2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 38-14-44-861-051-A ** ON A/C NOT FOR ALL
Subtask 38-14-44-020-050-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.02 06:25:43 UTC
Removal of the Overflow Valve
FIN: 8MP ** ON A/C NOT FOR ALL
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 2M (6 FT) |
| No specific | AR | CAP - BLANKING |
| No specific | AR | PLUG - BLANKING |
| No specific | AR | SAFETY CLIP - CIRCUIT BREAKER |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 132PW |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 38-10-00-614-002-A | Depressurization of the Potable Water System |
| TASK 52-30-00-860-001-A | Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
Subtask 38-14-44-861-051-A ** ON A/C NOT FOR ALL
A. Energize the ground service network
(Ref. AMM TASK 24-42-00-861-001).
(1) Put the ACCESS PLATFORM 2M (6 FT) in position.
Subtask 38-14-44-614-051-A ** ON A/C NOT FOR ALL Subtask 38-14-44-865-050-A ** ON A/C NOT FOR ALL (Ref. AMM TASK 24-42-00-861-001).
(1) Put the ACCESS PLATFORM 2M (6 FT) in position.
C. Open, safety and tag this(these) circuit breaker(s):
Subtask 38-14-44-010-050-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 2000VU | WATER SYSTEM-QANT-IND | 1MA | B01 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | WATER SYS-DRAIN | 1MP | B05 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | WATER-SYS-DRAIN | 1MP | B05 |
D. Get Access
(1) Open the FWD cargo-compartment door (Ref. AMM TASK 52-30-00-860-001).
(2) Remove the access panel 132PW.
4. Procedure(1) Open the FWD cargo-compartment door (Ref. AMM TASK 52-30-00-860-001).
(2) Remove the access panel 132PW.
Subtask 38-14-44-020-050-A ** ON A/C NOT FOR ALL
A. Removal of the Overflow Valve 8MP
(1) Open the insulation sleeve (11).
(2) Disconnect the electrical connector 8MP-A (3).
(3) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
(4) Remove the cotter pin (4), the washer (5) and the pin (7).
(5) Discard the cotter pin (4).
(6) Remove the control cable (6) from the overflow valve 8MP (1).
(7) Disconnect the connections (2) from the overflow valve 8MP (1).
(8) Put the PLUG-BLANKING in each disconnected line end.
(9) Remove the bolts (10), the washers (9), the overflow valve 8MP (1) and the spacers (8).
(10) Put PLUG - BLANKING on the open ports of the overflow valve 8MP.
(11) If necessary remove the insulation sleeve (11).
(1) Open the insulation sleeve (11).
(2) Disconnect the electrical connector 8MP-A (3).
(3) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
(4) Remove the cotter pin (4), the washer (5) and the pin (7).
(5) Discard the cotter pin (4).
(6) Remove the control cable (6) from the overflow valve 8MP (1).
(7) Disconnect the connections (2) from the overflow valve 8MP (1).
(8) Put the PLUG-BLANKING in each disconnected line end.
(9) Remove the bolts (10), the washers (9), the overflow valve 8MP (1) and the spacers (8).
(10) Put PLUG - BLANKING on the open ports of the overflow valve 8MP.
(11) If necessary remove the insulation sleeve (11).
Overflow Valve