Installation of the Overpressure Valve
TASK 36-11-53-400-803-A
Installation of the Overpressure Valve
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
C. Work Zones and Access Panels
D. Expendable Parts
E. Referenced Information
3. Job Set-up
Subtask 36-11-53-861-061-A
Subtask 36-11-53-420-056-A
Subtask 36-11-53-410-066-A
[Rev.10 from 2021]
2026.04.01 01:13:21 UTC
Installation of the Overpressure Valve
WARNING:
MAKE SURE THAT THE PNEUMATIC SYSTEM IS DEPRESSURIZED BEFORE YOU START WORK. PRESSURIZED AIR CAN CAUSE INJURY TO PERSONNEL.
WARNING:
BE CAREFUL WHEN YOU DO WORK ON THE ENGINE PARTS AFTER THE ENGINE SHUTDOWN. USE APPLICABLE THERMAL GLOVES. THE ENGINE PARTS CAN STAY HOT FOR ONE HOUR AFTER SHUTDOWN AND CAN BURN YOU.
WARNING:
YOU MUST NOT TOUCH HOT PARTS WITHOUT APPLICABLE GLOVES. HOT PARTS CAN CAUSE AN INJURY.
WARNING:
PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU START A TASK ON OR NEAR:
- THE FLIGHT CONTROLS
- THE FLIGHT CONTROL SURFACES
- THE LANDING GEAR AND THE RELATED DOORS
- COMPONENTS THAT MOVE.
CAUTION:
BE VERY CAREFUL WHEN YOU DO WORK ON OR NEAR THE AIR-CONDITIONING DUCTS. THE DUCTS ARE MADE OF THIN MATERIAL AND YOU CAN EASILY BREAK THEM.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE |
| No specific | 1 | FOIL - ALUMINUM |
| No specific | AR | WARNING NOTICE(S) |
| No specific | 1 | WATER - SOAPY SOLUTION |
| No specific | Torque wrench: range to between 1.41 and 1.3 m.daN (124.78 and 115.04 lbf.in ) ![]() | |
| No specific | Torque wrench: range to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft ) ![]() | |
| No specific | Torque wrench: range to between 1.75 and 1.64 m.daN (12.91 and 12.09 lbf.ft ) ![]() | |
| 98D27803000000 | 1 | LOCKING TOOL-FLAP SLAT LEVER,INT. POSITION |
| 98L12003001000 | AR | HARNESS,SAFETY |
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.14QEB1) | Wire-Locking Dia: 0.6 mm CRES Nickel Alloy - |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 413 | UPPER FWD PYLON |
| 423 | UPPER FWD PYLON |
| 191DB | |
| FOR [7115HM1] (VALVE-OVERPRESSURE, ENG 1) | |
| 413CT | |
| FOR [7115HM2] (VALVE-OVERPRESSURE, ENG 2) | |
| 423CT | |
| FIG.ITEM | DESIGNATION | IPC-CSN |
|---|---|---|
| 12 | SEAL | AIPC 36-11-86-50-150 |
| 2 | SEAL | AIPC 36-11-86-50-150 |
| 6 | SEAL | AIPC 36-11-86-50-150 |
| 22 | SPECIAL SEAL | AIPC 36-11-86-50-230 |
| 15 | SEAL | AIPC 36-11-86-50-300 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 12-00-00-481-002-A | Installation of the Wingrip |
| TASK 20-23-22-910-001-A | Marking of the Unions after Application of Standard or Specific Tightening Torque |
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 36-11-53-720-803-A | Functional Check of Overpressure Valve |
| TASK 36-11-53-720-803-A-01 | Functional Test of the Overpressure Valve (OPV) with the Bleed Test Set P/N 99127B04 and the Bleed Test Kit P/N 99127-281 |
| TASK 36-12-00-860-805-A | Pressurization of the Bleed System with the APU |
| TASK 36-12-00-860-806-A | Pressurization of the Bleed System through the HP Ground Connector |
| TASK 49-00-00-860-009-A | APU Shutdown by External Power (131-9(A)) |
| TASK 49-00-00-860-009-A-01 | APU Shutdown by Batteries (131-9(A)) |
| TASK 54-52-11-000-807-A | Removal of the Access Skin Panels |
| TASK 54-52-11-400-807-A | Installation of the Access Skin Panels |
Subtask 36-11-53-861-061-A
A. Energize the aircraft electrical circuits
(1) Make sure that the aircraft electrical circuits are energized (Ref. AMM TASK 24-41-00-861-002) or (Ref. AMM TASK 24-41-00-861-002).
