | Polysulfide Sealant-General Purpose Interfay - |
| (Material No.08BAA9) | Non Aqueous Cleaner-General - - |
| (Material No.14SBA1) | Textile-Lint free Cotton - |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 130 | FWD CARGO COMPT AFT BULKHEAD OF AVNCS COMPT TO FWD PRESSURE BULKHEAD OF WING CENTER BOX |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 25-50-00-200-002-A | Visual Check of Cargo Compartment Decompression, Lining, Floor Panels and Pressure Compensation Valve (as far as Visible, if ACT(s) or Sliding Carpet System Installed) |
| TASK 52-30-00-860-001-A | Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
| TASK 52-30-00-860-002-A | Close the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
| TASK 53-22-14-400-001-A | Installation of the Forward Cargo-Compartment Floor-Panels |
| TASK 53-22-14-400-001-A-01 | Installation of the Forward Cargo-Compartment Floor-Panels (Alternative Installation Procedure with the Skyflex Option) |
Subtask 53-22-14-860-053-A
A. Aircraft Maintenance Configuration
(1) Make sure that the ground service network is energized (Ref. AMM TASK 24-42-00-861-001).
(2) Make sure that the forward cargo-compartment door is open (Ref. AMM TASK 52-30-00-860-001).
Subtask 53-22-14-110-051-A (1) Make sure that the ground service network is energized (Ref. AMM TASK 24-42-00-861-001).
(2) Make sure that the forward cargo-compartment door is open (Ref. AMM TASK 52-30-00-860-001).
B. Cleaning Procedure
(1) Remove all the remaining sealant from the floor panel with the SCRAPER - NON METALLIC.
(2) Clean the component interface and the adjacent area with the Non Aqueous Cleaner-General - - (Material No.08BAA9) and the Textile-Lint free Cotton - (Material No.14SBA1) .
(3) Make sure that the parts retained from the removed component are clean and in the correct condition.
(4) Do the inspection of the floor panel (Ref. AMM TASK 25-50-00-200-002).
4. Procedure(1) Remove all the remaining sealant from the floor panel with the SCRAPER - NON METALLIC.
(2) Clean the component interface and the adjacent area with the Non Aqueous Cleaner-General - - (Material No.08BAA9) and the Textile-Lint free Cotton - (Material No.14SBA1) .
(3) Make sure that the parts retained from the removed component are clean and in the correct condition.
(4) Do the inspection of the floor panel (Ref. AMM TASK 25-50-00-200-002).
Subtask 53-22-14-420-053-A
A. Installation of the Floor Panel Seal
Floor Panel Seal of the Forward Cargo Compartment ** ON A/C NOT FOR ALL
Floor Panel Seal of the Forward Cargo Compartment ** ON A/C NOT FOR ALL
Floor Panel Seal of the Forward Cargo Compartment ** ON A/C NOT FOR ALL
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Cut the seal (2) to the necessary length and as a continuous piece.
(3) Clean the seal (2) to remove dust and dirt.
(4) Put the seal (2) in position.
(5) Make sure that the seal (2) is flush with the surfaces of the adjacent floor panel (1).
(6) Apply Polysulfide Sealant-General Purpose Interfay - (Material No.06AAC1) on the holes at the end of the seal (2) at a minimum distance of 40 mm (1.5748 in.) from the edge of the seal.
(7) Make sure that all the seal intersections are flush with each other.
(8) If you removed the adjacent floor panel (1), install it (Ref. AMM TASK 53-22-14-400-001).
5. Close-up
Floor Panel Seal of the Forward Cargo Compartment ** ON A/C NOT FOR ALL
Floor Panel Seal of the Forward Cargo Compartment ** ON A/C NOT FOR ALL
Floor Panel Seal of the Forward Cargo Compartment ** ON A/C NOT FOR ALL (2) Cut the seal (2) to the necessary length and as a continuous piece.
(3) Clean the seal (2) to remove dust and dirt.
(4) Put the seal (2) in position.
(5) Make sure that the seal (2) is flush with the surfaces of the adjacent floor panel (1).
(6) Apply Polysulfide Sealant-General Purpose Interfay - (Material No.06AAC1) on the holes at the end of the seal (2) at a minimum distance of 40 mm (1.5748 in.) from the edge of the seal.
(7) Make sure that all the seal intersections are flush with each other.
(8) If you removed the adjacent floor panel (1), install it (Ref. AMM TASK 53-22-14-400-001).
Subtask 53-22-14-410-053-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the forward cargo-compartment door (Ref. AMM TASK 52-30-00-860-002).
(3) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
Subtask 53-22-14-862-050-A (1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the forward cargo-compartment door (Ref. AMM TASK 52-30-00-860-002).
(3) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
B. Aircraft Maintenance Configuration
(1) De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).
(1) De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).