Detailed Inspection of the LH and RH Wing Leading Edge Overheat Sensing Elements
TASK 36-22-16-200-001-A
Detailed Inspection of the LH and RH Wing Leading Edge Overheat Sensing Elements
Detailed inspection of the bleed air duct leak/sensing element detection system, for example, after a duct leak warning.
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 36-22-16-941-065-A ** ON A/C NOT FOR ALL
Subtask 36-22-16-210-065-A ** ON A/C NOT FOR ALL
Subtask 36-22-16-410-059-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.01 01:17:16 UTC
Detailed Inspection of the LH and RH Wing Leading Edge Overheat Sensing Elements
WARNING:
PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU START A TASK ON OR NEAR:
- THE FLIGHT CONTROLS
- THE FLIGHT CONTROL SURFACES
- THE LANDING GEAR AND THE RELATED DOORS
- COMPONENTS THAT MOVE.
WARNING:
MAKE SURE THAT THE GROUND SAFETY-LOCKS ARE IN POSITION ON THE LANDING GEAR. THIS WILL PREVENT UNWANTED MOVEMENT OF THE LANDING GEAR, AND THUS POSSIBLE INJURY TO PERSONS AND DAMAGE TO THE AIRCRAFT AND/OR EQUIPMENT.
WARNING:
BEFORE YOU START WORK, YOU MUST PUT ON A SAFETY HARNESS AND ATTACH IT TO THE ACCESS PLATFORM. WITHOUT A SAFETY HARNESS, YOU CAN FALL. THIS CAN KILL YOU OR CAUSE YOU INJURY.
WARNING:
DO NOT TOUCH THE COMPONENT UNTIL IT IS SUFFICIENTLY
COOL TO PREVENT BURNS.
1. Reason for the JobDetailed inspection of the bleed air duct leak/sensing element detection system, for example, after a duct leak warning.
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE |
| No specific | AR | SAFETY BARRIER(S) |
| No specific | AR | SAFETY CLIP - CIRCUIT BREAKER |
| No specific | AR | WARNING NOTICE(S) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 191CT, 191EB, 192CT, 192EB, 521AB, 521BB, 521BT, 521CB, 521EB, 521GB, 521HB, 522AB, 522AT, 522CB, 522EB, 522FB, 621AB, 621BB, 621BT, 621CB, 621EB, 621GB, 621HB, 622AB, 622AT, 622CB, 622EB, 622FB |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 20-28-00-912-802-A | Electrical Bonding - General Maintenance Procedure |
| TASK 27-80-00-866-004-A | Extending the Slats on the Ground |
| TASK 27-80-00-866-005-A | Retracting the Slats on the Ground |
| TASK 32-00-00-481-001-A | Installation of the Safety Devices on the Landing Gears |
| TASK 53-35-11-000-001-A | Removal of the Wing-to-Fuselage Fairings |
| TASK 53-35-11-400-001-A | Installation of the Wing-to-Fuselage Fairings |
| TASK 57-41-37-000-003-A | Removal of the Access Panel |
| TASK 57-41-37-000-004-A | Removal of the Pressure Relief Panels |
| TASK 57-41-37-000-005-A | Removal of the NACA Duct Panel |
| TASK 57-41-37-000-006-A | Removal of the Access Panels |
| TASK 57-41-37-400-002-A | Installation of the Pressure Relief Panels |
| TASK 57-41-37-400-003-A | Installation of the Access Panel |
| TASK 57-41-37-400-005-A | Installation of the NACA Duct Panel |
| TASK 57-41-37-400-006-A | Installation of the Access Panels |
Subtask 36-22-16-941-065-A ** ON A/C NOT FOR ALL
A. Safety Precautions
(1) Put the SAFETY BARRIER(S) in position.
(2) Put a WARNING NOTICE(S) in the cockpit to tell persons not to operate the slat controls.
(3) Make sure that the ground safety locks are installed on the landing gear (Ref. AMM TASK 32-00-00-481-001).
Subtask 36-22-16-860-080-A ** ON A/C NOT FOR ALL Subtask 36-22-16-865-080-A ** ON A/C NOT FOR ALL (1) Put the SAFETY BARRIER(S) in position.
(2) Put a WARNING NOTICE(S) in the cockpit to tell persons not to operate the slat controls.
(3) Make sure that the ground safety locks are installed on the landing gear (Ref. AMM TASK 32-00-00-481-001).
C. Open, safety and tag this(these) circuit breaker(s):
Subtask 36-22-16-010-058-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | FLIGHT CONTROLS/SLT/CTL AND MONG/SYS1 | 5CV | B06 |
| 49VU | AIR BLEED/ENG 1/CTL | 3HA1 | D12 |
| 49VU | AIR BLEED/ENG 1/MONG | 2HA1 | D11 |
| 121VU | FLIGHT CONTROLS/SLT/CTL/SYS2 | 7CV | R21 |
| 122VU | AIR BLEED/ENG 2/CTL | 3HA2 | Z23 |
| 122VU | AIR BLEED/ENG 2/MONG | 2HA2 | Z22 |
D. Get Access
(1) Put the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position below the applicable access panels.
