Removal of the Probe Heat Computer (PHC)
TASK 30-31-34-000-002-A
Removal of the Probe Heat Computer (PHC)
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 30-31-34-865-051-A
Subtask 30-31-34-020-050-A
[Rev.10 from 2021]
2026.04.01 00:30:49 UTC
Removal of the Probe Heat Computer (PHC)
WARNING:
MAKE SURE THAT CIRCUIT BREAKERS 2KS1 AND 2KS2 ARE CLOSED BEFORE YOU OPEN PROBE HEATER CIRCUIT-BREAKERS 1DA1(2), 3DA1(2,3), 4DA1(2,3) AND 5DA1(2,3). IF YOU DO NOT OBEY THIS INSTRUCTION:
- THE PROBES WILL BECOME TOO HOT.
- THIS CAN CAUSE DAMAGE TO EQUIPMENT AND INJURY TO MAINTENANCE PERSONNEL.
WARNING:
BEFORE YOU OPEN PHC CIRCUIT BREAKERS 2DA1(2,3), OPEN PROBE HEATER CIRCUIT-BREAKERS 1DA1(2), 3DA1(2,3), 4DA1(2,3) AND 5DA1(2,3). IF YOU DO NOT OBEY THIS SEQUENCE:
- THE PROBES WILL BECOME TOO HOT.
- THIS CAN CAUSE DAMAGE TO EQUIPMENT AND INJURY TO MAINTENANCE PERSONNEL.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | AR | ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE |
| No specific | AR | CAP - BLANKING |
| No specific | AR | SAFETY CLIP - CIRCUIT BREAKER |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 121 | AVIONICS COMPARTMENT |
| 122 | AVIONICS COMPARTMENT |
| 811 |
| REFERENCE | DESIGNATION |
|---|---|
Subtask 30-31-34-865-051-A
A. Open, safety and tag this(these) circuit breaker(s):
Subtask 30-31-34-865-054-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| FOR FIN: 6DA1 (PHC1) | |||
| 49VU | ANTI ICE/PROBES/AOA/1 | 4DA1 | D04 |
| 49VU | ANTI ICE/PROBES/PITOT/1 | 3DA1 | D02 |
| 122VU | ANTI ICE/PROBES/1/STATIC | 5DA1 | Z13 |
| 122VU | ANTI ICE/PROBES/1/TAT | 1DA1 | Z12 |
| FOR FIN: 6DA2 (PHC2) | |||
| 122VU | ANTI ICE/PROBES/2/TAT | 1DA2 | Y15 |
| 122VU | ANTI ICE/PROBES/2/PITOT | 3DA2 | Y14 |
| 122VU | ANTI ICE/PROBES/2/AOA | 4DA2 | Y13 |
| 122VU | ANTI ICE/PROBES/2/STATIC | 5DA2 | Y11 |
| FOR FIN: 6DA3 (PHC3) | |||
| 122VU | ANTI ICE/PROBES/3/PITOT | 3DA3 | Z16 |
| 122VU | ANTI ICE/PROBES/3/AOA | 4DA3 | Z15 |
| 122VU | ANTI ICE/PROBES/3/STATIC | 5DA3 | Z14 |
B. Open, safety and tag this(these) circuit breaker(s):
Subtask 30-31-34-010-050-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| FOR FIN: 6DA1 (PHC1) | |||
| 49VU | ANTI ICE/PROBES/PHC/1 | 2DA1 | D03 |
| FOR FIN: 6DA2 (PHC2) | |||
| 122VU | ANTI ICE/PROBES/PHC/2 | 2DA2 | Y12 |
| FOR FIN: 6DA3 (PHC3) | |||
| 122VU | ANTI ICE/PROBES/PHC/3 | 2DA3 | Y16 |
C. Get Access
(1) Put the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position.
(2) Open the access door 811.
4. Procedure(1) Put the ACCESS PLATFORM 3M (10 FT)- ADJUSTABLE in position.
(2) Open the access door 811.
Subtask 30-31-34-020-050-A
A. Removal of the PHC
(1) Disconnect the electrical connector (4) from the PHC (3).
(2) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
(3) Remove the screws (1) and the washers (2).
(4) Remove the PHC (3).
(1) Disconnect the electrical connector (4) from the PHC (3).
(2) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
(3) Remove the screws (1) and the washers (2).
(4) Remove the PHC (3).
PHC Backshell Connector