W DOC AIRBUS | AMM A320F

Display Units Swapping procedure


TASK 31-63-22-400-002-A
Display Units Swapping procedure


ZONE: 210
FIN: 2WT1 ** ON A/C NOT FOR ALL
FIN: 2WT2 ** ON A/C NOT FOR ALL
FIN: 3WT1 ** ON A/C NOT FOR ALL
FIN: 3WT2 ** ON A/C NOT FOR ALL
FIN: 4WT1 ** ON A/C NOT FOR ALL
FIN: 4WT2 ** ON A/C NOT FOR ALL
1. Reason for the Job
Refer to the MPD TASK: 316322-01
REPOSITION ALL CATHODE RAY TUBES BY SWAPPING ALL DISPLAY UNITS FROM ONE POSITION(PFD,ND, UPPER ECAM,LOWER ECAM)TO ANOTHER
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
1
ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
210
CKPT,FWD COMPT BHD TO FLT COMPT BULKHEAD
811
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 22-97-00-710-001-A
Operational Test of the LAND CAT III Capability
TASK 31-60-00-710-001-A
Operational Test of the EIS
TASK 52-41-00-410-002-A
Close the Avionics Compartment Doors after Access
3. Job Set-up
Subtask 31-63-22-860-054-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
   (1) Make sure that the ground service network is energized
   (2) Make sure that the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE is in position at the access door 811.
   (3) Make sure that the access door 811 is open.

Subtask 31-63-22-865-053-A ** ON A/C NOT FOR ALL
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
49VUEIS/PFD CAPT/SPLY11WT1E03
** ON A/C NOT FOR ALL
49VUEIS/ECAM DU/UPPER/SWTG24WT1E06
49VUEIS/ECAM DU/UPPER/SPLY13WT1E05
49VUEIS/PFD CAPT/SWTG22WT1E04
49VUEIS/ND CAPT/SWTG23WT1E02
49VUEIS/ND CAPT/SPLY12WT1E01
** ON A/C NOT FOR ALL
49VUEIS/PFD/CAPT/SPLY11WT1E03
** ON A/C NOT FOR ALL
121VUEIS/ECAM DU/LOWER/SPLY13WT2R11
121VUEIS/ECAM DU/LOWER/SWTG24WT2R10
121VUEIS/ND/F/O/SWTG23WT2R06
121VUEIS/PFD/F/O/SWTG22WT2R05
121VUEIS/ND/F/O12WT2R04
121VUEIS/PFD/F/O11WT2R03
4. Procedure
Subtask 31-63-22-020-051-A ** ON A/C NOT FOR ALL
A. Removal of the PFD CAPT (2WT1)
NOTE: IF THE OPERATOR TAKES ADVANTAGE OF A SCHEDULED REMOVAL TO PROCEED TO THE SWAPPING PROCEDURE IT IS POSIBLE TO START FROM ANY OTHER DU THAN THE PFD CAPT PROVIDED THE SWAPPING IS ACHIEVED IN THE SAME DIRECTION (FOR EXAMPLE THE DUs MOVING COUNTERCLOCKWISE AS MENTIONNED)
F Display Unit ** ON A/C NOT FOR ALL
   (1) Remove the thermoformed cover from the CAPT main instrument panel.
   (2) Push in the two locking catches (4).
   (3) If necessary, push up the handle (3) to decrease the load applied to the locking catches (4): the handle falls to the level of the studs.
   (4) Slowly and continuously lower the handle (3) to the bottom section of the screen: at the same time, the unit (2) moves out from the panel by approximately 3 cm.
   (5) Pull the handle (3) found at the removal point and disengage the unit (2).
   (6) Remove the unit (2).
   (7) Put the unit aside, and retain it to be installed as the last one of the six display units.

Subtask 31-63-22-020-052-A ** ON A/C NOT FOR ALL
B. Removal of the ND CAPT (3WT1)
   (1) Push in the two locking catches (4).
   (2) If necessary, push up the handle (3) to decrease the load applied to the locking catches (4): the handle falls to the level of the studs.
   (3) Slowly and continuously lower the handle (3) to the bottom section of the screen: at the same time, the unit (2) moves out from the panel by approximately 3 cm.
   (4) Pull the handle (3) found at the removal point and disengage the unit (2).
   (5) Remove the unit (2).

Subtask 31-63-22-420-051-A ** ON A/C NOT FOR ALL
C. Installation of the ND CAPT in place of the PFD CAPT
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) In the housing (8), make sure that:
  • the ventilation air inlet (7) is in the correct condition (flexible seal installed and duct not blocked)
  • the locking studs (5) and the movable locking hooks (6) are not damaged.
   (4) Make sure that all the electrical connections are clean and in the correct condition.
   (5) Install the unit (2) in the panel opening previously fitted with the PFD just removed.
Fully move down the handle (3) to the bottom of the screen.
   (6) Push the unit until the locking studs (5) touch the movable locking hooks (at this time, the face of the unit must be out of the panel by approximately 3 cm).
   (7) Push the two sides of the unit (2) to connect the electrical connector (1). Let the handle (3) move up freely until it is at the level of the locking catches (4) (the unit is now in line with the panel).
   (8) Slowly and continuously move the handle (3) to its maximum position. In this position the two locking catches (4) are locked under the handle (3).

