SATCOM Link Test of the ATSU
TASK 46-21-00-710-005-A
SATCOM Link Test of the ATSU
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 46-21-00-861-084-C ** ON A/C NOT FOR ALL Subtask 46-21-00-865-075-A ** ON A/C NOT FOR ALL
Subtask 46-21-00-710-057-C ** ON A/C NOT FOR ALL
Subtask 46-21-00-860-096-C ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.02 06:26:04 UTC
SATCOM Link Test of the ATSU
ZONE: 210
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 210 | CKPT,FWD COMPT BHD TO FLT COMPT BULKHEAD |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 31-60-00-860-001-A | EIS Start Procedure |
| TASK 31-60-00-860-002-A | EIS Stop Procedure |
Subtask 46-21-00-861-084-C ** ON A/C NOT FOR ALL Subtask 46-21-00-865-075-A ** ON A/C NOT FOR ALL
B. Make sure that this(these) circuit breaker(s) is(are) closed:
Subtask 46-21-00-860-095-C ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | AUTO FLT/MCDU/1 | 11CA1 | B01 |
| 49VU | SDAC/1/SPLY | 3WV | F04 |
| 49VU | FWS/FWC1/SPLY | 3WW | F01 |
| 121VU | CFDS/CFDIU/SPLY | 2TW | J18 |
| 121VU | ATSU 1 | 3TX1 | L16 |
| 121VU | ATSU 1/SWTG | 5TX1 | L15 |
| 121VU | EIS/FWC2/SPLY | 2WW | Q07 |
C. Aircraft Maintenance Configuration
(1) Do the EIS start procedure (upper and lower ECAM DUs only) (Ref. AMM TASK 31-60-00-860-001).
(2) On the center pedestal, on MCDU 1, adjust the brightness of the MCDU screen.
4. Procedure(1) Do the EIS start procedure (upper and lower ECAM DUs only) (Ref. AMM TASK 31-60-00-860-001).
(2) On the center pedestal, on MCDU 1, adjust the brightness of the MCDU screen.
Subtask 46-21-00-710-057-C ** ON A/C NOT FOR ALL
A. SATCOM Link Test of the ATSU
5. Close-up| ACTION | RESULT |
|---|---|
1.On MCDU1:
| On MCDU1:
|
2.On the MCDU MENU page:
| On the MCDU 1:
|
3.On the ATSU DATALINK page:
| On MCDU1:
|
4.On the COMM MENU page:
| On MCDU1:
|
5.On the MAINTENANCE page:
| On MCDU1:
|
6.On the TEST page:
| On the TEST page:
|
7.On MCDU1:
| |
8.On MCDU1:
| On the MCDU1:
|
Subtask 46-21-00-860-096-C ** ON A/C NOT FOR ALL
A. Put the aircraft back to its initial configuration.
(1) On MCDU1, fully decrease the brightness of the MCDU screen (display off).
(2) Do the EIS stop procedure (Ref. AMM TASK 31-60-00-860-002).
Subtask 46-21-00-862-069-C ** ON A/C NOT FOR ALL (1) On MCDU1, fully decrease the brightness of the MCDU screen (display off).
(2) Do the EIS stop procedure (Ref. AMM TASK 31-60-00-860-002).
MCDU Access to COMM MENU Page