Installation of the Crossbleed Valve Actuator
TASK 36-12-52-400-002-A
Installation of the Crossbleed Valve Actuator
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Referenced Information
3. Job Set-up
Subtask 36-12-52-860-053-A
Subtask 36-12-52-420-051-A
Subtask 36-12-52-410-052-A
[Rev.10 from 2021]
2026.04.01 01:15:44 UTC
Installation of the Crossbleed Valve Actuator
WARNING:
MAKE SURE THAT THE PNEUMATIC SYSTEM IS DEPRESSURIZED BEFORE YOU START WORK. PRESSURIZED AIR CAN CAUSE INJURY TO PERSONNEL.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE |
| No specific | AR | WARNING NOTICE(S) |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 36-12-00-710-001-A | Operational Test of the APU Bleed Air Supply and Crossbleed Systems |
Subtask 36-12-52-860-053-A
A. Aircraft Maintenance Configuration
(1) Make sure that the WARNING NOTICE(S) are in position:
(3) Make sure that the access panel 192FB is open.
Subtask 36-12-52-865-056-A (1) Make sure that the WARNING NOTICE(S) are in position:
- in the cockpit on the Engine Control Panel 115VU to tell persons not to start the engine(s),
- in the cockpit on the AIR COND Overhead Control Panel 30VU to tell persons not to push in the APU BLEED pushbutton switch,
- on the HP ground connector to tell persons not to pressurize the pneumatic system.
(3) Make sure that the access panel 192FB is open.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR BLEED/ENG 1/CTL | 3HA1 | D12 |
| 49VU | AIR BLEED/ENG 1/MONG | 2HA1 | D11 |
| ** ON A/C ALL | |||
| 49VU | AIR BLEED/X FEED/VALVE/BAT | 2HV | D13 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR BLEED/ENG 2/MONG | 3HA2 | D12 |
| 49VU | AIR BLEED/ENG 1/CTL | 2HA1 | D11 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | AIR BLEED/ENG 2/CTL | 3HA2 | Z23 |
| 122VU | AIR BLEED/ENG 2/MONG | 2HA2 | Z22 |
| ** ON A/C ALL | |||
| 122VU | AIR BLEED/X FEED VALVE/NORM | 1HV | Z20 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | AIR BLEED/ENG 1/MONG | 3HA1 | Z23 |
| 122VU | AIR BLEED/ENG 2/CTL | 2HA2 | Z22 |
Subtask 36-12-52-420-051-A
A. Installation of the Crossbleed Valve Actuator
(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Check the adapter (10) and the spring pin (9) for correct condition.
(4) Install the crossbleed valve actuator (13) to the adapter (10).
(5) Make sure that the spring pin (9) correctly engages the hole in the adapter.
(6) Install the half clamps (11),(15) with the screws (14) to the adapter (10) and the actuator (13).
(7) Tighten the screws (14).
(8) Remove the CAP-BLANKING from each electrical connector and receptacle.
receptacle.
(9) Connect the electrical connector (12) to the crossbleed valve actuator (13).
Subtask 36-12-52-865-057-A (1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Check the adapter (10) and the spring pin (9) for correct condition.
(4) Install the crossbleed valve actuator (13) to the adapter (10).
(5) Make sure that the spring pin (9) correctly engages the hole in the adapter.
(6) Install the half clamps (11),(15) with the screws (14) to the adapter (10) and the actuator (13).
(7) Tighten the screws (14).
(8) Remove the CAP-BLANKING from each electrical connector and receptacle.
receptacle.
(9) Connect the electrical connector (12) to the crossbleed valve actuator (13).
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 36-12-52-710-051-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR BLEED/ENG 1/CTL | 3HA1 | D12 |
| 49VU | AIR BLEED/ENG 1/MONG | 2HA1 | D11 |
| ** ON A/C ALL | |||
| 49VU | AIR BLEED/X FEED/VALVE/BAT | 2HV | D13 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR BLEED/ENG 2/MONG | 3HA2 | D12 |
| 49VU | AIR BLEED/ENG 1/CTL | 2HA1 | D11 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | AIR BLEED/ENG 2/CTL | 3HA2 | Z23 |
| 122VU | AIR BLEED/ENG 2/MONG | 2HA2 | Z22 |
| ** ON A/C ALL | |||
| 122VU | AIR BLEED/X FEED VALVE/NORM | 1HV | Z20 |
| ** ON A/C NOT FOR ALL | |||
| 122VU | AIR BLEED/ENG 1/MONG | 3HA1 | Z23 |
| 122VU | AIR BLEED/ENG 2/CTL | 2HA2 | Z22 |
C. Do the operational test of the APU Bleed Air-Supply and Crossbleed System (Ref. AMM TASK 36-12-00-710-001).
5. Close-upSubtask 36-12-52-410-052-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the access panel 192FB.
Subtask 36-12-52-942-056-A (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the access panel 192FB.
B. Put the aircraft back to its initial configuration.
(1) Remove the access platform(s).
(2) Remove the WARNING NOTICE(S).
(1) Remove the access platform(s).
(2) Remove the WARNING NOTICE(S).
Crossbleed Valve Actuator