Subtask 31-63-22-020-053-A ** ON A/C NOT FOR ALL
D. Removal of the upper ECAM DU (4WT1)
   (1) Remove the thermoformed cover from the center instrument panel.
   (2) Push in the two locking catches (4).
   (3) If necessary, push up the handle (3) to decrease the load applied to the locking catches (4): the handle falls to the level of the studs.
   (4) Slowly and continuously lower the handle (3) to the bottom section of the screen: at the same time, the unit (2) moves out from the panel by approximately 3 cm.
   (5) Pull the handle (3) found at the removal point and disengage the unit (2).
   (6) Remove the unit (2).

Subtask 31-63-22-420-052-A ** ON A/C NOT FOR ALL
E. Installation of the upper ECAM DU in place of the ND CAPT
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) In the housing (8), make sure that:
  • the ventilation air inlet (7) is in the correct condition (flexible seal installed and duct not blocked)
  • the locking studs (5) and the movable locking hooks (6) are not damaged.
   (4) Make sure that all the electrical connections are clean and in the correct condition.
   (5) Install the unit (2) in the panel opening previously fitted with the ND just removed.
Fully move down the handle (3) to the bottom of the screen.
   (6) Push the unit until the locking studs (5) touch the movable locking hooks (at this time, the face of the unit must be out of the panel by approximately 3 cm).
   (7) Push the two sides of the unit (2) to connect the electrical connector (1). Let the handle (3) move up freely until it is at the level of the locking catches (4) (the unit is now in line with the panel).
   (8) Slowly and continuously move the handle (3) to its maximum position. In this position the two locking catches (4) are locked under the handle (3).

Subtask 31-63-22-020-054-A ** ON A/C NOT FOR ALL
F. Removal of the ND F/0 (3WT2)
Remove the thermoformed cover from the F/O main instrument panel.
   (1) Push in the two locking catches (4).
   (2) If necessary, push up the handle (3) to decrease the load applied to the locking catches (4): the handle falls to the level of the studs.
   (3) Slowly and continuously lower the handle (3) to the bottom section of the screen: at the same time, the unit (2) moves out from the panel by approximately 3 cm.
   (4) Pull the handle (3) found at the removal point and disengage the unit (2).
   (5) Remove the unit (2).

Subtask 31-63-22-420-053-A ** ON A/C NOT FOR ALL
G. Installation of the ND F/O in place of the upper ECAM DU
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) In the housing (8), make sure that:
  • the ventilation air inlet (7) is in the correct condition (flexible seal installed and duct not blocked)
  • the locking studs (5) and the movable locking hooks (6) are not damaged.
   (4) Make sure that all the electrical connections are clean and in the correct condition.
   (5) Install the unit (2) in the panel opening previously fitted with the upper ECAM DU just removed.
Fully move down the handle (3) to the bottom of the screen.
   (6) Push the unit until the locking studs (5) touch the movable locking hooks (at this time, the face of the unit must be out of the panel by approximately 3 cm).
   (7) Push the two sides of the unit (2) to connect the electrical connector (1). Let the handle (3) move up freely until it is at the level of the locking catches (4) (the unit is now in line with the panel).
   (8) Slowly and continuously move the handle (3) to its maximum position. In this position the two locking catches (4) are locked under the handle (3).

Subtask 31-63-22-020-055-A ** ON A/C NOT FOR ALL
H. Removal of the PFD F/0 (2WT2)
   (1) Push in the two locking catches (4).
   (2) If necessary, push up the handle (3) to decrease the load applied to the locking catches (4): the handle falls to the level of the studs.
   (3) Slowly and continuously lower the handle (3) to the bottom section of the screen: at the same time, the unit (2) moves out from the panel by approximately 3 cm.
   (4) Pull the handle (3) found at the removal point and disengage the unit (2).
   (5) Remove the unit (2).

Subtask 31-63-22-420-054-A ** ON A/C NOT FOR ALL
I. Installation of the PFD F/O in place of the ND F/O
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) In the housing (8), make sure that:
  • the ventilation air inlet (7) is in the correct condition (flexible seal installed and duct not blocked)
  • the locking studs (5) and the movable locking hooks (6) are not damaged.
   (4) Make sure that all the electrical connections are clean and in the correct condition.
   (5) Install the unit (2) in the panel opening previously fitted with the ND just removed.
Fully move down the handle (3) to the bottom of the screen.
   (6) Push the unit until the locking studs (5) touch the movable locking hooks (at this time, the face of the unit must be out of the panel by approximately 3 cm).
   (7) Push the two sides of the unit (2) to connect the electrical connector (1). Let the handle (3) move up freely until it is at the level of the locking catches (4) (the unit is now in line with the panel).
   (8) Slowly and continuously move the handle (3) to its maximum position. In this position the two locking catches (4) are locked under the handle (3).

