Installation of the SDAC
TASK 31-55-34-400-001-A
Installation of the SDAC
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 31-55-34-860-050-A
Subtask 31-55-34-420-050-A
Subtask 31-55-34-410-050-A
[Rev.10 from 2021]
2026.04.01 00:37:33 UTC
Installation of the SDAC
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 127 | REAR AVIONIC COMPARTMENT |
| 128 | REAR AVIONIC COMPARTMENT |
| 824 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 31-50-00-710-001-A | Ground Scanning of the Central Warning System |
| TASK 31-50-00-710-003-A | Operational Test of the System Data Acquisition Concentrator (SDAC) |
| TASK 52-41-00-010-002-A | Open the Avionics Compartment Doors for Access |
| TASK 52-41-00-410-002-A | Close the Avionics Compartment Doors after Access |
Subtask 31-55-34-860-050-A
A. Aircraft Maintenance Configuration
(1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position at the access door 824 in zone 128.
(2) Make sure that the access door 824 is open (Ref. AMM TASK 52-41-00-010-002).
Subtask 31-55-34-865-054-A (1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position at the access door 824 in zone 128.
(2) Make sure that the access door 824 is open (Ref. AMM TASK 52-41-00-010-002).
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| FOR FIN: 1WV1 (SDAC1) | |||
| 49VU | SDAC/1 AND 2/28VDC/ESS BUS | 12WV | F05 |
| 49VU | SDAC/1/SPLY | 3WV | F04 |
| 49VU | SDAC/1/26VAC SYNC/AC ESS BUS | 5WV | F02 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | EIS/SDAC/1/BUS1/26VAC SYNC AC | 9WV | Q04 |
| ** ON A/C ALL | |||
| 121VU | HYDRAULIC/HYD/QTY/IND | 1831GQ | P35 |
| 121VU | EIS/SDAC/1/BUS2/26VAC SYNC AC | 7WV | Q03 |
| FOR FIN: 1WV2 (SDAC2) | |||
| 49VU | SDAC/1 AND 2/28VDC/ESS BUS | 12WV | F05 |
| 49VU | SDAC/2/26VAC SYNC/AC ESS BUS | 6WV | F03 |
| 121VU | EIS/SDAC/2/SPLY | 2WV | Q06 |
| 121VU | EIS/SDAC/2/BUS1/26VAC SYNC AC | 10WV | Q05 |
| 121VU | EIS/SDAC/2/BUS2/26VAC SYNC AC | 8WV | Q02 |
Subtask 31-55-34-420-050-A
A. Installation of the SDAC
(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Remove blanking caps from the electrical connectors (1).
(4) Make sure that the electrical connectors (1) are in the correct condition.
(5) Install the SDAC (5) on its rack (2).
(6) Push the SDAC (5) on its rack (2) to connect the electrical connectors (1).
Subtask 31-55-34-865-052-A (1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Remove blanking caps from the electrical connectors (1).
(4) Make sure that the electrical connectors (1) are in the correct condition.
(5) Install the SDAC (5) on its rack (2).
(6) Push the SDAC (5) on its rack (2) to connect the electrical connectors (1).
CAUTION:
MAKE SURE THAT THE OBRM(S) IS (ARE) CORRECTLY INSTALLED. IF IT (THEY) IS(ARE) NOT INSTALLED CORRECTLY, PUSH THE OBRM(S) UNTIL THE LOCKING DEVICES ARE LOCKED.
(7) Engage the nuts (3) on the lugs (4) and tighten. B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 31-55-34-710-051-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| FOR FIN: 1WV1 (SDAC1) | |||
| 49VU | SDAC/1 AND 2/28VDC/ESS BUS | 12WV | F05 |
| 49VU | SDAC/1/SPLY | 3WV | F04 |
| 49VU | SDAC/1/26VAC SYNC/AC ESS BUS | 5WV | F02 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | EIS/SDAC/1/BUS1/26VAC SYNC AC | 9WV | Q04 |
| ** ON A/C ALL | |||
| 121VU | HYDRAULIC/HYD/QTY/IND | 1831GQ | P35 |
| 121VU | EIS/SDAC/1/BUS2/26VAC SYNC AC | 7WV | Q03 |
| FOR FIN: 1WV2 (SDAC2) | |||
| 49VU | SDAC/1 AND 2/28VDC/ESS BUS | 12WV | F05 |
| 49VU | SDAC/2/26VAC SYNC/AC ESS BUS | 6WV | F03 |
| 121VU | EIS/SDAC/2/SPLY | 2WV | Q06 |
| 121VU | EIS/SDAC/2/BUS1/26VAC SYNC AC | 10WV | Q05 |
| 121VU | EIS/SDAC/2/BUS2/26VAC SYNC AC | 8WV | Q02 |
C. Do the ground scanning of the Central Warning System (Ref. AMM TASK 31-50-00-710-001)
5. Close-upNOTE: As an alternative procedure, you can do this operational test without the CFDS (Ref. AMM TASK 31-50-00-710-003).
Subtask 31-55-34-410-050-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access door 824 (Ref. AMM TASK 52-41-00-410-002).
(3) Remove the access platform(s).
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access door 824 (Ref. AMM TASK 52-41-00-410-002).
(3) Remove the access platform(s).