Installation of the Manifold Assembly
TASK 32-31-36-400-802-A
Installation of the Manifold Assembly
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
C. Work Zones and Access Panels
D. Expendable Parts
E. Referenced Information
3. Job Set-up
Subtask 32-31-36-860-054-A
Subtask 32-31-36-110-051-A
Subtask 32-31-36-865-055-A
[Rev.10 from 2021]
2026.04.01 00:45:10 UTC
Installation of the Manifold Assembly
WARNING:
MAKE SURE THAT ALL THE CIRCUITS IN MAINTENANCE ARE ISOLATED BEFORE YOU SUPPLY ELECTRICAL POWER TO THE AIRCRAFT. UNWANTED ELECTRICAL POWER CAN BE DANGEROUS.
WARNING:
PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU START A TASK ON OR NEAR:
- THE FLIGHT CONTROLS
- THE FLIGHT CONTROL SURFACES
- THE LANDING GEAR AND THE RELATED DOORS
- COMPONENTS THAT MOVE.
WARNING:
OBEY THE HYDRAULIC SAFETY PROCEDURES.
WARNING:
BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
ZONE: 734
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.02ABA1) | Phosphate Ester Hydraulic Fluid-General Power - - |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 734 | MAIN DOOR |
| FIG.ITEM | DESIGNATION | IPC-CSN |
|---|---|---|
| 3 | PACKING | AIPC 32-31-03-10-240 |
| 3 | PACKING | AIPC 32-31-83-04-180 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 12-12-29-611-001-A | Fill the Hydraulic Fluid Reservoir with a Hand Pump |
| TASK 20-23-22-910-001-A | Marking of the Unions after Application of Standard or Specific Tightening Torque |
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 29-00-00-910-002-A | Safety Procedures of the Hydraulic System |
| TASK 29-10-00-863-001-A | Pressurize the Green Hydraulic System with a Hydraulic Ground Power-Cart |
| TASK 29-10-00-864-001-A | Depressurize the Green Hydraulic System |
| TASK 29-14-00-614-001-A | Depressurization of the Hydraulic Reservoirs |
| TASK 29-23-00-860-001-A | Disconnection of the Isolation Coupling of the Power Transfer Unit (PTU) |
| TASK 29-23-00-860-002-A | Connection of the Isolation Coupling of the Power Transfer Unit (PTU) |
| TASK 32-00-00-081-002-A | Removal of the Safety Devices from the Landing Gear Doors |
| TASK 32-00-00-481-002-A | Installation of the Safety Devices on the Landing Gear Doors |
| TASK 32-00-00-860-001-A | Flight Configuration Precautions with Electrical Power |
| TASK 32-00-00-860-001-A-01 | Flight Configuration Precautions without Electrical Power |
| TASK 32-00-00-860-002-A | Ground Configuration after Flight Configuration with Electrical Power |
| TASK 32-00-00-860-002-A-01 | Ground Configuration after Flight Configuration without Electrical Power |
| TASK 32-12-00-010-001-A | Open the Main Gear Doors for Access |
| TASK 32-12-00-410-001-A | Close the Main Gear Doors after Access |
| TASK 32-31-36-400-001-A | Installation of the MLG Check Valves |
| TASK 32-33-00-720-001-A | Functional Check of Free-Fall Extension |
| TASK 51-75-13-916-002-A | Repair to a layer of Corrosion Preventive Compound |
Subtask 32-31-36-860-054-A
A. Aircraft Maintenance Configuration
(1) Make sure that the aircraft electrical circuits are energized.
(Ref. AMM TASK 24-41-00-861-002).
(2) Make sure that the Green hydraulic system is depressurized
(Ref. AMM TASK 29-10-00-864-001).
(3) Make sure that the left MLG door is open (Ref. AMM TASK 32-12-00-010-001).
(4) Make sure that the safety devices are installed on the left MLG door (Ref. AMM TASK 32-00-00-481-002).
(5) Make sure that the reservoir of the Green hydraulic system is depressurized
(Ref. AMM TASK 29-14-00-614-001).
(6) Make sure that the PTU isolation coupling is disconnected (Ref. AMM TASK 29-23-00-860-001).
(7) Make sure that the WARNING NOTICE(S) are in position to tell persons not to pressurize the Green hydraulic system:
(9) Obey the hydraulic safety procedures (Ref. AMM TASK 29-00-00-910-002).
(10) Make sure that the ACCESS PLATFORM 1M(3 FT) is in position at zone 734.
(11) Make sure that the CONTAINER - HYDRAULIC FLUID RESISTANT is in position below the disconnected line ends to collect unwanted hydraulic fluid.
