W DOC AIRBUS | AMM A320F

Installation of the Standby Airspeed Indicator


TASK 34-21-26-400-001-A
Installation of the Standby Airspeed Indicator


ZONE: 211
FIN: 9FN ** ON A/C NOT FOR ALL
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
211
COCKPIT
 B. Referenced Information
REFERENCE
DESIGNATION
TASK 25-13-41-000-002-A
Removal of the Sidewall Panels
TASK 25-13-41-400-002-A
Installation of the Sidewall Panels
TASK 33-13-00-710-001-A
Operational Test of the Instrument and Panel Integral-Lighting
3. Job Set-up
Subtask 34-21-26-865-054-A ** ON A/C NOT FOR ALL
A. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
122VULIGHTING/INSTL LT/MAIN INST/PNL AND/PED4LFY04
Subtask 34-21-26-010-051-A ** ON A/C NOT FOR ALL
B. Remove the sidewall panel 211LW (Ref. AMM TASK 25-13-41-000-002)
4. Procedure
Subtask 34-21-26-420-050-A ** ON A/C NOT FOR ALL
A. Installation of the Standby Airspeed Indicator (9FN)
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) Remove the blanking plugs from the line ends (4) and (5).
   (4) Connect the quick-disconnect couplings (5) of the pressure lines (green and red) to the related connectors (4) of the standby airspeed indicator (2).
   (5) Make sure that you can see the blue ring on the quick-disconnect couplings.
   (6) Pull the quick-disconnect couplings to be sure that they are correctly attached.
   (7) Make sure that the quick-disconnect coupling is correctly engaged (the pin located on the quick-disconnect male part is fully engaged into the groove located in the quick-disconnect female part).
   (8) Remove the blanking caps from the electrical connectors (3) and (6).
   (9) Make sure that all the electrical connections are clean and in the correct condition.
   (10) Connect the electrical connector (6) to the receptacle (3) of the standby airspeed indicator (2).
   (11) Install the standby airspeed indicator (2) in its housing.
   (12) Look behind the standby airspeed indicator and make sure that the position of the flexible hoses (static and total pressure lines) is satisfactory (no crushing, kinks, creases or folds).
   (13) Tighten the screws (1).
Subtask 34-21-26-865-055-A ** ON A/C NOT FOR ALL
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
122VULIGHTING/INSTL LT/MAIN INST/PNL AND/PED4LFY04
Subtask 34-21-26-710-050-A ** ON A/C NOT FOR ALL
C. Do the operational test of the instrument and panel integral lighting (Ref. AMM TASK 33-13-00-710-001).
5. Close-up
Subtask 34-21-26-410-050-A ** ON A/C NOT FOR ALL
A. Put the aircraft back to its initial configuration.
   (1) Install the thermoformed cover on the center instrument panel.
   (2) Install the sidewall panel 211LW (Ref. AMM TASK 25-13-41-400-002).
   (3) Make sure that the work area is clean and clear of tools and other items.
[Rev.10 from 2021] 2026.04.02 06:23:13 UTC