W DOC AIRBUS | AMM A320F

Installation of the Clock


TASK 31-21-21-400-001-A
Installation of the Clock


ZONE: 210
FIN: 2FS
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
SAFETY CLIP - CIRCUIT BREAKER
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
210
CKPT,FWD COMPT BHD TO FLT COMPT BULKHEAD
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 31-21-00-710-002-A
Operational Test of the Clock
TASK 31-21-00-750-002-A
Procedure to Set the Clock
3. Job Set-up
Subtask 31-21-21-865-051-A
A. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
49VUCLOCK/NORM/SPLY6FSF11
121VUCLOCK/STBY/SPLY4FSN02
Subtask 31-21-21-865-054-A
B. Open, safety and tag this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
49VUNAV/MMR/142RT1G12
** ON A/C NOT FOR ALL
121VUCOM NAV/MMR/242RT2K09
** ON A/C NOT FOR ALL
121VUCFDS/CFDIU/SPLY2TWJ18
121VUCFDS/CFDIU/BACK/UP8TWJ17
** ON A/C NOT FOR ALL
121VUCOM NAV/MMR/242RT2L07
** ON A/C NOT FOR ALL
121VUCFDS/CFDIU/SPLY2TWJ41
121VUCFDS/CFDIU/BACK/UP8TWJ40
4. Procedure
Subtask 31-21-21-420-050-A ** ON A/C NOT FOR ALL
A. Installation of the Clock
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) Remove the blanking caps from the electrical connectors (3) and (5).
   (4) Make sure that the electrical connectors (3) and (5) are clean and in the correct condition.
   (5) Connect the electrical connector (5) to the clock (2).
   (6) Install the clock (2) in its housing (1).
   (7) Tighten the screws (4).
   (8) Install the thermoformed cover on the center instrument panel.
Subtask 31-21-21-420-050-B ** ON A/C NOT FOR ALL
A. Installation of the Clock
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) Remove the blanking caps from the electrical connectors (3) and (5).
   (4) Make sure that the electrical connectors (3) and (5) are clean and in the correct condition.
   (5) Connect the electrical connector (5) to the clock (2).
   (6) Install the clock (2) in its housing (1).
   (7) Tighten the screws (4).
   (8) Install the thermoformed cover on the center instrument panel.
   (9) Set the GPS/INT/SET selector switch to INT.
Subtask 31-21-21-865-052-A
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
49VUCLOCK/NORM/SPLY6FSF11
121VUCLOCK/STBY/SPLY4FSN02
Subtask 31-21-21-750-050-A
C. Do the procedure to set the clock (Ref. AMM TASK 31-21-00-750-002).
Subtask 31-21-21-710-051-A
D. Do the operational test of the clock (Ref. AMM TASK 31-21-00-710-002)
Subtask 31-21-21-865-053-A
E. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
121VUCFDS/CFDIU/SPLY2TWJ18
121VUCFDS/CFDIU/BACK/UP8TWJ17
** ON A/C NOT FOR ALL
121VUCFDS/CFDIU/SPLY2TWJ41
121VUCFDS/CFDIU/BACK/UP8TWJ40
Subtask 31-21-21-860-050-A
F. The time displayed on the lower ECAM display unit should be in accordance with the clock.
5. Close-up
Subtask 31-21-21-942-050-A
A. Make sure that the work area is clean and clear of tools and other items.