General Visual Inspection of Fuselage Internal Structure, below Galley and Toilet, between FR12 and FR15 and between Stringer 23 LH and Stringer 23 RH...
TASK 53-11-00-210-804-A
General Visual Inspection of Fuselage Internal Structure, below Galley and Toilet, between FR12 and FR15 and between Stringer 23 LH and Stringer 23 RH...
Refer to the MPD TASK: 531169-01
GENERAL VISUAL INSPECTION OF FUSELAGE INTERNAL STRUCTURE, BELOW GALLEY AND TOILET, BETWEEN FR 12 AND FR 15 AND BETWEEN STRINGER 23 LH AND STRINGER 23 RH, EXCLUDING STRUCTURE FROM FR 12 TO FR 14 UNDER HEAT EXCHANGER PANELS.
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
C. Work Zones and Access Panels
D. Referenced Information
3. Job Set-up
Subtask 53-11-00-010-095-A
Subtask 53-11-00-210-084-A
Subtask 53-11-00-410-095-A
[Rev.10 from 2021]
2026.04.02 06:28:43 UTC
General Visual Inspection of Fuselage Internal Structure, below Galley and Toilet, between FR12 and FR15 and between Stringer 23 LH and Stringer 23 RH...
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
1. Reason for the JobRefer to the MPD TASK: 531169-01
GENERAL VISUAL INSPECTION OF FUSELAGE INTERNAL STRUCTURE, BELOW GALLEY AND TOILET, BETWEEN FR 12 AND FR 15 AND BETWEEN STRINGER 23 LH AND STRINGER 23 RH, EXCLUDING STRUCTURE FROM FR 12 TO FR 14 UNDER HEAT EXCHANGER PANELS.
NOTE: The effectivity of this task is "ALL". To know if this task is applicable to your aircraft, refer to the MPD task applicability.
The information on weight variant groups is given in the MPD and SRM introductions.
2. Job Set-up InformationThe information on weight variant groups is given in the MPD and SRM introductions.
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE |
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.08BAA9) | Non Aqueous Cleaner-General - - |
| (Material No.12ABC1) | Corrosion Preventive Compound_Water Displacing Soft Film - |
| (Material No.14SBA1) | Textile-Lint free Cotton - |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 123 | NOSE GEAR WELL |
| 124 | NOSE GEAR WELL |
| 125 | LATERAL AVIONIC COMPARTMENT |
| 126 | LATERAL AVIONIC COMPARTMENT |
| 812, 822 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 25-80-00-000-001-A | Removal of the Insulation Blankets |
| TASK 25-80-00-400-001-A | Installation of the Insulation Blankets |
| TASK 51-78-00-916-001-A | Application of Temporary Protection System (TPS) |
| TASK 52-41-00-010-002-A | Open the Avionics Compartment Doors for Access |
| TASK 52-41-00-410-002-A | Close the Avionics Compartment Doors after Access |
| SRM 511100 | (for corrective action) |
| SRM 512200 | (for corrective action) |
Subtask 53-11-00-010-095-A
A. Get Access
(1) Put an ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE at zone 123 (124) and/or 125 (126).
(2) Open the lateral avionics-compartment doors 812 ( 822) (Ref. AMM TASK 52-41-00-010-002).
(3) Remove the necessary insulation blankets between FR12 and FR15 to get access to the inspection areas (Ref. AMM TASK 25-80-00-000-001).
Subtask 53-11-00-110-110-A (1) Put an ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE at zone 123 (124) and/or 125 (126).
(2) Open the lateral avionics-compartment doors 812 ( 822) (Ref. AMM TASK 52-41-00-010-002).
(3) Remove the necessary insulation blankets between FR12 and FR15 to get access to the inspection areas (Ref. AMM TASK 25-80-00-000-001).
B. Preparation of the Inspection Area
(1) Make sure that the inspection area is sufficiently clean to do a satisfactory inspection of the area.
(2) If it is not sufficiently clean, clean the inspection area with Non Aqueous Cleaner-General - - (Material No.08BAA9) and a Textile-Lint free Cotton - (Material No.14SBA1) .
(3) If there is a Temporary Protection System (TPS) layer and if it does not let you do a satisfactory inspection, remove the TPS layer (Ref. AMM TASK 51-78-00-916-001).
4. Procedure(1) Make sure that the inspection area is sufficiently clean to do a satisfactory inspection of the area.
(2) If it is not sufficiently clean, clean the inspection area with Non Aqueous Cleaner-General - - (Material No.08BAA9) and a Textile-Lint free Cotton - (Material No.14SBA1) .
(3) If there is a Temporary Protection System (TPS) layer and if it does not let you do a satisfactory inspection, remove the TPS layer (Ref. AMM TASK 51-78-00-916-001).
Subtask 53-11-00-210-084-A
A. Inspection
(1) Do a general visual inspection of the fuselage internal structure between FR12 and FR15 and stringer 23 on the left and right sides below galley and toilet for damage and discontinuities. This inspection does not include the areas below the heat exchanger panels between structure FR12 to FR14.
(2) Make sure that there is no:
(a) Corrosion damage:
Subtask 53-11-00-916-067-A (1) Do a general visual inspection of the fuselage internal structure between FR12 and FR15 and stringer 23 on the left and right sides below galley and toilet for damage and discontinuities. This inspection does not include the areas below the heat exchanger panels between structure FR12 to FR14.
(2) Make sure that there is no:
(a) Corrosion damage:
- If you find corrosion, refer to the Structural Repair Manual ( SRM 512200) for the corrosion types, inspection, removal and subsequent corrosion protection.
- If you find this type of damage, refer to the Structural Repair Manual ( SRM 511100) for the damage types, classification and corrective action.
B. Check and Application of the TPS Layer
(1) If the TPS was removed at the "Preparation of the Inspection Area", apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) (Ref. AMM TASK 51-78-00-916-001).
(2) If the TPS was not removed at the "Preparation of the Inspection Area", do a check of the condition and integrity of the TPS layer (Ref. AMM TASK 51-78-00-916-001).
If the TPS layer has local damage, remove the damaged TPS layer and apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) (Ref. AMM TASK 51-78-00-916-001).
5. Close-up(1) If the TPS was removed at the "Preparation of the Inspection Area", apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) (Ref. AMM TASK 51-78-00-916-001).
(2) If the TPS was not removed at the "Preparation of the Inspection Area", do a check of the condition and integrity of the TPS layer (Ref. AMM TASK 51-78-00-916-001).
If the TPS layer has local damage, remove the damaged TPS layer and apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) (Ref. AMM TASK 51-78-00-916-001).
NOTE: If, after the check of the condition and integrity, the TPS layer is in the correct condition Airbus recommends that you apply a new layer as a spray on the existing layer. This is to make sure that the TPS layer continues to given, satisfactory corrosion protection.
Subtask 53-11-00-410-095-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the necessary insulation blankets between FR12 and FR15 (Ref. AMM TASK 25-80-00-400-001).
(3) Close the lateral avionics-compartment doors 812 ( 822) (Ref. AMM TASK 52-41-00-410-002).
(4) Remove the access platform(s).
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the necessary insulation blankets between FR12 and FR15 (Ref. AMM TASK 25-80-00-400-001).
(3) Close the lateral avionics-compartment doors 812 ( 822) (Ref. AMM TASK 52-41-00-410-002).
(4) Remove the access platform(s).
Temporary Protection Location Zone 123 (124) and 125 (126)