Functional Test of the Bleed Regulated Pressure-Transducer with the Bleed Test Set P/N 98D36109001000
TASK 36-11-16-720-802-A
Functional Test of the Bleed Regulated Pressure-Transducer with the Bleed Test Set P/N 98D36109001000
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 36-11-16-861-058-A ** ON A/C NOT FOR ALL Subtask 36-11-16-941-057-A ** ON A/C NOT FOR ALL
Subtask 36-11-16-720-053-A ** ON A/C NOT FOR ALL
Subtask 36-11-16-860-064-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.01 01:08:36 UTC
Functional Test of the Bleed Regulated Pressure-Transducer with the Bleed Test Set P/N 98D36109001000
WARNING:
PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU START A TASK ON OR NEAR:
- THE FLIGHT CONTROLS
- THE FLIGHT CONTROL SURFACES
- THE LANDING GEAR AND THE RELATED DOORS
- COMPONENTS THAT MOVE.
WARNING:
BE CAREFUL WHEN YOU DO WORK ON THE ENGINE PARTS AFTER THE ENGINE SHUTDOWN. USE APPLICABLE THERMAL GLOVES. THE ENGINE PARTS CAN STAY HOT FOR ONE HOUR AFTER SHUTDOWN AND CAN BURN YOU.
WARNING:
BEFORE YOU INSTALL/REMOVE THE GSE TOOL, READ THE MANUFACTURER'S INSTRUCTIONS, AND, WHILE YOU OPERATE THIS TOOL, CAREFULLY OBEY THEM. IF YOU DO NOT DO THIS, INJURY TO PERSONS AND DAMAGE TO EQUIPMENT CAN OCCUR.
CAUTION:
BE CAREFUL WHEN YOU CONNECT/DISCONNECT THE TEST SET TO/FROM THE EQUIPMENT.
THE PRESSURE REGULATING VALVE AND THE PRESSURE GAGE ASSEMBLY OF THE TEST SET ARE HEAVY AND CAN CAUSE DAMAGE TO THE ENGINE.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1) | |
| 415BL | |
| FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2) | |
| 425BL | |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 31-32-00-860-011-A | Procedure to Get Access to the SYSTEM REPORT/TEST/PNEU Page |
| FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1) | |
| TASK 54-51-21-000-802-A | Removal of the Pylon Lateral Access-Doors |
| TASK 54-51-21-400-802-A | Installation of the Pylon Lateral Access-Doors |
| FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2) | |
| TASK 54-51-21-000-802-A | Removal of the Pylon Lateral Access-Doors |
| TASK 54-51-21-400-802-A | Installation of the Pylon Lateral Access-Doors |
Subtask 36-11-16-861-058-A ** ON A/C NOT FOR ALL Subtask 36-11-16-941-057-A ** ON A/C NOT FOR ALL
B. Safety Precautions
(1) Make sure that the engine 1(2) shutdown occurred not less than 5 minutes before you do this procedure.
(2) On AIR COND panel 30VU:
Subtask 36-11-16-865-062-A ** ON A/C NOT FOR ALL (1) Make sure that the engine 1(2) shutdown occurred not less than 5 minutes before you do this procedure.
(2) On AIR COND panel 30VU:
- Make sure that ENG 1(2) BLEED pushbutton switch is released (OFF legend is on).
- Make sure that the APU BLEED pushbutton switch is released (ON legend is off).
- Put a WARNING NOTICE(S) in position to tell persons not to operate the pneumatic system.
- Put a WARNING NOTICE(S) in position to tell the persons not to start engine 1(2).
- Put a WARNING NOTICE(S) in position to tell persons not to pressurize the pneumatic system.
- Make sure that the ON legend of ENG/FADEC GND PWR 1(2) pushbutton switch is off.
- Put a WARNING NOTICE(S) in position to tell persons not to energize FADEC 1(2).
C. Make sure that this(these) circuit breaker(s) is(are) closed:
Subtask 36-11-16-010-058-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | AIR BLEED/APU BLEED VLV CTL/BMC1 OVRD | 11HV | D14 |
| 49VU | AIR BLEED/X FEED/VALVE/BAT | 2HV | D13 |
| 49VU | AIR BLEED/ENG 2/MONG | 3HA2 | D12 |
| 49VU | AIR BLEED/ENG 1/CTL | 2HA1 | D11 |
| 122VU | AIR BLEED/ENG 1/MONG | 3HA1 | Z23 |
| 122VU | AIR BLEED/ENG 2/CTL | 2HA2 | Z22 |
| 122VU | AIR BLEED/X FEED VALVE/NORM | 1HV | Z20 |
| 122VU | AIR BLEED/APU BLEED VLV CTL/BMC2 OVRD | 12HV | Z19 |
D. Get Access
(1) Put the ACCESS PLATFORM 5M (16 FT)- ADJUSTABLE in position at the pylon access.
(2) Remove the access panels:
(a) FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1)
415BL (Ref. AMM TASK 54-51-21-000-802)
(b) FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2)
425BL (Ref. AMM TASK 54-51-21-000-802).
Subtask 36-11-16-020-054-A ** ON A/C NOT FOR ALL (1) Put the ACCESS PLATFORM 5M (16 FT)- ADJUSTABLE in position at the pylon access.
(2) Remove the access panels:
(a) FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1)
415BL (Ref. AMM TASK 54-51-21-000-802)
(b) FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2)
425BL (Ref. AMM TASK 54-51-21-000-802).
E. Disconnection of the Sense Line
(2) Put the PLUG-BLANKING in each disconnected line end.
