Installation of the Actuator of the NLG Uplock Assy
TASK 32-31-21-400-002-A
Installation of the Actuator of the NLG Uplock Assy
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
C. Referenced Information
3. Job Set-up
Subtask 32-31-21-860-053-A
Subtask 32-31-21-110-051-A
Subtask 32-31-21-410-051-A
[Rev.10 from 2021]
2026.04.01 00:44:48 UTC
Installation of the Actuator of the NLG Uplock Assy
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Consumable Materials
| REFERENCE | DESIGNATION |
|---|---|
| (Material No.06LDG2) | Non Hardening Jointing Putty-High Temp. Area - Structure |
| (Material No.08BBB1) | Non Aqueous Cleaner-- Petroleum Based - |
| (Material No.14QFB1) | Wire-Locking Dia: 0.8 mm CRES Nickel Alloy - |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 29-00-00-864-001-A | Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action |
| TASK 29-14-00-614-001-A | Depressurization of the Hydraulic Reservoirs |
| TASK 32-00-00-860-001-A | Flight Configuration Precautions with Electrical Power |
| TASK 32-00-00-860-001-A-01 | Flight Configuration Precautions without Electrical Power |
| TASK 32-00-00-860-002-A | Ground Configuration after Flight Configuration with Electrical Power |
| TASK 32-00-00-860-002-A-01 | Ground Configuration after Flight Configuration without Electrical Power |
| TASK 32-22-00-010-001-A | Nose Gear Doors - Ground Doors Opening |
| TASK 32-22-00-410-001-A | Nose Gear Doors - Ground Doors Closing |
| TASK 32-30-00-867-001-A | Retraction of the Landing Gears for Maintenance |
| TASK 32-30-00-867-002-A | Extension of the Landing Gears after Maintenance |
| TASK 32-31-00-720-003-A | Functional Test of the Normal Extension and Retraction of the Nose Landing Gear |
Subtask 32-31-21-860-053-A
A. Aircraft Maintenance Configuration
(1) Make sure that the Green hydraulic system is depressurized and put it in the maintenance configuration.
(Ref. AMM TASK 29-00-00-864-001)
(2) Make sure that the reservoir of the Green hydraulic system is depressurized (Ref. AMM TASK 29-14-00-614-001).
(3) In the cockpit, on the panel 400VU, make sure that the WARNING NOTICE(S) is (are) in position to tell persons not to operate the landing gear control lever.
(4) Make sure that the WARNING NOTICE(S) is (are) in position to tell persons not to pressurize the Green hydraulic system:
(6) Make sure that the CONTAINER 5 L (1.32 USGAL) is in position below the NLG uplock assy (2530GM).
(7) Make sure that the doors of the nose landing gear are open (Ref. AMM TASK 32-22-00-010-001).
(8) Make sure that the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE is in position in zone 123.
(9) Make sure that you obeyed the flight configuration precautions (Ref. AMM TASK 32-00-00-860-001).
Subtask 32-31-21-865-055-A (1) Make sure that the Green hydraulic system is depressurized and put it in the maintenance configuration.
(Ref. AMM TASK 29-00-00-864-001)
(2) Make sure that the reservoir of the Green hydraulic system is depressurized (Ref. AMM TASK 29-14-00-614-001).
(3) In the cockpit, on the panel 400VU, make sure that the WARNING NOTICE(S) is (are) in position to tell persons not to operate the landing gear control lever.
(4) Make sure that the WARNING NOTICE(S) is (are) in position to tell persons not to pressurize the Green hydraulic system:
- on the panel 40VU in the cockpit,
- on the ground service panel of the Green hydraulic system, access door (197CB).
(6) Make sure that the CONTAINER 5 L (1.32 USGAL) is in position below the NLG uplock assy (2530GM).
(7) Make sure that the doors of the nose landing gear are open (Ref. AMM TASK 32-22-00-010-001).
(8) Make sure that the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE is in position in zone 123.
(9) Make sure that you obeyed the flight configuration precautions (Ref. AMM TASK 32-00-00-860-001).
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | L/G/LGCIU/SYS1/NORM | 1GA | C09 |
| 121VU | HYDRAULIC/LGCIU/SYS2 | 2GA | Q35 |
| 121VU | HYDRAULIC/LGCIU/SYS1/GRND SPLY | 52GA | Q34 |
Subtask 32-31-21-110-051-A
A. Preparation for Installation
(1) Clean the surfaces and the connection elements with Non Aqueous Cleaner-- Petroleum Based - (Material No.08BBB1) and dry with filtered compressed air.
