BITE Test of the Drainmast Ice Protection (through CIDS SYSTEM/TEST)
TASK 30-71-00-740-001-A
BITE Test of the Drainmast Ice Protection (through CIDS SYSTEM/TEST)
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 30-71-00-860-052-A ** ON A/C NOT FOR ALL
Subtask 30-71-00-740-050-A ** ON A/C NOT FOR ALL
Subtask 30-71-00-860-053-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.04.01 00:31:44 UTC
BITE Test of the Drainmast Ice Protection (through CIDS SYSTEM/TEST)
ZONE: 210
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 210 | CKPT,FWD COMPT BHD TO FLT COMPT BULKHEAD |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 31-32-00-860-003-A | Procedure to Get Access to the SYSTEM REPORT/TEST/COM Page |
Subtask 30-71-00-860-052-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Energize the aircraft electrical circuits (Ref. AMM TASK 24-41-00-861-002).
(2) Do the procedure to get the SYSTEM REPORT/TEST item COM (Ref. AMM TASK 31-32-00-860-003).
Subtask 30-71-00-865-078-A ** ON A/C NOT FOR ALL (1) Energize the aircraft electrical circuits (Ref. AMM TASK 24-41-00-861-002).
(2) Do the procedure to get the SYSTEM REPORT/TEST item COM (Ref. AMM TASK 31-32-00-860-003).
B. Make sure that this(these) circuit breaker(s) is(are) closed:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 2000VU | WASTE WIP-DRAINMAST-FWD | 1DU | B06 |
| ** ON A/C NOT FOR ALL | |||
| 2000VU | DRAINMAST-FWD | 1DU | B03 |
| ** ON A/C NOT FOR ALL | |||
| 2000VU | WASTE WIP-DRAINMAST-FWD | 1DU | B03 |
| 2000VU | WASTE WIP-HEATER-CTL | 9DU | B02 |
| 2000VU | WASTE WIP-HEATER-LINE | 8DU | B01 |
| ** ON A/C NOT FOR ALL | |||
| 2000VU | WASTE WIP-HEATER-CTL | 9DU | B05 |
| 2000VU | WASTE WIP-HEATER-LINE | 8DU | B04 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | WASTE WIP-DRAINMAST-AFT | 11DU | E01 |
Subtask 30-71-00-740-050-A ** ON A/C NOT FOR ALL
A. Do this test
5. Close-upNOTE: You can do this test only on the Cabin Intercommunication Data System (CIDS) DIR, which is in operation.
NOTE: Two cycles of the Multipurpose Control & Display Unit (MCDU) test are necessary to get the first test result.
(1) Open the circuit breakers of CIDS 1 when you do test on CIDS 2.| ACTION | RESULT |
|---|---|
| 1.In the cockpit, on the MCDU: | In the cockpit, on the MCDU: |
|
|
|
|
|
|
| 2.In the cockpit, on the MCDU: | In the cockpit, on the MCDU: |
|
|
|
|
|
|
Subtask 30-71-00-860-053-A ** ON A/C NOT FOR ALL
A. Put the aircraft back to its initial configuration
(1) On the MCDU, push the line select key adjacent to the RETURN indication until the CFDS menu page comes into view.
(2) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
(1) On the MCDU, push the line select key adjacent to the RETURN indication until the CFDS menu page comes into view.
(2) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).