W DOC AIRBUS | AMM A320F

Installation of the Parking Brake Valve


TASK 32-45-14-400-001-A
Installation of the Parking Brake Valve


WARNING: MAKE SURE THAT ALL THE CIRCUITS IN MAINTENANCE ARE ISOLATED BEFORE YOU SUPPLY ELECTRICAL POWER TO THE AIRCRAFT. UNWANTED ELECTRICAL POWER CAN BE DANGEROUS.
WARNING: PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU START A TASK ON OR NEAR:
  • THE FLIGHT CONTROLS
  • THE FLIGHT CONTROL SURFACES
  • THE LANDING GEAR AND THE RELATED DOORS
  • COMPONENTS THAT MOVE.
MOVEMENT OF COMPONENTS CAN KILL OR CAUSE INJURY TO PERSONS AND/OR CAN CAUSE DAMAGE TO THE EQUIPMENT.
WARNING: OBEY THE HYDRAULIC SAFETY PROCEDURES.
WARNING: BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
FIN: 2579GM ** ON A/C NOT FOR ALL
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
1
WRENCH - STANDARD
No specific
Torque wrench: range to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft ) T
No specific
Torque wrench: range to between 3.47 and 3.19 m.daN (25.59 and 23.53 lbf.ft ) T
No specific
Torque wrench: range to between 5.9 and 5.4 m.daN (43.51 and 39.82 lbf.ft ) T
 B. Consumable Materials
REFERENCE
DESIGNATION
(Material No.02ABA1)
Phosphate Ester Hydraulic Fluid-General Power - -
(Material No.04JMD9)
Top Coat Polyurethane-- Decorative Furnishing
(Material No.06AEA1)
Polysulfide Sealant-Low Adhesion Brushable -
 C. Expendable Parts
FIG.ITEM
DESIGNATION
IPC-CSN
3
PACKING
AIPC 32-45-03-03-230
 D. Referenced Information
REFERENCE
DESIGNATION
TASK 12-12-29-611-001-A
Fill the Hydraulic Fluid Reservoir with a Hand Pump
TASK 20-23-11-917-001-A
Tightening Practices for Hydraulic Connections
TASK 29-10-00-864-002-A
Depressurize the Yellow Hydraulic System
TASK 29-14-00-614-001-A
Depressurization of the Hydraulic Reservoirs
TASK 29-23-00-860-001-A
Disconnection of the Isolation Coupling of the Power Transfer Unit (PTU)
TASK 32-12-00-410-001-A
Close the Main Gear Doors after Access
TASK 32-43-00-710-001-A
Operational Check of Alternate Braking System
TASK 32-43-00-870-002-A
Bleeding of the High Pressure Alternate Braking System
TASK 32-45-00-710-001-A
Operational Check of the Parking Brake System
TASK 51-75-13-916-002-A
Repair to a layer of Corrosion Preventive Compound
3. Job Set-up
Subtask 32-45-14-860-051-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
   (1) Make sure that the PTU isolation coupling is disconnected (Ref. AMM TASK 29-23-00-860-001).
   (2) Make sure that the Yellow hydraulic system is depressurized (Ref. AMM TASK 29-10-00-864-002).
   (3) Make sure that the reservoir of the Yellow hydraulic system is depressurized (Ref. AMM TASK 29-14-00-614-001).
Subtask 32-45-14-865-051-A ** ON A/C NOT FOR ALL
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
49VUL/G/Y BRK/PRESS/IND61GGC10
121VUHYDRAULIC/BRAKING AND STEERING/SYS2/SPLY4GGM36
121VUHYDRAULIC/BRAKING AND STEERING/SYS2/CTL3GGM35
121VUHYDRAULIC/BRAKING AND STEERING/SYS1/CTL1GGM34
121VUHYDRAULIC/BRAKING AND STEERING/SYS1/IND AND/SPLY2GGM33
121VUHYDRAULIC/PARK BRK/CTL/STBY71GGN37
121VUHYDRAULIC/PARK BRK/CTL/NORM70GGN36
121VUHYDRAULIC/HYD POWER/Y3803GXN30
121VUHYDRAULIC/Y HYD/PUMP ENG2/MONG3700GDQ37
121VUHYDRAULIC/Y HYD/PUMP ENG2/CTL3701GDQ36
123VUY HYD/ELEC/PUMP3802GXAB06
123VUY HYD/ELEC/ELEC PUMP/NORM3801GXAB03
Subtask 32-45-14-941-051-A ** ON A/C NOT FOR ALL
C. Make sure that the warning notices are in position to tell persons not to pressurize the Yellow hydraulic system:
  • on the panel 40VU in the cockpit,
  • on the ground service panel of the Yellow hydraulic system.
Subtask 32-45-14-560-050-A ** ON A/C NOT FOR ALL
