Operational Test of the Potable Water Drain-System
TASK 38-14-00-710-001-A
Operational Test of the Potable Water Drain-System
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 38-14-00-861-050-A Subtask 38-14-00-865-064-A
Subtask 38-14-00-710-050-B ** ON A/C NOT FOR ALL
Subtask 38-14-00-080-050-A
[Rev.10 from 2021]
2026.04.02 06:25:43 UTC
Operational Test of the Potable Water Drain-System
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 1M(3 FT) |
| No specific | 1 | HOSE - DRAIN |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 133AL, 171AL | |
| 192NB |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 12-15-38-613-001-A | Fill the Potable Water Tank System (Aircraft Electrical Power Available) |
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 38-10-00-614-001-A | Pressurization of the Potable Water System from a Ground Air Supply |
Subtask 38-14-00-861-050-A Subtask 38-14-00-865-064-A
B. Make sure that this(these) circuit breaker(s) is(are) closed:
Subtask 38-14-00-010-050-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 2000VU | WATER SYSTEM-QANT-IND | 1MA | B01 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | WATER SYS-QUANT-IND | 1MA | B06 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | WATER SYS-DRAIN | 1MP | B05 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | WATER-SYS-DRAIN | 1MP | B05 |
C. Get Access
(1) Put the ACCESS PLATFORM 1M(3 FT) in position at Zone 171.
(2) Open the access panels 133AL 171AL.
(3) Remove the cap from the fill/drain port at the water service panel 2023VU.
Subtask 38-14-00-480-050-A ** ON A/C NOT FOR ALL (1) Put the ACCESS PLATFORM 1M(3 FT) in position at Zone 171.
(2) Open the access panels 133AL 171AL.
(3) Remove the cap from the fill/drain port at the water service panel 2023VU.
D. Connection of the Drain Hoses
(1) Connect the HOSE - DRAIN to the potable water fill and drain port at the service panel 2023VU.
(2) Connect the HOSE - DRAIN to the potable water drain-port at the forward drain panel.
Subtask 38-14-00-010-050-B ** ON A/C NOT FOR ALL (1) Connect the HOSE - DRAIN to the potable water fill and drain port at the service panel 2023VU.
(2) Connect the HOSE - DRAIN to the potable water drain-port at the forward drain panel.
E. Get Access
(1) Put the ACCESS PLATFORM 1M(3 FT) in position at Zone 171.
(2) Open the access panels 133AL 192NB 171AL.
(3) Remove the cap from the fill/drain port at the water service panel 2023VU.
Subtask 38-14-00-480-050-B ** ON A/C NOT FOR ALL (1) Put the ACCESS PLATFORM 1M(3 FT) in position at Zone 171.
(2) Open the access panels 133AL 192NB 171AL.
(3) Remove the cap from the fill/drain port at the water service panel 2023VU.
F. Connection of the Drain Hoses
(1) Connect the HOSE - DRAIN to the potable water fill and drain port at the service panel 2023VU.
(2) Connect the HOSE - DRAIN to the potable water drain-port at the forward drain panel.
(3) Connect the HOSE - DRAIN to the drain port at the drain and overflow panel.
Subtask 38-14-00-860-052-B (1) Connect the HOSE - DRAIN to the potable water fill and drain port at the service panel 2023VU.
(2) Connect the HOSE - DRAIN to the potable water drain-port at the forward drain panel.
(3) Connect the HOSE - DRAIN to the drain port at the drain and overflow panel.
G. Aircraft Maintenance Configuration
(1) Make sure that all the water shutoff valves in the lavatories and galleys are open.
(2) Make sure that there is sufficient water in the system before you do this test.
4. Procedure(1) Make sure that all the water shutoff valves in the lavatories and galleys are open.
(2) Make sure that there is sufficient water in the system before you do this test.
Subtask 38-14-00-710-050-B ** ON A/C NOT FOR ALL
A. Do this test.
Subtask 38-14-00-710-050-D ** ON A/C NOT FOR ALL | ACTION | RESULT |
|---|---|
1.At the service panel 2023VU:
| At the service panel 2023VU and the drain panel 133AL:
|
|
|
2.At the circuit breaker panel 2001VU:
NOTE: This section of the text is to test the valves mechanically. | At the service panel 2023VU:
|
3.At the service panel 2023VU:
| At the service panel 2023VU and the drain panel 133AL:
|
4.At the drain panel 133AL:
| At the service panel 2023VU and the drain panel 133AL:
|
5.At the drain panel 133AL and the service panel 2023VU:
| At the drain panel 133AL and the service panel 2023VU:
|
6.At the circuit breaker panel 2001VU:
| At the service panel 2023VU:
|
A. Do this test.
5. Close-up| ACTION | RESULT |
|---|---|
| 1.At the service panel 2023VU: | At the service panel 2023VU, the drain panel 133AL and the drain and overflow panel 192NB: |
|
|
|
|
2.At the circuit breaker panel 2001VU:
NOTE: This section of the text is to test the valves mechanically. | At the service panel 2023VU:
|
| 3.At the service panel 2023VU: | At the service panel 2023VU, the drain panel 133AL and the drain and overflow panel 192NB: |
|
NOTE: Water with a decreased flow will drain from the fill and drain port. This is because the overflow valve 8MP is closed. |
4.At the drain panel 133AL, the drain and overflow panel 192NB:
| At the service panel 2023VU and the drain panel 133AL:
|
5.At the drain panel 133AL, the drain and overflow panel 192NB, and the service panel 2023VU:
| At the drain panel 133AL, the drain and overflow panel 192NB, and the service panel 2023VU:
|
6.At the circuit breaker panel 2001VU:
| At the service panel 2023VU:
|
Subtask 38-14-00-080-050-A
A. Remove the drain hoses from the drain ports.
Subtask 38-14-00-613-050-A B. Fill the Potable Water System
(1) Fill the potable water tank 3000MM (Ref. AMM TASK 12-15-38-613-001).
(2) Pressurize the potable water system (Ref. AMM TASK 38-10-00-614-001).
(3) Operate the water faucets to bleed the potable water system.
(4) Turn on all the water heaters.
Subtask 38-14-00-410-050-A ** ON A/C NOT FOR ALL (1) Fill the potable water tank 3000MM (Ref. AMM TASK 12-15-38-613-001).
(2) Pressurize the potable water system (Ref. AMM TASK 38-10-00-614-001).
(3) Operate the water faucets to bleed the potable water system.
(4) Turn on all the water heaters.
C. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access panels 171AL 133AL.
(3) Remove the access platform(s).
Subtask 38-14-00-410-050-B ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access panels 171AL 133AL.
(3) Remove the access platform(s).
C. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access panels 171AL 133AL 192NB.
(3) Remove the access platform(s).
Subtask 38-14-00-862-050-A (1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access panels 171AL 133AL 192NB.
(3) Remove the access platform(s).