Functional Test of the Bleed Regulated Pressure-Transducer with the Bleed Test Set P/N 99127B03
TASK 36-11-16-720-001-A-02
Functional Test of the Bleed Regulated Pressure-Transducer with the Bleed Test Set P/N 99127B03
1. Reason for the Job
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 36-11-16-861-055-A ** ON A/C NOT FOR ALL Subtask 36-11-16-941-055-A ** ON A/C NOT FOR ALL
Subtask 36-11-16-480-050-A ** ON A/C NOT FOR ALL
Subtask 36-11-16-420-053-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.01 01:08:35 UTC
Functional Test of the Bleed Regulated Pressure-Transducer with the Bleed Test Set P/N 99127B03
1. Reason for the Job
NOTE: You can use bleed test set P/N 99127B04 as an alternative to bleed test set P/N 99127B03.
2. Job Set-up InformationA. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 5M (16 FT)- ADJUSTABLE |
| No specific | AR | PLUG - BLANKING |
| No specific | 1 | SUPPLY - 28 VDC, ELECTRICAL |
| No specific | AR | WARNING NOTICE(S) |
| No specific | Torque wrench: range to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft ) ![]() | |
| 99127-231 | 1 | TEST SET BLEED - KIT |
| 99127B03 | 1 | BLEED TEST SET |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1) | |
| 415AL, 415AR | |
| FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2) | |
| 425AL, 425AR | |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 31-60-00-860-001-A | EIS Start Procedure |
| TASK 31-60-00-860-002-A | EIS Stop Procedure |
Subtask 36-11-16-861-055-A ** ON A/C NOT FOR ALL Subtask 36-11-16-941-055-A ** ON A/C NOT FOR ALL
B. Safety Precautions
(1) Make sure that the engine 1(2) shutdown occurred not less than 5 minutes before you do this procedure.
(2) On the AIR COND panel 30VU:
Subtask 36-11-16-010-055-A ** ON A/C NOT FOR ALL (1) Make sure that the engine 1(2) shutdown occurred not less than 5 minutes before you do this procedure.
(2) On the AIR COND panel 30VU:
- Make sure that the ENG 1(2) BLEED pushbutton switch is released (the OFF legend is on).
- Make sure that the APU BLEED pushbutton switch is released (the ON legend is off).
- Put a WARNING NOTICE(S) in position to tell persons not to operate the pneumatic system.
- Put a WARNING NOTICE(S) in position to tell persons not to start the engine 1(2).
- Put a WARNING NOTICE(S) in position to tell persons not to pressurize the pneumatic system.
- Make sure that the ON legend of the ENG/FADEC GND PWR 1(2) pushbutton switch is off.
- Put a WARNING NOTICE(S) in position to tell persons not to energize the FADEC 1(2).
C. Get Access
(1) Put the ACCESS PLATFORM 5M (16 FT)- ADJUSTABLE in position at the pylon access.
(2) Open the access doors:
(a) FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1)
415AL 415AR
(b) FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2)
425AL 425AR.
Subtask 36-11-16-020-052-A ** ON A/C NOT FOR ALL (1) Put the ACCESS PLATFORM 5M (16 FT)- ADJUSTABLE in position at the pylon access.
(2) Open the access doors:
(a) FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1)
415AL 415AR
(b) FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2)
425AL 425AR.
D. Disconnection of the Sense Line
(2) Put the PLUG-BLANKING in each disconnected line end.
Subtask 36-11-16-860-060-A ** ON A/C NOT FOR ALL CAUTION:
USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT THE PNEUMATIC LINES ON UNIONS.
(1) Disconnect the sense line from the bleed regulated pressure-transducer 8HA1(2). (2) Put the PLUG-BLANKING in each disconnected line end.
E. Aircraft Maintenance Configuration
(1) Do the EIS start procedure (upper ECAM DU and lower ECAM DU only)
(Ref. AMM TASK 31-60-00-860-001).
4. Procedure(1) Do the EIS start procedure (upper ECAM DU and lower ECAM DU only)
(Ref. AMM TASK 31-60-00-860-001).
Subtask 36-11-16-480-050-A ** ON A/C NOT FOR ALL
A. Installation of the Tool
(1) Connection of the 99127B03 BLEED TEST SET
(c) Connect the "Y" adaptor (T06) to the test port adaptor (T25).
(d) Connect the pneumatic hose (T04) between the "Y" adaptor (T06) and the test set connection (9).
(e) Connect the pneumatic hose (T05) between the "Y" adaptor (T06) and the test set connection (14).
(f) Open the primary pressure-source shutoff-valve to slowly pressurize the 99127B03 BLEED TEST SET to 100 psi (6.89 bar).
Subtask 36-11-16-720-052-A ** ON A/C NOT FOR ALL (1) Connection of the 99127B03 BLEED TEST SET
NOTE: Use the bleed test-set kit 99127-231 TEST SET BLEED - KIT to perform this test.
