Removal of the Latching Shaft Assembly
TASK 52-32-21-000-012-A
Removal of the Latching Shaft Assembly
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 52-32-21-010-063-A ** ON A/C NOT FOR ALL
Subtask 52-32-21-020-069-A ** ON A/C NOT FOR ALL
(1) Make match marks on the components that you disconnect/remove to record their connections/positions. This is important for the subsequent installation procedure.
(2) Disconnect the shaft levers (175) from the link rods (181):
(a) Turn the latching shaft (171) to remove the bolts (178) through the mounting holes of the door frame.
(b) Remove and discard the cotter pins (172).
(c) Remove the nuts (173) and (191), the washers (179) and the bolts (178) from the shaft levers (175).
(d) Remove the eye-end of the link rods (181) from the fork-end of the shaft levers (175).
(e) Remove the bushes (180) and (182) from the shaft levers (175).
(3) Disconnect the link lever (40) from the connection rod (44):
(a) Turn the latching shaft (171) to remove the bolt (45) through the mounting holes of the door frame.
(b) Remove and discard the cotter pin (41).
(c) Remove the nut (42), the washers (43) and the bolt (45) from the connection rod (44).
(d) Remove the fork-end of the connection rod (44) from the link lever (40).
(4) Remove the latching shaft (171) from the cargo door:
(a) Remove the nuts (177), the sleeves (176) and the tapered pins (174) from the shaft levers (175).
(b) Remove the nut (185), the sleeve (184) and the tapered pin (183) from the link lever (40).
(c) Remove the nuts (188), the sleeves (189) and the tapered pins (187) from the interlock cam (186) and the control lever (190).
(d) Remove the latching shaft (171) slowly through the lateral cutout of the cargo door.
(e) Collect the shaft levers (175), the control lever (190), the link lever (40) and the interlock cam (186) during this movement.
(5) If necessary, remove the target from the control lever (190) (Ref. AMM TASK 52-35-13-000-002).
[Rev.10 from 2021]
2026.04.02 06:28:03 UTC
Removal of the Latching Shaft Assembly
ZONE: 826
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE |
| No specific | AR | SAFETY CLIP - CIRCUIT BREAKER |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 826 | AFT CARGO COMPARTMENT DOOR |
| 826AR | |
| 826BR, 826CR |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 52-30-00-860-001-A | Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
| TASK 52-32-33-000-001-A | Removal of the Door Fairings and Access Panels |
| TASK 52-35-13-000-002-A | Removal of the Proximity Switches |
Subtask 52-32-21-010-063-A ** ON A/C NOT FOR ALL
A. Get Access
Access Panel and Protection Plugs ** ON A/C NOT FOR ALL
Access Panel and Protection Plugs ** ON A/C NOT FOR ALL
(1) Open the AFT cargo-compartment door (referred to as cargo door) and safety it with the actuator safety locks (Ref. AMM TASK 52-30-00-860-001).
(2) Put the ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE in position at the cargo door.
(3) Remove the access panel 826AR from the cargo door.
(4) Remove the protection plug (6) from the lateral cutout of the edge member as required.
Subtask 52-32-21-010-063-C ** ON A/C NOT FOR ALL
Access Panel and Protection Plugs ** ON A/C NOT FOR ALL
Access Panel and Protection Plugs ** ON A/C NOT FOR ALL (2) Put the ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE in position at the cargo door.
(3) Remove the access panel 826AR from the cargo door.
(4) Remove the protection plug (6) from the lateral cutout of the edge member as required.
A. Get Access
Access Panel and Protection Plugs ** ON A/C NOT FOR ALL
Access Panel and Protection Plugs ** ON A/C NOT FOR ALL
(1) Open the AFT cargo-compartment door (referred to as cargo door) and safety it with the actuator safety locks (Ref. AMM TASK 52-30-00-860-001).
(2) Put the ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE in position at the cargo door.
(3) Remove the door fairing 826CR and the access panels 826AR and 826BR from the cargo door (Ref. AMM TASK 52-32-33-000-001).
(4) Remove the protection plugs (9) or (12) from the lateral cutout of the edge member as necessary.
Subtask 52-32-21-865-080-A
Access Panel and Protection Plugs ** ON A/C NOT FOR ALL
Access Panel and Protection Plugs ** ON A/C NOT FOR ALL (2) Put the ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE in position at the cargo door.
(3) Remove the door fairing 826CR and the access panels 826AR and 826BR from the cargo door (Ref. AMM TASK 52-32-33-000-001).
(4) Remove the protection plugs (9) or (12) from the lateral cutout of the edge member as necessary.
B. Open, safety and tag this(these) circuit breaker(s):
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/HYD POWER/Y | 3803GX | N30 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/HYD POWER/Y | 3803GX | N31 |
| ** ON A/C ALL | |||
| 122VU | DOORS/CARGO | 1MJ | T12 |
| 123VU | Y HYD/ELEC/PUMP | 3802GX | AB06 |
| 123VU | Y HYD/ELEC/ELEC PUMP/NORM | 3801GX | AB03 |
Subtask 52-32-21-020-069-A ** ON A/C NOT FOR ALL
A. Removal of the Latching Shaft
Latching Shaft Assembly ** ON A/C NOT FOR ALL
Latching Shaft Assembly ** ON A/C NOT FOR ALL
Latching Shaft Assembly ** ON A/C NOT FOR ALL
Latching Shaft Assembly ** ON A/C NOT FOR ALL
(a) Turn the latching shaft (171) so that you can remove the bolts (178) thru the mounting holes of the door frame.
(b) Remove and discard the cotter pin (172) from the nut (173).
