Wetting Current Procedure


TASK 36-22-00-200-802-A
Wetting Current Procedure


WARNING: BEFORE YOU INSTALL/REMOVE THE GSE-TOOL, READ THE INSTRUCTIONS IN THE APPLICABLE GSE INSTRUCTION MANUAL. WHILE YOU OPERATE THIS TOOL, CAREFULLY OBEY THEM. IF YOU DO NOT OBEY THE INSTRUCTIONS, INJURY AND/OR DAMAGE CAN OCCUR.
ZONE: 121
ZONE: 122
1. Reason for the Job
To supply wetting current to the OverHeat Detection System (OHDS) loops which have a higher Centre Wire Resistance (CWR) value than the maximum permitted CWR value specified in AMM procedure 36-22-00-760-802-A.
A wetting current is an electrical current that can go through the film oxidation or contamination at the surface of the connector contact mating-surfaces. The film oxidation or contamination can cause open fault messages in the OHDS loops. The supply of wetting current gives the location function more accurately.
This procedure can extend the operation of the OHDS loops less than 3 months or a longer time for the different OHDS loop locations and/or environmental conditions on the aircraft. Thus, it cannot be known for a specified time period.
NOTE: This procedure is not applicable if there is a gold plate installed on the OHDS connecting-cable pins. The first three digits of the part numbers for the OHDS gold-plated connectors are 114.
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
1
ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE
No specific
AR
SAFETY CLIP - CIRCUIT BREAKER
CB0X406
1
CAPACITANCE DEC BOX
ELC132A
1
LCR METERS
HPG1
1
SIGNAL GEN-POCKET
KRTG36-1032
1
BLEED LOOP GROUND TEST
R5406
1
CAPACITANCE DEC BOX
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
121
AVIONICS COMPARTMENT
122
AVIONICS COMPARTMENT
811
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 24-41-00-861-002-A
Energize the Aircraft Electrical Circuits from the External Power
TASK 24-41-00-861-002-A-01
Energize the Aircraft Electrical Circuits from the APU
TASK 24-41-00-861-002-A-02
Energize the Aircraft Electrical Circuits from Engine 1(2)
TASK 24-41-00-862-002-A
De-energize the Aircraft Electrical Circuits Supplied from the External Power
TASK 24-41-00-862-002-A-01
De-energize the Aircraft Electrical Circuits Supplied from the APU
TASK 24-41-00-862-002-A-02
De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2)
TASK 36-11-34-000-001-A
Removal of the BMC
TASK 36-11-34-400-001-A
Installation of the BMC
TASK 36-22-00-100-803-A
Clean the Overheat Detection System (OHDS) Connectors and Apply the Electrical Insulating Compound
TASK 36-22-00-760-802-A
Measurement of the Centre Wire Resistance (CWR) of the OverHeat Detection System (OHDS) Loops
TASK 52-41-00-010-002-A
Open the Avionics Compartment Doors for Access
TASK 52-41-00-410-002-A
Close the Avionics Compartment Doors after Access
3. Job Set-up
Subtask 36-22-00-860-075-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
   (1) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
Subtask 36-22-00-865-078-A ** ON A/C NOT FOR ALL
B. Open, safety and tag this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
49VUAIR BLEED/ENG 2/MONG3HA2D12
49VUAIR BLEED/ENG 1/CTL2HA1D11
122VUAIR BLEED/ENG 1/MONG3HA1Z23
122VUAIR BLEED/ENG 2/CTL2HA2Z22
Subtask 36-22-00-010-059-A ** ON A/C NOT FOR ALL
C. Get access to the avionics compartment.
   (1) Put an ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE in position at access door 811.
   (2) Open access door 811 to get access to the main avionics compartment (Ref. AMM TASK 52-41-00-010-002).
4. Procedure
Subtask 36-22-00-480-053-A ** ON A/C NOT FOR ALL
A. Installation of the Tool
F Wetting Current Connections ** ON A/C NOT FOR ALL
   (1) Remove the Bleed Monitoring Computer (BMC) (1) that controls the loop on which you will do the procedure (Ref. AMM TASK 36-11-34-000-001).
NOTE: BMC-1 controls zones loop A and loop APU. BMC-2 controls zone loop B.
   (2) On the R5406 CAPACITANCE DEC BOX or CB0X406 CAPACITANCE DEC BOX (T2):
F Capacitor Decade Box ** ON A/C NOT FOR ALL
     (a) Make sure that all the switches are in the OUT position.
     (b) Set the switches that follow to IN to select 10 µF:
  • 1 µF
  • 2 µF
  • 3 µF
  • 4 µF.
   (3) On the ELC132A LCR METERS, select the C function.
