W DOC AIRBUS | AMM A320F

Operational Test of the PED Power System


TASK 46-26-90-700-802-A
Operational Test of the PED Power System


ZONE: 211
ZONE: 212
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
211
COCKPIT
212
COCKPIT
 B. Referenced Information
REFERENCE
DESIGNATION
TASK 24-41-00-861-002-A
Energize the Aircraft Electrical Circuits from the External Power
TASK 24-41-00-861-002-A-01
Energize the Aircraft Electrical Circuits from the APU
TASK 24-41-00-861-002-A-02
Energize the Aircraft Electrical Circuits from Engine 1(2)
TASK 24-42-00-862-001-A
De-energize the Ground Service Network Supplied from the External Power
3. Job Set-up
Subtask 46-26-90-861-059-A ** ON A/C NOT FOR ALL
A. Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
Subtask 46-26-90-875-050-B ** ON A/C NOT FOR ALL
B. Make sure that this(these) circuit breaker(s) is(are) closed:
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
122VUEFB/LEFT9002TAU09
122VUEFB/RIGHT9001TAU08
4. Procedure
Subtask 46-26-90-710-053-A ** ON A/C NOT FOR ALL
A. Operational Test of the (CAPT or F/O) PED Power System
   (1) On the PED, make sure that the battery charge is correct.
   (2) On the PED side, do a check of the battery load and record it.
   (3) Keep the PED energized for 20 minutes.
   (4) Make sure that the battery load did not decrease.
5. Close-up
Subtask 46-26-90-410-059-A ** ON A/C NOT FOR ALL
A. Put the aircraft back to its initial configuration.
   (1) Make sure that the work area is clean and clear of tools and other items.
Subtask 46-26-90-862-058-A ** ON A/C NOT FOR ALL
B. De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).
[Rev.10 from 2021] 2026.04.02 07:20:14 UTC