(c) Remove the nut (173), the washers (179), the bushes (180) and (182) and the bolt (178) from the shaft levers (175).
(d) Remove the eye-end of the link rod (181) from the fork- end of the shaft lever (175).
(2) Disconnect the link lever (40) from the connection rod (44) follows:
(a) Turn the latching shaft (171) so that you can remove the bolts (45) thru the mounting holes of the door frame.
(b) Remove and discard the cotter pin (41) from the nut (42).
(c) Remove the nut (42), the washers (43) and the bolt (45) from the link rod (44).
(d) Remove the fork-end of the link rod (44) from the link lever (40).
(3) Remove the locking shaft (171) from the cargo door as follows:
(a) Remove the nuts (177), the sleeves (176) and the tapered pins (174) from each shaft levers (175).
(b) Remove the nuts (185), the sleeves (184) and the tapered pins (183) from the the link lever (40).
(c) Remove the nuts (188), the sleeves (189) and the tapered pins (187) from the interlock cam (186).
(d) Remove the nut (192), the sleeve (193) and the tapered pin (191) from the the control lever (190).
(e) Remove the locking shaft (171) slowly through the lateral cutout of the cargo door.
(5) If necessary, remove the target from the control lever (190) (Ref. AMM TASK 52-35-13-000-002).
Subtask 52-32-21-020-069-C ** ON A/C NOT FOR ALL
Latching Shaft Assembly ** ON A/C NOT FOR ALL
Latching Shaft Assembly ** ON A/C NOT FOR ALL
Latching Shaft Assembly ** ON A/C NOT FOR ALL
Latching Shaft Assembly ** ON A/C NOT FOR ALL NOTE: Identify the installation position of the link lever, shaft levers, the control lever and the interlock cam with a mark.
(1) Disconnect the shaft lever (175) from the link rod (181) of each latching unit as follows: (a) Turn the latching shaft (171) so that you can remove the bolts (178) thru the mounting holes of the door frame.
(b) Remove and discard the cotter pin (172) from the nut (173).
(c) Remove the nut (173), the washers (179), the bushes (180) and (182) and the bolt (178) from the shaft levers (175).
(d) Remove the eye-end of the link rod (181) from the fork- end of the shaft lever (175).
(2) Disconnect the link lever (40) from the connection rod (44) follows:
(a) Turn the latching shaft (171) so that you can remove the bolts (45) thru the mounting holes of the door frame.
(b) Remove and discard the cotter pin (41) from the nut (42).
(c) Remove the nut (42), the washers (43) and the bolt (45) from the link rod (44).
(d) Remove the fork-end of the link rod (44) from the link lever (40).
(3) Remove the locking shaft (171) from the cargo door as follows:
(a) Remove the nuts (177), the sleeves (176) and the tapered pins (174) from each shaft levers (175).
(b) Remove the nuts (185), the sleeves (184) and the tapered pins (183) from the the link lever (40).
(c) Remove the nuts (188), the sleeves (189) and the tapered pins (187) from the interlock cam (186).
(d) Remove the nut (192), the sleeve (193) and the tapered pin (191) from the the control lever (190).
(e) Remove the locking shaft (171) slowly through the lateral cutout of the cargo door.
NOTE: Collect the shaft levers (175), the control lever (190), the link lever (40) and the interlock cam (186) during this movement.
(4) Remove the shaft levers (175),the control lever (190) and the interlock cam (186) while you remove the locking shaft (171) from the cargo door. (5) If necessary, remove the target from the control lever (190) (Ref. AMM TASK 52-35-13-000-002).
WARNING:
USE PROTECTIVE GOGGLES WHEN YOU REMOVE OR INSTALL A COTTER PIN. EACH TIME YOU REMOVE A COTTER PIN DURING THE TASK, DISCARD IT IMMEDIATELY. A LOOSE COTTER PIN CAN CUT YOU OR MAKE YOU BLIND.
A. Removal of the Latching Shaft(1) Make match marks on the components that you disconnect/remove to record their connections/positions. This is important for the subsequent installation procedure.
(2) Disconnect the shaft levers (175) from the link rods (181):
(a) Turn the latching shaft (171) to remove the bolts (178) through the mounting holes of the door frame.
(b) Remove and discard the cotter pins (172).
(c) Remove the nuts (173) and (191), the washers (179) and the bolts (178) from the shaft levers (175).
(d) Remove the eye-end of the link rods (181) from the fork-end of the shaft levers (175).
(e) Remove the bushes (180) and (182) from the shaft levers (175).
(3) Disconnect the link lever (40) from the connection rod (44):
(a) Turn the latching shaft (171) to remove the bolt (45) through the mounting holes of the door frame.
(b) Remove and discard the cotter pin (41).
(c) Remove the nut (42), the washers (43) and the bolt (45) from the connection rod (44).
(d) Remove the fork-end of the connection rod (44) from the link lever (40).
(4) Remove the latching shaft (171) from the cargo door:
(a) Remove the nuts (177), the sleeves (176) and the tapered pins (174) from the shaft levers (175).
(b) Remove the nut (185), the sleeve (184) and the tapered pin (183) from the link lever (40).
(c) Remove the nuts (188), the sleeves (189) and the tapered pins (187) from the interlock cam (186) and the control lever (190).
(d) Remove the latching shaft (171) slowly through the lateral cutout of the cargo door.
(e) Collect the shaft levers (175), the control lever (190), the link lever (40) and the interlock cam (186) during this movement.
(5) If necessary, remove the target from the control lever (190) (Ref. AMM TASK 52-35-13-000-002).