NOTE: Set the pressure gage (5) to ON. The pressure value given on the LCD screen must be equal to 0 psi. If it is not equal to 0 psi, push the ON button during 10 seconds.
(a) Connect the 28VDC electrical cord (T03) between the electrical inlet (11) of the 99127B03 BLEED TEST SET (T01) and an external SUPPLY - 28 VDC, ELECTRICAL: - Start the SUPPLY - 28 VDC, ELECTRICAL.
(c) Connect the "Y" adaptor (T06) to the test port adaptor (T25).
(d) Connect the pneumatic hose (T04) between the "Y" adaptor (T06) and the test set connection (9).
(e) Connect the pneumatic hose (T05) between the "Y" adaptor (T06) and the test set connection (14).
(f) Open the primary pressure-source shutoff-valve to slowly pressurize the 99127B03 BLEED TEST SET to 100 psi (6.89 bar).
B. Functional Test of the Bleed Regulated Pressure-Transducer
(1) Do the test that follows:
Subtask 36-11-16-080-050-A ** ON A/C NOT FOR ALL (1) Do the test that follows:
| ACTION | RESULT |
|---|---|
1.On the test set:
| |
2.On the ECAM control panel:
| On the SD:
|
3.On the test set:
| On the test set:
|
| | On the SD:
|
4.On the test set:
| On the test set:
|
C. Removal of the Tool
(1) Disconnection of the 99127B03 BLEED TEST SET
(a) Set the blue valve (7) to OFF.
(b) Close the primary pressure-source shutoff-valve to depressurize the 99127B03 BLEED TEST SET.
(c) Stop the SUPPLY - 28 VDC, ELECTRICAL.
(d) Disconnect the 28VDC electrical cord (T03) from the electrical inlet (11) of the 99127B03 BLEED TEST SET (T01) and the external SUPPLY - 28 VDC, ELECTRICAL.
(e) Disconnect the pneumatic hoses (T04) and (T05) from the test set connections (9) and (14).
(f) Disconnect the pneumatic hoses (T04) and (T05) from the "Y" adaptor (T06).
(g) Disconnect the "Y" adaptor (T06) from the test port adaptor (T25).
(h) Disconnect the test port adaptor (T25) from the union of the bleed regulated pressure-transducer.
5. Close-up(1) Disconnection of the 99127B03 BLEED TEST SET
(a) Set the blue valve (7) to OFF.
(b) Close the primary pressure-source shutoff-valve to depressurize the 99127B03 BLEED TEST SET.
(c) Stop the SUPPLY - 28 VDC, ELECTRICAL.
(d) Disconnect the 28VDC electrical cord (T03) from the electrical inlet (11) of the 99127B03 BLEED TEST SET (T01) and the external SUPPLY - 28 VDC, ELECTRICAL.
(e) Disconnect the pneumatic hoses (T04) and (T05) from the test set connections (9) and (14).
(f) Disconnect the pneumatic hoses (T04) and (T05) from the "Y" adaptor (T06).
(g) Disconnect the "Y" adaptor (T06) from the test port adaptor (T25).
(h) Disconnect the test port adaptor (T25) from the union of the bleed regulated pressure-transducer.
Subtask 36-11-16-420-053-A ** ON A/C NOT FOR ALL
A. Connection of the Sense Line
(2) Connect the sense line to the bleed regulated pressure-transducer 8HA1(2).
(3) TORQUE the nut of the sense line to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
.
Subtask 36-11-16-942-053-A ** ON A/C NOT FOR ALL CAUTION:
USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT THE PNEUMATIC LINES ON UNIONS.
(1) Remove the PLUG-BLANKING from each disconnected line end.(2) Connect the sense line to the bleed regulated pressure-transducer 8HA1(2).
(3) TORQUE the nut of the sense line to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
. B. Aircraft Maintenance Configuration
(1) Do the EIS stop procedure
(Ref. AMM TASK 31-60-00-860-002).
Subtask 36-11-16-410-054-A ** ON A/C NOT FOR ALL (1) Do the EIS stop procedure
(Ref. AMM TASK 31-60-00-860-002).
C. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access doors:
(a) FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1)
415AL 415AR
(b) FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2)
425AL 425AR.
(3) Remove the access platform(s).
(4) Remove the WARNING NOTICE(S).
Subtask 36-11-16-862-055-A ** ON A/C NOT FOR ALL (1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access doors:
(a) FOR [8HA1] (XDCR-BLEED REGULATED PRESS, ENG 1)
415AL 415AR
(b) FOR [8HA2] (XDCR-BLEED REGULATED PRESS, ENG 2)
425AL 425AR.
(3) Remove the access platform(s).
(4) Remove the WARNING NOTICE(S).
Functional Test of the Bleed Regulated Pressure-Transducer with the Bleed Test Set P/N 99127B03