Operational Test of the Anti-Syphon Valve
TASK 38-31-00-710-005-A
Operational Test of the Anti-Syphon Valve
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 38-31-00-861-056-A Subtask 38-31-00-010-059-A ** ON A/C NOT FOR ALL
Subtask 38-31-00-710-056-A
Subtask 38-31-00-614-051-A Subtask 38-31-00-410-061-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.01 01:19:45 UTC
Operational Test of the Anti-Syphon Valve
ZONE: 200
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 200 | UPPER HALF FUSELAGE |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 25-45-22-000-001-A | Removal of the Toilet Shroud and the Seat |
| TASK 25-45-22-000-802-A | Removal of the Toilet Shroud of the Space Flex Lavatory |
| TASK 25-45-22-400-001-A | Installation of the Toilet Shroud and the Seat |
| TASK 25-45-22-400-802-A | Installation of the Toilet Shroud of the Space Flex Lavatory |
| TASK 38-10-00-614-001-A | Pressurization of the Potable Water System from a Ground Air Supply |
| TASK 38-10-00-614-002-A | Depressurization of the Potable Water System |
| TASK 38-10-00-614-003-A | Pressurization of the Potable Water System with the Compressor |
| TASK 38-31-56-000-001-A | Removal of the Anti-Syphon Valve |
| TASK 38-31-56-400-001-A | Installation of the Anti-Syphon Valve |
Subtask 38-31-00-861-056-A Subtask 38-31-00-010-059-A ** ON A/C NOT FOR ALL
B. Get Access
(1) Get access to the cabin.
(2) Open the applicable lavatory door.
(3) Remove the toilet shroud.
(a) Remove the screws (1).
(b) Remove the shroud (2).
Subtask 38-31-00-010-059-C ** ON A/C NOT FOR ALL (1) Get access to the cabin.
(2) Open the applicable lavatory door.
(3) Remove the toilet shroud.
(a) Remove the screws (1).
(b) Remove the shroud (2).
B. Get Access
(1) Get access to the cabin.
(2) Open the related lavatory door.
(3) Remove the toilet shroud (Ref. AMM TASK 25-45-22-000-001) (Ref. AMM TASK 25-45-22-000-802).
Subtask 38-31-00-614-050-A (1) Get access to the cabin.
(2) Open the related lavatory door.
(3) Remove the toilet shroud (Ref. AMM TASK 25-45-22-000-001) (Ref. AMM TASK 25-45-22-000-802).
C. Pressurize the potable water system (Ref. AMM TASK 38-10-00-614-001) or (Ref. AMM TASK 38-10-00-614-003).
4. ProcedureSubtask 38-31-00-710-056-A
A. Do the Test
(1) Operate the toilet flush switch.
(2) Make sure that the toilet flushes satisfactorily.
Subtask 38-31-00-790-050-A (1) Operate the toilet flush switch.
(2) Make sure that the toilet flushes satisfactorily.
B. Examine the anti-syphon valve for leaks. If leaks are found, remove and replace the anti-syphon valve (Ref. AMM TASK 38-31-56-000-001) and (Ref. AMM TASK 38-31-56-400-001).
5. Close-upSubtask 38-31-00-614-051-A Subtask 38-31-00-410-061-A ** ON A/C NOT FOR ALL
B. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the toilet shroud.
(a) Put the shroud (2) in position.
(b) Install the screws (1).
(3) Close the lavatory door.
Subtask 38-31-00-410-061-C ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the toilet shroud.
(a) Put the shroud (2) in position.
(b) Install the screws (1).
(3) Close the lavatory door.
B. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the toilet shroud (Ref. AMM TASK 25-45-22-400-001) (Ref. AMM TASK 25-45-22-400-802).
(3) Close the related lavatory door.
Subtask 38-31-00-862-056-A (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the toilet shroud (Ref. AMM TASK 25-45-22-400-001) (Ref. AMM TASK 25-45-22-400-802).
(3) Close the related lavatory door.
Antisyphon Valve