Subtask 36-11-53-941-062-A (1) Make sure that the aircraft electrical circuits are energized (Ref. AMM TASK 24-41-00-861-002) or (Ref. AMM TASK 24-41-00-861-002).
B. Safety Precautions
(1) On AIR COND panel 30VU:
(a) Make sure that the ENG 1(2) BLEED pushbutton switch is released (OFF legend on).
(b) Make sure that the APU BLEED pushbutton switch is released (ON legend off).
(c) Make sure that the WARNING NOTICE(S) is in position to tell persons not to operate the pneumatic system.
(2) On the center pedestal, on ENG panel 115VU:
(a) Make sure that the ENG/MODE selector switch is in the NORM position.
(b) Make sure that the ENG/MASTER 1(2) control switch was in the OFF position not less than five minutes before you do this procedure.
(c) Make sure that the WARNING NOTICE(S) are in position to tell persons not to operate:
(a) Make sure that the ON legend of the FADEC GND PWR/1(2) pushbutton switch is off.
(b) Make sure that the WARNING NOTICE(S) is in position to tell persons not to energize FADEC 1(2).
(4) On access door 191DB, on the HP ground connector:
(a) Make sure that the WARNING NOTICE(S) is in position to tell persons not to pressurize the pneumatic system.
(5) On FLAPS panel 114VU:
Subtask 36-11-53-865-066-A (1) On AIR COND panel 30VU:
(a) Make sure that the ENG 1(2) BLEED pushbutton switch is released (OFF legend on).
(b) Make sure that the APU BLEED pushbutton switch is released (ON legend off).
(c) Make sure that the WARNING NOTICE(S) is in position to tell persons not to operate the pneumatic system.
(2) On the center pedestal, on ENG panel 115VU:
(a) Make sure that the ENG/MODE selector switch is in the NORM position.
(b) Make sure that the ENG/MASTER 1(2) control switch was in the OFF position not less than five minutes before you do this procedure.
(c) Make sure that the WARNING NOTICE(S) are in position to tell persons not to operate:
- The ENG/MODE selector switch, and
- The ENG/MASTER 1(2) control switch.
(a) Make sure that the ON legend of the FADEC GND PWR/1(2) pushbutton switch is off.
(b) Make sure that the WARNING NOTICE(S) is in position to tell persons not to energize FADEC 1(2).
(4) On access door 191DB, on the HP ground connector:
(a) Make sure that the WARNING NOTICE(S) is in position to tell persons not to pressurize the pneumatic system.
(5) On FLAPS panel 114VU:
- Make sure that the 98D27803000000 LOCKING TOOL-FLAP SLAT LEVER,INT. POSITION is in position on the flap/slat control lever.
- Make sure that the WARNING NOTICE(S) is in position on the flap/slat control lever to tell persons not to operate the flap/slat controls.
C. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
Subtask 36-11-53-010-073-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | AIR BLEED/ENG 2/MONG | 3HA2 | D12 |
| 49VU | AIR BLEED/ENG 1/CTL | 2HA1 | D11 |
| 122VU | AIR BLEED/ENG 1/MONG | 3HA1 | Z23 |
| 122VU | AIR BLEED/ENG 2/CTL | 2HA2 | Z22 |
D. Get Access
(1) Make sure that the ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE is in position at the pylon access panels.