Subtask 31-63-22-020-056-A ** ON A/C NOT FOR ALL
J. Removal of the lower ECAM DU (4WT2)
   (1) Push in the two locking catches (4).
   (2) If necessary, push up the handle (3) to decrease the load applied to the locking catches (4): the handle falls to the level of the studs.
   (3) Slowly and continuously lower the handle (3) to the bottom section of the screen: at the same time, the unit (2) moves out from the panel by approximately 3 cm.
   (4) Pull the handle (3) found at the removal point and disengage the unit (2).
   (5) Remove the unit (2).

Subtask 31-63-22-420-055-A ** ON A/C NOT FOR ALL
K. Installation of the lower ECAM DU in place of the PFD F/O
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) In the housing (8), make sure that:
  • the ventilation air inlet (7) is in the correct condition (flexible seal installed and duct not blocked)
  • the locking studs (5) and the movable locking hooks (6) are not damaged.
   (4) Make sure that all the electrical connections are clean and in the correct condition.
   (5) Install the unit (2) in the panel opening previously fitted with the PFD just removed.
Fully move down the handle (3) to the bottom of the screen.
   (6) Push the unit until the locking studs (5) touch the movable locking hooks (at this time, the face of the unit must be out of the panel by approximately 3 cm).
   (7) Push the two sides of the unit (2) to connect the electrical connector (1). Let the handle (3) move up freely until it is at the level of the locking catches (4) (the unit is now in line with the panel).
   (8) Slowly and continuously move the handle (3) to its maximum position. In this position the two locking catches (4) are locked under the handle (3).

Subtask 31-63-22-420-056-A ** ON A/C NOT FOR ALL
L. Installation of the remaining PFD CAPT in place of the lower ECAM DU
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) In the housing (8), make sure that:
  • the ventilation air inlet (7) is in the correct condition (flexible seal installed and duct not blocked)
  • the locking studs (5) and the movable locking hooks (6) are not damaged.
   (4) Make sure that all the electrical connections are clean and in the correct condition.
   (5) Install the unit (2) in the panel opening previously fitted with the just removed lower ECAM DU.
Fully move down the handle (3) to the bottom of the screen.
   (6) Push the unit until the locking studs (5) touch the movable locking hooks (at this time, the face of the unit must be out of the panel by approximately 3 cm).
   (7) Push the two sides of the unit (2) to connect the electrical connector (1). Let the handle (3) move up freely until it is at the level of the locking catches (4) (the unit is now in line with the panel).
   (8) Slowly and continuously move the handle (3) to its maximum position. In this position the two locking catches (4) are locked under the handle (3).
Install the thermoformed cover on the CAPT main instrument panel.
Install the thermoformed cover on the F/O main instrument panel.
Install the thermoformed cover on the center instrument panel.

Subtask 31-63-22-865-054-A ** ON A/C NOT FOR ALL
M. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
49VUEIS/PFD CAPT/SPLY11WT1E03
** ON A/C NOT FOR ALL
49VUEIS/ECAM DU/UPPER/SWTG24WT1E06
49VUEIS/ECAM DU/UPPER/SPLY13WT1E05
49VUEIS/PFD CAPT/SWTG22WT1E04
49VUEIS/ND CAPT/SWTG23WT1E02
49VUEIS/ND CAPT/SPLY12WT1E01
** ON A/C NOT FOR ALL
49VUEIS/PFD/CAPT/SPLY11WT1E03
** ON A/C NOT FOR ALL
121VUEIS/ECAM DU/LOWER/SPLY13WT2R11
121VUEIS/ECAM DU/LOWER/SWTG24WT2R10
121VUEIS/ND/F/O/SWTG23WT2R06
121VUEIS/PFD/F/O/SWTG22WT2R05
121VUEIS/ND/F/O12WT2R04
121VUEIS/PFD/F/O11WT2R03
Subtask 31-63-22-710-052-A ** ON A/C NOT FOR ALL
N. Do the operational test of the Electronic Instrument System (EIS) (Ref. AMM TASK 31-60-00-710-001).

Subtask 31-63-22-710-053-A ** ON A/C NOT FOR ALL
O. VALID whenever the PFD or ND have been removed:
If the A/C is operated in CAT3 conditions, you must also do this test (Ref. AMM TASK 22-97-00-710-001).

5. Close-up
Subtask 31-63-22-410-050-A ** ON A/C NOT FOR ALL
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Close the access door 811. (Ref. AMM TASK 52-41-00-410-002)
   (3) Remove the access platform(s).