Subtask 32-31-36-865-054-A (1) Make sure that the aircraft electrical circuits are energized.
(Ref. AMM TASK 24-41-00-861-002).
(2) Make sure that the Green hydraulic system is depressurized
(Ref. AMM TASK 29-10-00-864-001).
(3) Make sure that the left MLG door is open (Ref. AMM TASK 32-12-00-010-001).
(4) Make sure that the safety devices are installed on the left MLG door (Ref. AMM TASK 32-00-00-481-002).
(5) Make sure that the reservoir of the Green hydraulic system is depressurized
(Ref. AMM TASK 29-14-00-614-001).
(6) Make sure that the PTU isolation coupling is disconnected (Ref. AMM TASK 29-23-00-860-001).
(7) Make sure that the WARNING NOTICE(S) are in position to tell persons not to pressurize the Green hydraulic system:
- On panel 40VU in the cockpit
- On the ground service panel of the Green hydraulic system.
(9) Obey the hydraulic safety procedures (Ref. AMM TASK 29-00-00-910-002).
(10) Make sure that the ACCESS PLATFORM 1M(3 FT) is in position at zone 734.
(11) Make sure that the CONTAINER - HYDRAULIC FLUID RESISTANT is in position below the disconnected line ends to collect unwanted hydraulic fluid.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | L/G/LGCIU/SYS1/NORM | 1GA | C09 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | HYDRAULIC/G HYD/PUMP ENG1/CTL | 1701GK | H12 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/CTL | 1701GK | R35 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/MONG | 1702GK | R34 |
| 121VU | LGCIU/BAT SPLY/SYS2 | 59GA | R33 |
| 121VU | LGCIU/BAT SPLY/SYS1 | 58GA | R32 |
| ** ON A/C ALL | |||
| 121VU | HYDRAULIC/LGCIU/SYS2 | 2GA | Q35 |
| 121VU | HYDRAULIC/LGCIU/SYS1/GRND SPLY | 52GA | Q34 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/MONG | 1702GK | R33 |
| 121VU | LGCIU/BAT SPLY/SYS2 | 59GA | R32 |
| 121VU | LGCIU/BAT SPLY/SYS1 | 58GA | R31 |
Subtask 32-31-36-110-051-A
A. Preparation for Installation
(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Make sure that the parts retained from the removed component are clean and in the correct condition.
Subtask 32-31-36-420-055-A (1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Make sure that the parts retained from the removed component are clean and in the correct condition.
B. Installation of the Manifold Assembly
(2) Install the washers (5) and the bolts (6).
(3) Tighten the bolts (6).
(4) Apply Phosphate Ester Hydraulic Fluid-General Power - - (Material No.02ABA1) to the:
(6) Install the reducer (2) on the manifold (4).
(7) TORQUE the reducer (2) to between 4.61 and 4.32 m.daN (34.00 and 31.86 lbf.ft )
.
(8) Remove the PLUG - BLANKING from the disconnected end of the hydraulic line (1).
(9) Connect the hydraulic line (1) to the reducer (2).
(10) TORQUE the nut of the hydraulic line (1) to between 3.20 and 2.90 m.daN (23.60 and 21.39 lbf.ft )
.
(11) Install the MLG check valves (7) and (8) (Ref. AMM TASK 32-31-36-400-001).
(12) Identify the tightened union nuts with a red line
(Ref. AMM TASK 20-23-22-910-001).
5. Close-upCAUTION:
USE A SECOND WRENCH TO APPLY COUNTERTORQUE TO THE UNION WHEN YOU DISCONNECT/CONNECT HYDRAULIC LINES ON UNIONS. IF YOU DO NOT USE THE SECOND WRENCH, THERE IS A RISK THAT YOU WILL LOOSEN OR TIGHTEN THE UNION TOO MUCH.
(1) Put the manifold (4) in position on the bracket (9). (2) Install the washers (5) and the bolts (6).
(3) Tighten the bolts (6).
(4) Apply Phosphate Ester Hydraulic Fluid-General Power - - (Material No.02ABA1) to the:
- Threads of the reducer (2)
- New AIPC 32-31-03-10-240 PACKING (3) or the new AIPC 32-31-83-04-180 PACKING (3).
(6) Install the reducer (2) on the manifold (4).
(7) TORQUE the reducer (2) to between 4.61 and 4.32 m.daN (34.00 and 31.86 lbf.ft )
. (8) Remove the PLUG - BLANKING from the disconnected end of the hydraulic line (1).
(9) Connect the hydraulic line (1) to the reducer (2).
(10) TORQUE the nut of the hydraulic line (1) to between 3.20 and 2.90 m.daN (23.60 and 21.39 lbf.ft )
. (11) Install the MLG check valves (7) and (8) (Ref. AMM TASK 32-31-36-400-001).