(2) Make sure that this access panel is removed (Ref. AMM TASK 54-52-11-000-807):
(a) FOR [7115HM1] (VALVE-OVERPRESSURE, ENG 1)
413CT
(b) FOR [7115HM2] (VALVE-OVERPRESSURE, ENG 2)
423CT
4. Procedure(1) Make sure that the ACCESS PLATFORM 4M (13 FT)-ADJUSTABLE is in position at the pylon access panels.
(2) Make sure that this access panel is removed (Ref. AMM TASK 54-52-11-000-807):
(a) FOR [7115HM1] (VALVE-OVERPRESSURE, ENG 1)
413CT
(b) FOR [7115HM2] (VALVE-OVERPRESSURE, ENG 2)
423CT
Subtask 36-11-53-420-056-A
A. Installation of the Overpressure Valve
(1) If you use the APU to energize the electrical circuits, stop the APU:
(a) Make sure that the pressure and the temperature of the bleed-air duct system are in ambient conditions.
(4) Clean the component interfaces and the adjacent area.
(5) Remove the PLUG - BLANKING from the overpressure valve (18) and the precooler exchanger (17).
(6) Remove the PLUG-BLANKING from each disconnected line end.
(7) Make sure that the parts retained from the removed component are clean and in the correct condition.
(8) Install a new AIPC 36-11-86-50-300 SEAL (15) on the precooler exchanger (17).
(9) Put the overpressure valve (18) in position:
(a) Make sure that the flow direction arrow on the valve points to the precooler exchanger (17) direction.
(b) Make sure that the alignment tab engages.
(10) Install the clamp (14):
(a) Use the clocking device (23) of the overpressure valve (18) to install the clamp (14) in the correct position. Do not tighten the clamp (14) at this time.
Subtask 36-11-53-420-057-A (1) If you use the APU to energize the electrical circuits, stop the APU:
- For GTCP 36-300 APU (Ref. AMM D/O 49-00-00-86)
- For APS 3200 APU (Ref. AMM D/O 49-00-00-86)
- For 131-9(A) APU (Ref. AMM TASK 49-00-00-860-009).
(a) Make sure that the pressure and the temperature of the bleed-air duct system are in ambient conditions.
WARNING:
MAKE SURE THAT THE PNEUMATIC SYSTEM IS DEPRESSURIZED BEFORE YOU START WORK. PRESSURIZED AIR CAN CAUSE INJURY TO PERSONNEL.
WARNING:
DO NOT TOUCH THE UNIT UNTIL IT IS SUFFICIENTLY COOL TO PREVENT BURNS WHEN YOU DO THE MAINTENANCE TASK(S).
(3) Do an inspection of the component interfaces and the adjacent area.(4) Clean the component interfaces and the adjacent area.
(5) Remove the PLUG - BLANKING from the overpressure valve (18) and the precooler exchanger (17).
(6) Remove the PLUG-BLANKING from each disconnected line end.
(7) Make sure that the parts retained from the removed component are clean and in the correct condition.
(8) Install a new AIPC 36-11-86-50-300 SEAL (15) on the precooler exchanger (17).
(9) Put the overpressure valve (18) in position:
(a) Make sure that the flow direction arrow on the valve points to the precooler exchanger (17) direction.
(b) Make sure that the alignment tab engages.
(10) Install the clamp (14):
(a) Use the clocking device (23) of the overpressure valve (18) to install the clamp (14) in the correct position. Do not tighten the clamp (14) at this time.
B. Installation of the Bellows and the T-Duct
(1) Do an inspection of the component interfaces and the adjacent area.
(2) Clean the component interfaces and the adjacent area.
(3) Remove the PLUG-BLANKING from each disconnected line end.
(4) Make sure that the parts retained from the removed component are clean and in the correct condition.
(5) Installation of the T-duct:
(b) Carefully install the two shims (19) in position.
(c) Carefully put the T-duct (9) in position.
(d) Install the couplings (13) and (20). Do not tighten the couplings (13) and (20) at this time.
(e) Install the washer (7) and bolt (8) on the oblong hole in the right side. Do not tighten the bolt (8) at this time.
(f) Install the bushing (11) and bolt (10). Do not tighten the bolt (10) at this time.
(6) Installation of the bellows:
(a) Install a new AIPC 36-11-86-50-150 SEAL (6) in the T-duct (9) and a new AIPC 36-11-86-50-150 SEAL (2) in the starter duct (1).
