W DOC AIRBUS | AMM A320F

Detailed Inspection of MLG Door, Forward and Aft Fittings, LH/RH


TASK 52-81-00-200-001-A
Detailed Inspection of MLG Door, Forward and Aft Fittings, LH/RH


WARNING: PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU START A TASK ON OR NEAR:
  • THE FLIGHT CONTROLS
  • THE FLIGHT CONTROL SURFACES
  • THE LANDING GEAR AND THE RELATED DOORS
  • COMPONENTS THAT MOVE.
MOVEMENT OF COMPONENTS CAN KILL OR CAUSE INJURY TO PERSONS AND/OR CAN CAUSE DAMAGE TO THE EQUIPMENT.
WARNING: BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
ZONE: 734
ZONE: 744
1. Reason for the Job
Refer to the MPD TASK: 528101-01
DETAILED INSPECTION OF MLG DOOR, FORWARD AND AFT FITTINGS, LH/RH
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE
No specific
AR
SAFETY BARRIER(S)
No specific
AR
WARNING NOTICE(S)
 B. Consumable Materials
REFERENCE
DESIGNATION
(Material No.08BAA9)
Non Aqueous Cleaner-General - -
(Material No.12ABB1)
Corrosion Preventive Compound-Water Displacing Hard Film -
(Material No.12ABC1)
Corrosion Preventive Compound_Water Displacing Soft Film -
(Material No.14SBA1)
Textile-Lint free Cotton -
 C. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
734
MAIN DOOR
744
MAIN DOOR
 D. Referenced Information
REFERENCE
DESIGNATION
TASK 32-00-00-481-001-A
Installation of the Safety Devices on the Landing Gears
TASK 32-00-00-481-002-A
Installation of the Safety Devices on the Landing Gear Doors
TASK 32-12-00-010-001-A
Open the Main Gear Doors for Access
TASK 32-12-00-410-001-A
Close the Main Gear Doors after Access
TASK 51-78-00-916-001-A
Application of Temporary Protection System (TPS)
SRM 511100
SRM 512200
3. Job Set-up
Subtask 52-81-00-941-050-A
A. Safety Precautions
WARNING: MAKE SURE THAT THE GROUND SAFETY-LOCKS ARE IN POSITION ON THE LANDING GEAR. THIS WILL PREVENT UNWANTED MOVEMENT OF THE LANDING GEAR, AND THUS POSSIBLE INJURY TO PERSONS AND DAMAGE TO THE AIRCRAFT AND/OR EQUIPMENT.
   (1) Make sure that a ground lock sleeve is installed on the applicable MLG lockstay actuator (Ref. AMM TASK 32-00-00-481-001).
   (2) Put WARNING NOTICE(S) in position to tell persons not to operate the MLG and the MLG doors.
   (3) As necessary, use the applicable SAFETY BARRIERS, specified by the operator's instructions and your local regulations.
Subtask 52-81-00-010-050-A
B. Get Access
   (1) Open the MLG doors (Ref. AMM TASK 32-12-00-010-001).
   (2) Make sure that the 460005835 SLEEVE - GROUND LOCK is on the MLG door actuators (Ref. AMM TASK 32-00-00-481-002).
   (3) Put the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position below the inspection area.
Subtask 52-81-00-110-050-A
C. Preparation of the Inspection Area
   (1) Make sure that the inspection area is sufficiently clean to do a satisfactory inspection of the area.
   (2) If not, clean the inspection area with Non Aqueous Cleaner-General - - (Material No.08BAA9) and a Textile-Lint free Cotton - (Material No.14SBA1) .
   (3) If there is a TPS layer and if it does not let you do a satisfactory inspection, remove the TPS layer (Ref. AMM TASK 51-78-00-916-001).
4. Procedure
Subtask 52-81-00-210-050-A
A. Inspection
   (1) Do a detailed inspection of the MLG door, forward and aft fittings on the LH and RH sides, for damages or discontinuities.
   (2) Make sure that there is no:
     (a) Corrosion damage:
If you find corrosion, refer to the Structural Repair Manual ( SRM 512200) for corrosion types, inspection, removal and subsequent corrosion protection.
     (b) Other damage (cracks, scratches, gouges, dents, creases):
If you find this type of damage, refer to the Structural Repair Manual ( SRM 511100) for the damage types, classification and corrective action.
5. Close-up
Subtask 52-81-00-916-050-A
A. Check and Application of the TPS Layer
CAUTION: DO NOT APPLY TEMPORARY PROTECTION SYSTEM (TPS) TYPE 3 ON THE MOVABLE COMPONENTS. USE ONLY TPS TYPE 1 GRADE 2. IF YOU DO NOT OBEY THIS INSTRUCTION, THE MECHANISMS WILL NOT OPERATE CORRECTLY.
   (1) If the TPS layer was removed at the "Preparation of the Inspection Area", apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) or Corrosion Preventive Compound-Water Displacing Hard Film - (Material No.12ABB1) (Ref. AMM TASK 51-78-00-916-001).
   (2) If the TPS layer was not removed at the "Preparation of the Inspection Area", do a check of the condition and integrity of the TPS layer (Ref. AMM TASK 51-78-00-916-001).
   (3) If the TPS layer has local damage, remove the damaged TPS layer and apply a new layer of Corrosion Preventive Compound_Water Displacing Soft Film - (Material No.12ABC1) or Corrosion Preventive Compound-Water Displacing Hard Film - (Material No.12ABB1) (Ref. AMM TASK 51-78-00-916-001).
NOTE: If, after the check of the condition and integrity, the TPS layer is in the correct condition, Airbus recommends that you apply a new layer as a spray on the existing layer. This is to make sure that the TPS layer continues to give satisfactory corrosion protection.
Subtask 52-81-00-410-050-A
B. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Remove the access platform(s).
   (3) Close the MLG doors (Ref. AMM TASK 32-12-00-410-001).
Subtask 52-81-00-942-050-A
C. Remove the Equipment
   (1) Remove the SAFETY BARRIER(S).
   (2) Remove the WARNING NOTICE(S).
   (3) Remove the ground support and maintenance equipment, the special and standard tools and all other items.