(2) Apply Non Hardening Jointing Putty-High Temp. Area - Structure (Material No.06LDG2) to the threads of the screws (1).
Subtask 32-31-21-420-053-A (1) Clean the surfaces and the connection elements with Non Aqueous Cleaner-- Petroleum Based - (Material No.08BBB1) and dry with filtered compressed air.
(2) Apply Non Hardening Jointing Putty-High Temp. Area - Structure (Material No.06LDG2) to the threads of the screws (1).
B. Installation of the Actuator of the NLG Uplock Assy
(1) Put the actuator (2) in position on the NLG uplock.
(2) Install and tighten the three screws (1) on the actuator (2).
(3) Safety the three screws (1) with14QFB1 Wire-Locking Dia: 0.8 mm CRES Nickel Alloy - .
(4) Remove the blanking plugs from the disconnected line ends of the hydraulic lines (3) and (4).
(5) Connect the hydraulic lines (3) and (4) to the actuator (2).
(6) TORQUE the hydraulic lines (3) and (4) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
.
Subtask 32-31-21-865-056-A (1) Put the actuator (2) in position on the NLG uplock.
(2) Install and tighten the three screws (1) on the actuator (2).
(3) Safety the three screws (1) with
(4) Remove the blanking plugs from the disconnected line ends of the hydraulic lines (3) and (4).
(5) Connect the hydraulic lines (3) and (4) to the actuator (2).
(6) TORQUE the hydraulic lines (3) and (4) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
. C. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 32-31-21-869-054-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | L/G/LGCIU/SYS1/NORM | 1GA | C09 |
| 121VU | HYDRAULIC/LGCIU/SYS2 | 2GA | Q35 |
| 121VU | HYDRAULIC/LGCIU/SYS1/GRND SPLY | 52GA | Q34 |
D. After you close the LGCIU circuit breakers, put the aircraft back to the correct (ground) condition (Ref. AMM TASK 32-00-00-860-002).
Subtask 32-31-21-941-055-A E. Preparation for the Test
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Remove the container below the NLG uplock assy (2530GM).
(3) Make sure that the NLG uplock assy (2530GM) is in the open configuration.
(4) Make sure that the travel range of the landing gear is clean.
(5) Remove the access platform below the NLG uplock assy (2530GM).
(6) Close the NLG doors (Ref. AMM TASK 32-22-00-410-001).
(7) Do 5 full retraction and extension cycles of the nose landing gear at very low speed to bleed the Green hydraulic system (Ref. AMM TASK 32-30-00-867-001) and (Ref. AMM TASK 32-30-00-867-002).
Subtask 32-31-21-720-051-A (1) Make sure that the work area is clean and clear of tools and other items.
(2) Remove the container below the NLG uplock assy (2530GM).
(3) Make sure that the NLG uplock assy (2530GM) is in the open configuration.
(4) Make sure that the travel range of the landing gear is clean.
(5) Remove the access platform below the NLG uplock assy (2530GM).
(6) Close the NLG doors (Ref. AMM TASK 32-22-00-410-001).
(7) Do 5 full retraction and extension cycles of the nose landing gear at very low speed to bleed the Green hydraulic system (Ref. AMM TASK 32-30-00-867-001) and (Ref. AMM TASK 32-30-00-867-002).
F. Functional Test
(1) Do the operational test of the NLG normal extension and retraction (Ref. AMM TASK 32-31-00-720-003).
(2) Make sure that there are no leaks on the disconnected line ends.
5. Close-up(1) Do the operational test of the NLG normal extension and retraction (Ref. AMM TASK 32-31-00-720-003).
(2) Make sure that there are no leaks on the disconnected line ends.
Subtask 32-31-21-410-051-A
A. Close Access
(1) Remove the WARNING NOTICE(S).
(2) Remove the access platform(s).
(3) Make sure that the work area is clean and clear of tools and other items.
(4) Close the doors of the nose landing gear (Ref. AMM TASK 32-22-00-410-001).
(1) Remove the WARNING NOTICE(S).
(2) Remove the access platform(s).
(3) Make sure that the work area is clean and clear of tools and other items.
(4) Close the doors of the nose landing gear (Ref. AMM TASK 32-22-00-410-001).
Actuator of the NLG Uplock Assy