(b) Put the bellows (4) in position.
(c) Install the couplings (5) and (3). Do not tighten the couplings (5) and (3) at this time.
(7) Make sure that the bellows (4), T-duct (9) and overpressure valve (18) are correctly assembled and aligned.
(8) Make sure that the couplings (3), (5), (13) and (20) are installed in the same positions as recorded during the removal procedure.
(9) TORQUE the couplings (3), (5) and (13), and clamp (14) to between 1.41 and 1.3 m.daN (124.78 and 115.04 lbf.in )
.
(10) TORQUE the coupling (20) to between 1.75 and 1.64 m.daN (12.91 and 12.09 lbf.ft )
.
(11) Tighten the bolts (8) and (10).
(12) Identify the tightened union nuts of the couplings (3), (5), (13) and (20), and clamp (14) with a red line (Ref. AMM TASK 20-23-22-910-001).
(13) Connect the sense line (16) to the precooler exchanger (17).
(14) TORQUE the sense line (16) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
.
(15) Identify the tightened union nut of the sense line (16) with a red line (Ref. AMM TASK 20-23-22-910-001).
Subtask 36-11-53-865-067-A (1) Do an inspection of the component interfaces and the adjacent area.
(2) Clean the component interfaces and the adjacent area.
(3) Remove the PLUG-BLANKING from each disconnected line end.
(4) Make sure that the parts retained from the removed component are clean and in the correct condition.
(5) Installation of the T-duct:
CAUTION:
WHEN YOU INSTALL OR REMOVE THE T-DUCT, BE VERY CAREFUL NOT TO LET THE REMOVABLE PARTS FALL INTO THE BLEED DUCT. IF YOU DO NOT OBEY THIS INSTRUCTION, DAMAGE TO THE EQUIPMENT CAN OCCUR.
(a) Install a new AIPC 36-11-86-50-150 SEAL (12) in the T-duct (9) and a new AIPC 36-11-86-50-230 SPECIAL SEAL (22) in the ECS pipe (21). (b) Carefully install the two shims (19) in position.
(c) Carefully put the T-duct (9) in position.
(d) Install the couplings (13) and (20). Do not tighten the couplings (13) and (20) at this time.
(e) Install the washer (7) and bolt (8) on the oblong hole in the right side. Do not tighten the bolt (8) at this time.
(f) Install the bushing (11) and bolt (10). Do not tighten the bolt (10) at this time.
(6) Installation of the bellows:
(a) Install a new AIPC 36-11-86-50-150 SEAL (6) in the T-duct (9) and a new AIPC 36-11-86-50-150 SEAL (2) in the starter duct (1).
(b) Put the bellows (4) in position.
(c) Install the couplings (5) and (3). Do not tighten the couplings (5) and (3) at this time.
(7) Make sure that the bellows (4), T-duct (9) and overpressure valve (18) are correctly assembled and aligned.
(8) Make sure that the couplings (3), (5), (13) and (20) are installed in the same positions as recorded during the removal procedure.
(9) TORQUE the couplings (3), (5) and (13), and clamp (14) to between 1.41 and 1.3 m.daN (124.78 and 115.04 lbf.in )
. (10) TORQUE the coupling (20) to between 1.75 and 1.64 m.daN (12.91 and 12.09 lbf.ft )
. (11) Tighten the bolts (8) and (10).
(12) Identify the tightened union nuts of the couplings (3), (5), (13) and (20), and clamp (14) with a red line (Ref. AMM TASK 20-23-22-910-001).
(13) Connect the sense line (16) to the precooler exchanger (17).
(14) TORQUE the sense line (16) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
. (15) Identify the tightened union nut of the sense line (16) with a red line (Ref. AMM TASK 20-23-22-910-001).
C. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 36-11-53-480-058-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | AIR BLEED/ENG 2/MONG | 3HA2 | D12 |
| 49VU | AIR BLEED/ENG 1/CTL | 2HA1 | D11 |
| 122VU | AIR BLEED/ENG 1/MONG | 3HA1 | Z23 |
| 122VU | AIR BLEED/ENG 2/CTL | 2HA2 | Z22 |
D. Prepare for the Leak Test on the Connections
(1) There are two procedures to do a leak check at the connections of the bleed air ducts (duct joint, flexible connections).
