General Visual Inspection of Cabin Floor Structure, excluding Areas below Galleys and Toilets, between FR 21 and FR 24
TASK 53-11-00-210-805-A
General Visual Inspection of Cabin Floor Structure, excluding Areas below Galleys and Toilets, between FR 21 and FR 24
Refer to the MPD TASK: 531190-01
GENERAL VISUAL INSPECTION OF CABIN FLOOR STRUCTURE, EXCLUDING AREAS BELOW GALLEYS AND TOILETS, BETWEEN FR 21 AND FR 24
A. Consumable Materials
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 53-11-00-010-096-A
Subtask 53-11-00-210-085-A
Subtask 53-11-00-410-096-A
[Rev.10 from 2021]
2026.04.02 06:28:44 UTC
General Visual Inspection of Cabin Floor Structure, excluding Areas below Galleys and Toilets, between FR 21 and FR 24
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
1. Reason for the JobRefer to the MPD TASK: 531190-01
GENERAL VISUAL INSPECTION OF CABIN FLOOR STRUCTURE, EXCLUDING AREAS BELOW GALLEYS AND TOILETS, BETWEEN FR 21 AND FR 24
NOTE: The effectivity of this task is "ALL". To know if this task is applicable to your aircraft, refer to the MPD task applicability.
The information on weight variant groups is given in the MPD and SRM introductions.
2. Job Set-up InformationThe information on weight variant groups is given in the MPD and SRM introductions.
A. Consumable Materials
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.08BAA9) | Non Aqueous Cleaner-General - - |
| (Material No.12ABC1) | Corrosion Preventive Compound_Water Displacing Soft Film - |
| (Material No.14SBA1) | Textile-Lint free Cotton - |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 221 | FWD CAB UTILITY AREA |
| 222 | FWD CAB UTILITY AREA |
| 231 | FWD PASSENGER COMPARTMENT |
| 232 | FWD PASSENGER COMPARTMENT |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 25-80-00-000-001-A | Removal of the Insulation Blankets |
| TASK 25-80-00-400-001-A | Installation of the Insulation Blankets |
| TASK 51-78-00-916-001-A | Application of Temporary Protection System (TPS) |
| TASK 53-12-12-000-001-A | Removal of the Cabin Floor Panels from FR12 thru FR24 |
| TASK 53-12-12-400-001-A | Installation of the Cabin Floor Panels from FR12 thru FR24 |
| SRM 511100 | (for corrective action) |
| SRM 512200 | (for corrective action) |
Subtask 53-11-00-010-096-A
A. Get Access
(1) Remove the necessary floor panels between FR21 and FR24 to get access to the inspection areas (Ref. AMM TASK 53-12-12-000-001).
(2) Remove the necessary insulation blankets between FR21 and FR24 to get access to the inspection areas (Ref. AMM TASK 25-80-00-000-001).
Subtask 53-11-00-110-111-A (1) Remove the necessary floor panels between FR21 and FR24 to get access to the inspection areas (Ref. AMM TASK 53-12-12-000-001).
(2) Remove the necessary insulation blankets between FR21 and FR24 to get access to the inspection areas (Ref. AMM TASK 25-80-00-000-001).
B. Preparation of the Inspection Area
(1) Make sure that the inspection area is sufficiently clean to do a satisfactory inspection of the area.
(2) If it is not sufficiently clean, clean the inspection area with Non Aqueous Cleaner-General - - (Material No.08BAA9) and a Textile-Lint free Cotton - (Material No.14SBA1) .
(3) If there is a Temporary Protection System (TPS) layer and if it does not let you do a satisfactory inspection, remove the TPS layer (Ref. AMM TASK 51-78-00-916-001).
4. Procedure(1) Make sure that the inspection area is sufficiently clean to do a satisfactory inspection of the area.
(2) If it is not sufficiently clean, clean the inspection area with Non Aqueous Cleaner-General - - (Material No.08BAA9) and a Textile-Lint free Cotton - (Material No.14SBA1) .
(3) If there is a Temporary Protection System (TPS) layer and if it does not let you do a satisfactory inspection, remove the TPS layer (Ref. AMM TASK 51-78-00-916-001).
Subtask 53-11-00-210-085-A
A. Inspection
(1) Do a general visual inspection of the cabin floor structure between FR21 and FR24 for damage or discontinuities. This inspection does not include the areas below the galleys and the toilets.
(2) Make sure that there is no:
(a) Corrosion damage:
Subtask 53-11-00-916-068-A (1) Do a general visual inspection of the cabin floor structure between FR21 and FR24 for damage or discontinuities. This inspection does not include the areas below the galleys and the toilets.
(2) Make sure that there is no:
(a) Corrosion damage:
- If you find corrosion, refer to the Structural Repair Manual ( SRM 512200) for the corrosion types, inspection, removal and subsequent corrosion protection.
- If you find this type of damage, refer to the Structural Repair Manual ( SRM 511100) for the damage types, classification and corrective action.
B. Check and Application of the TPS Layer
(1) If the TPS was removed at the "Preparation of the Inspection Area", apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) (Ref. AMM TASK 51-78-00-916-001).
(2) If the TPS was not removed at the "Preparation of the Inspection Area", do a check of the condition and integrity of the TPS layer (Ref. AMM TASK 51-78-00-916-001).
(3) If the TPS layer has local damage, remove the damaged TPS layer and apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) (Ref. AMM TASK 51-78-00-916-001).
5. Close-up(1) If the TPS was removed at the "Preparation of the Inspection Area", apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) (Ref. AMM TASK 51-78-00-916-001).
(2) If the TPS was not removed at the "Preparation of the Inspection Area", do a check of the condition and integrity of the TPS layer (Ref. AMM TASK 51-78-00-916-001).
(3) If the TPS layer has local damage, remove the damaged TPS layer and apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) (Ref. AMM TASK 51-78-00-916-001).
NOTE: If, after the check of the condition and integrity, the TPS layer is in the correct condition Airbus recommends that you apply a new layer as a spray on the existing layer. This is to make sure that the TPS layer continues to give satisfactory corrosion protection.
Subtask 53-11-00-410-096-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the necessary insulation blankets between FR21 and FR24 (Ref. AMM TASK 25-80-00-400-001).
(3) Install the necessary floor panels between FR21 and FR24 (Ref. AMM TASK 53-12-12-400-001).
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the necessary insulation blankets between FR21 and FR24 (Ref. AMM TASK 25-80-00-400-001).
(3) Install the necessary floor panels between FR21 and FR24 (Ref. AMM TASK 53-12-12-400-001).
Cabin Floor Structure between FR21 and FR24