Installation of the System 1 (2) Transformer


TASK 33-14-51-400-002-A
Installation of the System 1 (2) Transformer


ZONE: 212
FIN: 36LP
FIN: 37LP
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
CAP - BLANKING
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
212
COCKPIT
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 33-14-00-710-001-A
Operational Check of the Light Test System
3. Job Set-up
Subtask 33-14-51-865-055-A
A. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
122VULIGHTING/TST/BOARD/SPLY30LPX06
FOR FIN: 36LP (XFMRSYS 2)
122VULIGHTING/ANN LT SPLY/XFMR/BUS 227LPX05
FOR FIN: 37LP (XFMRSYS 1)
122VULIGHTING/ANN LT SPLY/XFMR/BUS 126LPX04
Subtask 33-14-51-010-053-A
B. Get Access
   (1) Make sure that the panel(s) 121VU and/or 122VU is (are) removed.
   (2) Make sure that the quick-disconnect fasteners are loosened for these panels:
     (a) FOR [37LP] (XFMR-SYS 1)
122VU.
     (b) FOR [36LP] (XFMR-SYS 2)
122VU, 121VU.
   (3) Make sure that these panels are pulled to the front.
4. Procedure
Subtask 33-14-51-420-051-A
A. Installation of the Transformer
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) Remove the CAP - BLANKING from the electrical connector.
   (4) Make sure that all the electrical connections are clean and in the correct condition.
   (5) Install the new transformer (1).
   (6) Install the four screws (3) and the washers (2) that attach the transformer (1) to the structure.
   (7) Connect the movable connector (4) to the transformer.
Subtask 33-14-51-410-050-A
B. Install these panels. Attach them with the quick-disconnect fasteners:
   (1) FOR [37LP] (XFMR-SYS 1)
122VU
   (2) FOR [36LP] (XFMR-SYS 2)
122VU, 121VU
Subtask 33-14-51-865-054-A
C. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
122VULIGHTING/TST/BOARD/SPLY30LPX06
FOR FIN: 36LP (XFMRSYS 2)
122VULIGHTING/ANN LT SPLY/XFMR/BUS 227LPX05
FOR FIN: 37LP (XFMRSYS 1)
122VULIGHTING/ANN LT SPLY/XFMR/BUS 126LPX04
Subtask 33-14-51-710-051-A
D. Do the operational test (Ref. AMM TASK 33-14-00-710-001).
5. Close-up
Subtask 33-14-51-942-051-A
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.