Subtask 36-11-16-860-063-A ** ON A/C NOT FOR ALL CAUTION:
USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT THE PNEUMATIC LINES ON UNIONS.
(1) Disconnect the sense line from the Bleed Regulated Pressure-Transducer 8HA1 (8HA2). (2) Put the PLUG-BLANKING in each disconnected line end.
F. Aircraft Maintenance Configuration
(1) Adjust the brightness of the MCDU screen.
(2) On one MCDU, get the SYSTEM REPORT/TEST PNEU/SENSOR STATUS menu page (Ref. AMM TASK 31-32-00-860-011).
4. Procedure(1) Adjust the brightness of the MCDU screen.
(2) On one MCDU, get the SYSTEM REPORT/TEST PNEU/SENSOR STATUS menu page (Ref. AMM TASK 31-32-00-860-011).
Subtask 36-11-16-720-053-A ** ON A/C NOT FOR ALL
A. Functional Test of the Bleed Regulated Pressure-Transducer 8HA1(8HA2)
(1) Close the shutoff valve, the purge valve and the pressure regulator valve on the 98D36109001000 TEST SET-EBAS,BLEED.
(2) Connect an AIR SOURCE - REGULATED, FILTERED, DRY to the 98D36109001000 TEST SET-EBAS,BLEED.
(a) Connect the 98D36109001000 TEST SET-EBAS,BLEED to the test port of the Bleed Regulated Pressure Transducer 8HA1 (8HA2).
(3) Set the digital pressure gage back to zero.
(4) Make sure that the regulator valve of the 98D36109001000 TEST SET-EBAS,BLEED is closed before pressurize the system.
(5) Do the test that follows:
(6) Close the shutoff valve of the AIR SOURCE - REGULATED, FILTERED, DRY.
(7) Slowly open the purge valve to depressurize the 98D36109001000 TEST SET-EBAS,BLEED to 0 psi (0.00 bar).
(8) Disconnection of the 98D36109001000 TEST SET-EBAS,BLEED:
5. Close-up(1) Close the shutoff valve, the purge valve and the pressure regulator valve on the 98D36109001000 TEST SET-EBAS,BLEED.
(2) Connect an AIR SOURCE - REGULATED, FILTERED, DRY to the 98D36109001000 TEST SET-EBAS,BLEED.
(a) Connect the 98D36109001000 TEST SET-EBAS,BLEED to the test port of the Bleed Regulated Pressure Transducer 8HA1 (8HA2).
(3) Set the digital pressure gage back to zero.
(4) Make sure that the regulator valve of the 98D36109001000 TEST SET-EBAS,BLEED is closed before pressurize the system.
(5) Do the test that follows:
| ACTION | RESULT |
|---|---|
1.On the MCDU control panel:
| On the MCDU:
|
2.Pressurize the 98D36109001000 TEST SET-EBAS,BLEED:
| |
3.On the 98D36109001000 TEST SET-EBAS,BLEED:
| On the 98D36109001000 TEST SET-EBAS,BLEED:
|
4.On the 98D36109001000 TEST SET-EBAS,BLEED:
| On the 98D36109001000 TEST SET-EBAS,BLEED:
|
(7) Slowly open the purge valve to depressurize the 98D36109001000 TEST SET-EBAS,BLEED to 0 psi (0.00 bar).
(8) Disconnection of the 98D36109001000 TEST SET-EBAS,BLEED:
WARNING:
BEFORE YOU START TO REMOVE THE TOOLING, MAKE SURE THAT THERE IS NO PRESSURIZED GAS LEFT INSIDE THE DUCTS. IT CAN CAUSE AN INJURY TO PERSONNEL AND/OR DAMAGE TO EQUIPMENT.
(a) Disconnect the 98D36109001000 TEST SET-EBAS,BLEEDfrom the test port of the Bleed Regulated Pressure-Transducer 8HA1 (8HA2). Subtask 36-11-16-860-064-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Close the MCDU session.
(2) Fully decrease the brightness of the MCDU screen (display off).
Subtask 36-11-16-420-055-A ** ON A/C NOT FOR ALL (1) Close the MCDU session.
(2) Fully decrease the brightness of the MCDU screen (display off).
B. Connection of the sense line:
(1) Remove the PLUG-BLANKING from each disconnected line end.
(2) Connect the sense line to the Bleed Regulated Pressure-Transducer 8HA1(8HA2).
.
Subtask 36-11-16-410-056-A ** ON A/C NOT FOR ALL (1) Remove the PLUG-BLANKING from each disconnected line end.
(2) Connect the sense line to the Bleed Regulated Pressure-Transducer 8HA1(8HA2).
CAUTION:
USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT THE PNEUMATIC LINES ON UNIONS.
(3) TORQUE the nut of the sense line to between 0.84 and 0.83 m.daN (74.34 and 73.45 lbf.in )
. C. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the access panels:
(a) FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1)
415BL (Ref. AMM TASK 54-51-21-400-802)
(b) FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2)
425BL (Ref. AMM TASK 54-51-21-400-802).
(3) Remove the access platform(s).
(4) Remove the WARNING NOTICE(S).
Subtask 36-11-16-862-057-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Install the access panels:
(a) FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1)
415BL (Ref. AMM TASK 54-51-21-400-802)
(b) FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2)
425BL (Ref. AMM TASK 54-51-21-400-802).
(3) Remove the access platform(s).
(4) Remove the WARNING NOTICE(S).
MCDU Valve Status Page