(12) Identify the tightened union nuts with a red line
(Ref. AMM TASK 20-23-22-910-001).
Subtask 32-31-36-865-055-A
A. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 32-31-36-860-056-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | L/G/LGCIU/SYS1/NORM | 1GA | C09 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | HYDRAULIC/G HYD/PUMP ENG1/CTL | 1701GK | H12 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/CTL | 1701GK | R35 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/MONG | 1702GK | R34 |
| 121VU | LGCIU/BAT SPLY/SYS2 | 59GA | R33 |
| 121VU | LGCIU/BAT SPLY/SYS1 | 58GA | R32 |
| ** ON A/C ALL | |||
| 121VU | HYDRAULIC/LGCIU/SYS2 | 2GA | Q35 |
| 121VU | HYDRAULIC/LGCIU/SYS1/GRND SPLY | 52GA | Q34 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | HYDRAULIC/G HYD/PUMP ENG1/MONG | 1702GK | R33 |
| 121VU | LGCIU/BAT SPLY/SYS2 | 59GA | R32 |
| 121VU | LGCIU/BAT SPLY/SYS1 | 58GA | R31 |
B. Preparation for Test
(1) Connect the PTU isolation coupling (Ref. AMM TASK 29-23-00-860-002).
(2) If the flight configuration precautions were obeyed, put the aircraft back to the ground configuration (Ref. AMM TASK 32-00-00-860-002).
(3) Remove the CONTAINER - HYDRAULIC FLUID RESISTANT.
(4) Remove the WARNING NOTICE(S).
(5) Remove the access platform(s).
(6) Close the left MLG door (Ref. AMM TASK 32-12-00-410-001).
(7) If necessary, fill the reservoir of the Green hydraulic system to the correct level (Ref. AMM TASK 12-12-29-611-001).
Subtask 32-31-36-720-051-A (1) Connect the PTU isolation coupling (Ref. AMM TASK 29-23-00-860-002).
(2) If the flight configuration precautions were obeyed, put the aircraft back to the ground configuration (Ref. AMM TASK 32-00-00-860-002).
(3) Remove the CONTAINER - HYDRAULIC FLUID RESISTANT.
(4) Remove the WARNING NOTICE(S).
(5) Remove the access platform(s).
(6) Close the left MLG door (Ref. AMM TASK 32-12-00-410-001).
(7) If necessary, fill the reservoir of the Green hydraulic system to the correct level (Ref. AMM TASK 12-12-29-611-001).
C. Test(s)
(1) Do a functional check of free-fall extension (Ref. AMM TASK 32-33-00-720-001).
(2) Open the left MLG door (Ref. AMM TASK 32-12-00-010-001).
(3) Put the ACCESS PLATFORM 1M(3 FT) in position.
(4) Make sure that there is no hydraulic fluid leakage from the check valve(s).
Subtask 32-31-36-410-052-A (1) Do a functional check of free-fall extension (Ref. AMM TASK 32-33-00-720-001).
(2) Open the left MLG door (Ref. AMM TASK 32-12-00-010-001).
(3) Put the ACCESS PLATFORM 1M(3 FT) in position.
(4) Make sure that there is no hydraulic fluid leakage from the check valve(s).
D. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Apply corrosion protection to the check valve(s), the pipe connections and the adjacent areas (Ref. AMM TASK 51-75-13-916-002).
(3) Remove the safety devices from the left MLG door (Ref. AMM TASK 32-00-00-081-002).
(4) Remove the ACCESS PLATFORM 1M(3 FT).
(5) Close the left MLG door (Ref. AMM TASK 32-12-00-410-001).
Subtask 32-31-36-863-050-A (1) Make sure that the work area is clean and clear of tools and other items.
(2) Apply corrosion protection to the check valve(s), the pipe connections and the adjacent areas (Ref. AMM TASK 51-75-13-916-002).
(3) Remove the safety devices from the left MLG door (Ref. AMM TASK 32-00-00-081-002).
(4) Remove the ACCESS PLATFORM 1M(3 FT).
(5) Close the left MLG door (Ref. AMM TASK 32-12-00-410-001).
E. Pressurization of the Hydraulic System
(1) Pressurize the Green hydraulic system (Ref. AMM TASK 29-10-00-863-001).
Subtask 32-31-36-862-050-A (1) Pressurize the Green hydraulic system (Ref. AMM TASK 29-10-00-863-001).
F. Put the aircraft back to its initial configuration.
(1) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
Subtask 32-31-36-942-053-A (1) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
G. Removal of Equipment
(1) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
(1) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
Manifold Assembly