NOTE: You can also use the KRTG36-1032 BLEED LOOP GROUND TEST as an alternative to the ELC132A LCR METERS.
   (4) Use the ELC132A LCR METERS to make sure that the R5406 CAPACITANCE DEC BOX or CB0X406 CAPACITANCE DEC BOX (T2) gives 10 µF (plus or minus 10 per cent).
   (5) Connect the adapter (T3) to the top of the HPG1 SIGNAL GEN-POCKET (T1).
   (6) Connect the test lead (T4) between the red plug of the adapter (T3) and the red plug of the R5406 CAPACITANCE DEC BOX or CB0X406 CAPACITANCE DEC BOX (T2).
   (7) Connect the banana plug of the test lead (T5) to the black plug of the R5406 CAPACITANCE DEC BOX or CB0X406 CAPACITANCE DEC BOX(T2).
   (8) Connect the banana plug of the test lead (T6) to the black plug of the adapter (T3).
   (9) Start the HPG1 SIGNAL GEN-POCKET (T1).
   (10) Make sure that the HPG1 SIGNAL GEN-POCKET (T1) battery is fully charged.
NOTE: After you use the HPG1 SIGNAL GEN-POCKET, we recommend that you charge the battery, refer to the manufacturer's instructions.
   (11) In the HPG1 SIGNAL GEN-POCKET (T1) menu:
     (a) Select a sine waveform.
     (b) Select a frequency of 1 KHz.
     (c) Select an amplitude of 8 V peak-to-peak (2.8 V RMS) output voltage.
Subtask 36-22-00-280-053-A ** ON A/C NOT FOR ALL
B. Wetting Current Procedure
F Wetting Current Connections ** ON A/C NOT FOR ALL
F CWR Table ** ON A/C NOT FOR ALL
   (1) On the CWR table, do a check of the specified pins for the applicable loop.
   (2) On the ELC132A LCR METERS, select the R series function and a frequency of 1 kHz.
   (3) Measure the CWR in the loop between the start pin and the end pin (Ref. AMM TASK 36-22-00-760-802).
   (4) Make sure that the measured CWR value is stable.
   (5) Record the measured CWR value.
   (6) For loop start:
     (a) Connect the end pin of the test lead (T5) to the applicable end pin given in the CWR table.
     (b) Connect the end pin of the test lead (T6) to the applicable start pin given in the CWR table.
     (c) Supply the wetting current during 60 seconds.
     (d) Disconnect the end pins of the test lead (T5) and the test lead (T6) from the connector.
   (7) For loop end:
     (a) Connect the end pin of the test lead (T5) to the applicable start pin given in the CWR table.
     (b) Connect the end pin of the test lead (T6) to the applicable end pin given in the CWR table.
     (c) Supply the wetting current during 60 seconds.
     (d) Disconnect the end pins of the test lead (T5) and the test lead (T6) from the connector.
   (8) On the ELC132A LCR METERS, make sure that the R series function and a frequency of 1 kHz are selected.
   (9) Measure the CWR of the applicable loop again between the start pin and the end pin (Ref. AMM TASK 36-22-00-760-802).
   (10) Compare the measured CWR value with the value that you recorded before.
F CWR Table ** ON A/C NOT FOR ALL
     (a) Make sure that the measured CWR value is lower than the maximum permitted CWR value for the loop.
     (b) If the CWR value is not correct:
       1 Clean the OHDS connectors and apply the electrical insulating compound (Ref. AMM TASK 36-22-00-100-803).
   (11) Disconnect the end pins of the test lead (T5) and the test lead (T6) from the connector.
   (12) Use the ELC132A LCR METERS to measure the CWR of the applicable loop again between the start pin and the end pin (Ref. AMM TASK 36-22-00-760-802).
   (13) Record the measured CWR value in the technical logbook.
   (14) Install the BMC (1) (Ref. AMM TASK 36-11-34-400-001).
5. Close-up
Subtask 36-22-00-410-061-A ** ON A/C NOT FOR ALL
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Close access door 811 (Ref. AMM TASK 52-41-00-410-002).
   (3) Remove the access platform(s).
Subtask 36-22-00-865-079-A ** ON A/C NOT FOR ALL
B. Remove the safety clips and tags and close these circuit breakers in this sequence:
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
49VUAIR BLEED/ENG 2/MONG3HA2D12
49VUAIR BLEED/ENG 1/CTL2HA1D11
122VUAIR BLEED/ENG 1/MONG3HA1Z23
122VUAIR BLEED/ENG 2/CTL2HA2Z22
Subtask 36-22-00-860-076-A ** ON A/C NOT FOR ALL
C. Aircraft Maintenance Configuration
   (1) Put the aircraft back to its initial configuration.
   (2) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).