W DOC AIRBUS | AMM A320F

Installation of the Annunciator-Light Test and Interface-Board


TASK 33-14-33-400-001-A
Installation of the Annunciator-Light Test and Interface-Board


CAUTION: DURING REMOVAL AND INSTALLATION OF THE PRINTED CIRCUIT BOARDS (PCB'S) THAT HAVE THE ESD SYMBOL, OBEY THESE PRECAUTIONS:
  • USE A CONDUCTIVE WRIST-STRAP THAT IS ELECTRICALLY GROUNDED (CONNECTED TO A BONDING-POINT NEAR THE WORK AREA) BEFORE AND DURING HANDLING OF THE PCB'S. IF NO WRIST-STRAP IS AVAILABLE, MAKE SURE THAT YOU ARE ELECTRICALLY CONNECTED TO THE AIRCRAFT GROUND BEFORE YOU HANDLE THE PCB'S.
  • DO NOT TOUCH THE ELECTRICAL CONNECTOR PINS.
  • PREVENT CONTACT WITH THE TOP FACE OR BOTTOM FACE OF THE PCB WHERE THE ELECTRONIC DEVICES ARE LOCATED.
  • MAKE SURE THAT THE REPLACEMENT PCB'S ARE IN THEIR PROTECTIVE PACKAGING AND/OR NON-CONDUCTIVE BOX WHEN YOU RECEIVE THEM ON THE AIRCRAFT.
  • MAKE SURE THAT YOU PUT THE DEFECTIVE (REMOVED) PCB'S IN PROTECTIVE WRAPS FOR TRANSPORT BACK TO THE HANGAR.
IF YOU DO NOT OBEY THESE INSTRUCTIONS, YOU CAN CAUSE ELECTROSTATIC DISCHARGE (ESD) DAMAGE TO THE PCB'S.
ZONE: 126
FIN: 1LP
FIN: 10LP
FIN: 11LP
FIN: 12LP
FIN: 18LP
FIN: 19LP
FIN: 2LP
FIN: 20LP
FIN: 3LP
FIN: 4LP
FIN: 5LP
FIN: 6LP
FIN: 7LP
FIN: 8LP
FIN: 9LP
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
126
LATERAL AVIONIC COMPARTMENT
822
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 33-14-00-710-001-A
Operational Check of the Light Test System
3. Job Set-up
Subtask 33-14-33-010-051-A
A. Get Access
   (1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position under the access door 822.
   (2) Make sure that the access door 822 is open.
Subtask 33-14-33-865-051-A
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
122VULIGHTING/TST/BOARD/SPLY30LPX06
4. Procedure
Subtask 33-14-33-420-050-A
A. Installation of the board
   (1) Install the new annunciator-light test and interface-board (1).
   (2) Tighten the two screws (2) that attach the annunciator light test and interface-board to its support (3).
Subtask 33-14-33-865-052-A
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
122VULIGHTING/TST/BOARD/SPLY30LPX06
Subtask 33-14-33-710-050-A
C. Do the operational test: (Ref. AMM TASK 33-14-00-710-001).
5. Close-up
Subtask 33-14-33-410-050-A
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Close the access door 822.
   (3) Remove the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE .
[Rev.10 from 2021] 2026.04.01 00:53:04 UTC