(2) Remove the applicable access panels (Ref. AMM TASK 57-41-37-000-004), (Ref. AMM TASK 57-41-37-000-006), (Ref. AMM TASK 57-41-37-000-005), (Ref. AMM TASK 57-41-37-000-003) and (Ref. AMM TASK 53-35-11-000-001):
4. Procedure(1) Put the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position below the applicable access panels.
(2) Remove the applicable access panels (Ref. AMM TASK 57-41-37-000-004), (Ref. AMM TASK 57-41-37-000-006), (Ref. AMM TASK 57-41-37-000-005), (Ref. AMM TASK 57-41-37-000-003) and (Ref. AMM TASK 53-35-11-000-001):
Subtask 36-22-16-210-065-A ** ON A/C NOT FOR ALL
A. Inspection of the Overheat Sensing Elements
(1) Make sure that the clearance between the sensing elements and the duct is a minimum of 12.7 MM (0.50 IN.), measured along the full length of the sensing element.
(2) Do an inspection of the sensing elements to make sure that they are installed on the outer side of the insulation.
(3) Make sure that the clearance between the sensing elements and the duct insulation is the same as at the mounting brackets.
(4) Make sure that the sensing elements are installed in the permitted tolerances.
(5) Make sure that each clamp has a silicon rubber grommet.
(6) Make sure that each mounting bracket, installed on the duct, has a spacer.
(7) Make sure that the sensing elements are installed correctly.
(8) Make sure that each mounting clamp is in the correct condition and has no corrosion.
(9) Make sure that the bonding straps are correctly attached (Ref. AMM TASK 20-28-00-912-802).
(10) Make sure that the lockwires are correctly installed on the connections of the sensing elements.
(11) Make sure that the duct insulation is in the correct condition and correctly installed.
(12) Make sure that the sensing elements have no cracks, nicks, sharp edges, bonds chafing or corrosion.
5. Close-up(1) Make sure that the clearance between the sensing elements and the duct is a minimum of 12.7 MM (0.50 IN.), measured along the full length of the sensing element.
(2) Do an inspection of the sensing elements to make sure that they are installed on the outer side of the insulation.
(3) Make sure that the clearance between the sensing elements and the duct insulation is the same as at the mounting brackets.
(4) Make sure that the sensing elements are installed in the permitted tolerances.
(5) Make sure that each clamp has a silicon rubber grommet.
(6) Make sure that each mounting bracket, installed on the duct, has a spacer.
(7) Make sure that the sensing elements are installed correctly.
(8) Make sure that each mounting clamp is in the correct condition and has no corrosion.
(9) Make sure that the bonding straps are correctly attached (Ref. AMM TASK 20-28-00-912-802).
(10) Make sure that the lockwires are correctly installed on the connections of the sensing elements.
(11) Make sure that the duct insulation is in the correct condition and correctly installed.
(12) Make sure that the sensing elements have no cracks, nicks, sharp edges, bonds chafing or corrosion.
Subtask 36-22-16-410-059-A ** ON A/C NOT FOR ALL
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the applicable access panels (Ref. AMM TASK 57-41-37-400-002), (Ref. AMM TASK 57-41-37-400-006), (Ref. AMM TASK 57-41-37-400-005), (Ref. AMM TASK 57-41-37-400-003) and (Ref. AMM TASK 53-35-11-400-001):
Subtask 36-22-16-865-081-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the applicable access panels (Ref. AMM TASK 57-41-37-400-002), (Ref. AMM TASK 57-41-37-400-006), (Ref. AMM TASK 57-41-37-400-005), (Ref. AMM TASK 57-41-37-400-003) and (Ref. AMM TASK 53-35-11-400-001):
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 36-22-16-860-081-A ** ON A/C NOT FOR ALL Subtask 36-22-16-942-058-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | FLIGHT CONTROLS/SLT/CTL AND MONG/SYS1 | 5CV | B06 |
| 49VU | AIR BLEED/ENG 1/CTL | 3HA1 | D12 |
| 49VU | AIR BLEED/ENG 1/MONG | 2HA1 | D11 |
| 121VU | FLIGHT CONTROLS/SLT/CTL/SYS2 | 7CV | R21 |
| 122VU | AIR BLEED/ENG 2/CTL | 3HA2 | Z23 |
| 122VU | AIR BLEED/ENG 2/MONG | 2HA2 | Z22 |
D. Removal of Equipment
(1) Remove the safety barriers.
(2) Remove the WARNING NOTICE(S).
(3) Remove the access platform(s).
(4) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
(1) Remove the safety barriers.
(2) Remove the WARNING NOTICE(S).
(3) Remove the access platform(s).
(4) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
Overheat Sensing Elements and Cables - Access Panels