3. Job Set-up
Subtask 47-20-00-860-056-A ** ON A/C NOT FOR ALL
Subtask 47-20-00-420-051-A ** ON A/C NOT FOR ALL
Subtask 47-20-00-410-053-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.02 06:26:18 UTC
Reactivation of the HP Air-Ground Connector Door
WARNING:
PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU START A TASK ON OR NEAR:
- THE FLIGHT CONTROLS
- THE FLIGHT CONTROL SURFACES
- THE LANDING GEAR AND THE RELATED DOORS
- COMPONENTS THAT MOVE.
WARNING:
YOU MUST PUT ON AND ATTACH A SAFETY HARNESS BEFORE YOU START WORK:
1. Reason for the Job- ON THE THS OR IN THE REAR FUSELAGE
- ON TOP OF THE WINGS OR PYLONS.
CDL 52-20
Access Door to HP Air Ground Connector 191 DB
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 2M (6 FT) |
| No specific | AR | SAFETY CLIP - CIRCUIT BREAKER |
| No specific | Torque wrench: range to between 0.308 and 0.252 m.daN (27.26 and 22.30 lbf.in ) ![]() |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 52-42-16-400-001-A | Installation of the HP Air-Ground Connector Door |
| TASK 53-35-13-000-002-A | Removal of the Quick-Release Access Panels from the Belly Fairing Structure |
| TASK 53-35-13-400-002-A | Installation of the Quick-Release Access Panels on the Belly Fairing Structure |
Subtask 47-20-00-860-056-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002)
Subtask 47-20-00-865-056-A ** ON A/C NOT FOR ALL (1) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002)
B. Open, safety and tag this(these) circuit breaker(s):
Subtask 47-20-00-010-053-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | IGGS/CTRL | 7YA | N28 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | IGGS/CTRL | 7YA | P28 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | CSAS / CTRL | 1HW | U17 |
C. Get Access
(1) Put an ACCESS PLATFORM 2M (6 FT) in position at zone 191.
(2) Remove the access panel 191BB (Ref. AMM TASK 53-35-13-000-002)
4. Procedure(1) Put an ACCESS PLATFORM 2M (6 FT) in position at zone 191.
(2) Remove the access panel 191BB (Ref. AMM TASK 53-35-13-000-002)
Subtask 47-20-00-420-051-A ** ON A/C NOT FOR ALL
A. Reactivation of the HP Air-Ground Connector Door (191DB)
(2) Make sure that the parts retained from the removed component are clean and in the correct condition.
(3) Install the clamp (2) on the bellow (3).
(4) Install the bellow (3) until the red ink mark on the pipe (1).
(5) Install the clamp (2) on its recorded position.
(6) TORQUE the screw of the clamp (2) to between 0.308 and 0.252 m.daN (27.26 and 22.30 lbf.in )
.
(7) Make sure that the work area is clean and clear of tools and other items.
5. Close-upWARNING:
DO NOT GO INTO THE WORK AREA UNTIL A MINIMUM OF 5 MINUTES AFTER YOU REMOVE THE ACCESS PANEL. LET AIR FLOW THROUGH THE WORK AREA. AIR FROM THIS SYSTEM HAS A LOW OXYGEN CONTENT AND CAN CAUSE INJURY OR DEATH.
(1) Clean the component interfaces and the adjacent area.(2) Make sure that the parts retained from the removed component are clean and in the correct condition.
(3) Install the clamp (2) on the bellow (3).
(4) Install the bellow (3) until the red ink mark on the pipe (1).
(5) Install the clamp (2) on its recorded position.
(6) TORQUE the screw of the clamp (2) to between 0.308 and 0.252 m.daN (27.26 and 22.30 lbf.in )
. (7) Make sure that the work area is clean and clear of tools and other items.
Subtask 47-20-00-410-053-A ** ON A/C NOT FOR ALL
A. Close Access
(1) Install the access panel 191BB (Ref. AMM TASK 53-35-13-400-002)
(2) Install the HP Air-Ground Connector Door (191DB) (Ref. AMM TASK 52-42-16-400-001)
(3) Make an entry in the log book to record that
Subtask 47-20-00-865-057-A ** ON A/C NOT FOR ALL (1) Install the access panel 191BB (Ref. AMM TASK 53-35-13-400-002)
(2) Install the HP Air-Ground Connector Door (191DB) (Ref. AMM TASK 52-42-16-400-001)
(3) Make an entry in the log book to record that
- the bellow (3) is installed,
and - the HP Air-Ground Connector Door (191DB) is reactivated.
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 47-20-00-860-057-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 121VU | IGGS/CTRL | 7YA | N28 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | IGGS/CTRL | 7YA | P28 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | CSAS / CTRL | 1HW | U17 |
C. Put the aircraft back to its initial configuration.
(1) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002)
(2) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
(3) Remove the WARNING NOTICE(S).
(1) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002)
(2) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
(3) Remove the WARNING NOTICE(S).
Bellow OEA Outlet