D. Preparation of the Replacement Component
F Parking Brake Valve 2579GM ** ON A/C NOT FOR ALL
WARNING: OBEY THE HYDRAULIC SAFETY PROCEDURES.
   (1) Apply the Phosphate Ester Hydraulic Fluid-General Power - - (Material No.02ABA1) to the:
Subtask 32-45-14-560-051-A ** ON A/C NOT FOR ALL
E. Preparation for Installation
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) Make sure that the parts retained from the removed component are clean and in the correct condition.
4. Procedure
Subtask 32-45-14-420-050-A ** ON A/C NOT FOR ALL
A. Installation of the Parking Brake Valve 2579GM
   (1) Apply the Polysulfide Sealant-Low Adhesion Brushable - (Material No.
06AEA1) to the component interface.
   (2) Put the parking brake valve (2) in position and install the washers (7) and the bolts (8).
   (3) Remove the blanking plugs.
   (4) Put the new packing (3) on the union (4) and install the union (4) in the parking brake valve (2).
   (5) TORQUE the union (4) to between 3.47 and 3.19 m.daN (25.59 and 23.53 lbf.ft ) T.
   (6) Connect the connector (5) to the union (4) and the connectors (1) and (6) to the parking brake valve (2).
   (7) Use a second WRENCH - STANDARD to hold the applicable unions and TORQUE the connectors (5) and (6) to between 5.9 and 5.4 m.daN (43.51 and 39.82 lbf.ft )
T (Ref. AMM TASK 20-23-11-917-001).
   (8) Use a second WRENCH - STANDARD to hold the applicable union and TORQUE the connector (1) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft ) T (Ref. AMM TASK 20-23-11-917-001).
   (9) Put a mark on the connectors with the Top Coat Polyurethane-- Decorative Furnishing (Material No.04JMD9) .
Subtask 32-45-14-865-053-A ** ON A/C NOT FOR ALL
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
49VUL/G/Y BRK/PRESS/IND61GGC10
121VUHYDRAULIC/BRAKING AND STEERING/SYS2/SPLY4GGM36
121VUHYDRAULIC/BRAKING AND STEERING/SYS2/CTL3GGM35
121VUHYDRAULIC/BRAKING AND STEERING/SYS1/CTL1GGM34
121VUHYDRAULIC/BRAKING AND STEERING/SYS1/IND AND/SPLY2GGM33
121VUHYDRAULIC/PARK BRK/CTL/STBY71GGN37
121VUHYDRAULIC/PARK BRK/CTL/NORM70GGN36
121VUHYDRAULIC/HYD POWER/Y3803GXN30
121VUHYDRAULIC/Y HYD/PUMP ENG2/MONG3700GDQ37
121VUHYDRAULIC/Y HYD/PUMP ENG2/CTL3701GDQ36
123VUY HYD/ELEC/PUMP3802GXAB06
123VUY HYD/ELEC/ELEC PUMP/NORM3801GXAB03
Subtask 32-45-14-860-052-A ** ON A/C NOT FOR ALL
C. Preparation for Installation
   (1) Connect the PTU isolation coupling (Ref. AMM TASK 29-23-00-860-001).
   (2) Bleed the alternate brake system (Ref. AMM TASK 32-43-00-870-002).
Subtask 32-45-14-710-050-A ** ON A/C NOT FOR ALL
D. Test
   (1) Do the operational check of the parking brake system (Ref. AMM TASK 32-45-00-710-001).
   (2) Do the operational check of the alternate braking with anti skid (Ref. AMM TASK 32-43-00-710-001).
   (3) Make sure that there is no hydraulic fluid leakage from the parking brake valve 2579GM. Leaks are not permitted.
5. Close-up
Subtask 32-45-14-410-050-A ** ON A/C NOT FOR ALL
A. Close Access
   (1) Apply corrosion protection to the bolt heads, connectors and the adjacent areas (Ref. AMM TASK 51-75-13-916-002).
   (2) Remove the container.
   (3) Remove the WARNING NOTICE(S).
   (4) Remove the access platform(s).
   (5) Make sure that the work area is clean and clear of tools and other items.
   (6) Close the right MLG door (Ref. AMM TASK 32-12-00-410-001).
   (7) If necessary fill the reservoir of the Yellow hydraulic system to the correct level (Ref. AMM TASK 12-12-29-611-001).
   (8) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
[Rev.10 from 2021] 2026.04.01 00:49:55 UTC