(a) Soap solution procedure.
2 Twist tight the seam of the foil wrap.
4 Attach the foil wrap at the two sides of the pneumatic joint with14QEB1 Wire-Locking Dia: 0.6 mm CRES Nickel Alloy - .
Subtask 36-11-53-790-050-A (1) There are two procedures to do a leak check at the connections of the bleed air ducts (duct joint, flexible connections).
(a) Soap solution procedure.
- Leaks are permitted if the WATER - SOAPY SOLUTION stays on the joint line with a continuous series of bubbles.
- Leaks are not permitted if the air pressure (from the air source) blows the soap solution off the joint line and prevents a continuous series of bubbles.
NOTE: This procedure is recommended when you do a leak check with hot air.
1 Wind the FOIL - ALUMINUM on the joint once. 2 Twist tight the seam of the foil wrap.
WARNING:
USE PROTECTIVE GOGGLES AND GLOVES WHEN YOU REMOVE OR INSTALL LOCKWIRE. EACH TIME YOU CUT LOCKWIRE, REMOVE AND DISCARD IT IMMEDIATELY. LOOSE LOCKWIRE CAN CUT YOU OR MAKE YOU BLIND, AND/OR CAN CAUSE DAMAGE.
3 Make the foil wrap as tight as possible on the tube but do not rip the wrap. 4 Attach the foil wrap at the two sides of the pneumatic joint with
E. Leak Test
(1) Pressurize the bleed system through the HP ground connector (Ref. AMM TASK 36-12-00-860-806) or with the APU (Ref. AMM TASK 36-12-00-860-805).
(a) Make sure that there are no leaks at:
Subtask 36-11-53-720-083-A 5. Close-up(1) Pressurize the bleed system through the HP ground connector (Ref. AMM TASK 36-12-00-860-806) or with the APU (Ref. AMM TASK 36-12-00-860-805).
(a) Make sure that there are no leaks at:
- The junction upstream of the precooler exchanger (17) and the overpressure valve (18)
- The junction of the overpressure valve (18) and the T-duct (9)
- The junction of the T-duct (9) and the bellows (4)
- The junction of the T-duct (9) and the ECS duct (21)
- The junction of the starter duct (1) and the bellows (4)
- The junction of the sense line (16) and the precooler exchanger (17).
NOTE: There is a leak when the foil installed on the pneumatic connection breaks or when it is too hot.
(2) Remove the materials used to do the leak test. Subtask 36-11-53-410-066-A
A. Close Access
(1) Put the aircraft back to its initial configuration.
(2) Make sure that the work area is clean and clear of tools and other items.
(3) Install the access panel (Ref. AMM TASK 54-52-11-400-807):
(a) FOR [7115HM1] (VALVE-OVERPRESSURE, ENG 1)
413CT
(b) FOR [7115HM2] (VALVE-OVERPRESSURE, ENG 2)
423CT
(4) Remove all the fixtures, tools, test and support equipment used during this procedure.
(5) Remove the access platform(s).
(6) Remove the WARNING NOTICE(S).
Subtask 36-11-53-862-058-A (1) Put the aircraft back to its initial configuration.
(2) Make sure that the work area is clean and clear of tools and other items.
(3) Install the access panel (Ref. AMM TASK 54-52-11-400-807):
(a) FOR [7115HM1] (VALVE-OVERPRESSURE, ENG 1)
413CT
(b) FOR [7115HM2] (VALVE-OVERPRESSURE, ENG 2)
423CT
(4) Remove all the fixtures, tools, test and support equipment used during this procedure.
(5) Remove the access platform(s).
(6) Remove the WARNING NOTICE(S).
B. De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002) or (Ref. AMM TASK 24-41-00-862-002).
(Ref. AMM TASK 24-41-00-862-002) or (Ref. AMM TASK 24-41-00-862-002).
Overpressure Valve