1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
1
ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE
No specific
AR
WARNING NOTICE(S)
No specific
Torque wrench: range to between 11 and 9 lbf.in (0.12 and 0.10 m.daN ) T
No specific
Torque wrench: range to between 124 and 106 lbf.in (1.40 and 1.20 m.daN ) T
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
437AL, 438AR, 451AL, 452AR
FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
447AL, 448AR, 461AL, 462AR
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 24-42-00-862-001-A
De-energize the Ground Service Network Supplied from the External Power
TASK 36-11-00-710-803-A
Operational Test of the Bleed Air System
TASK 71-13-00-010-803-A
Opening of the Fan Cowl Doors
TASK 71-13-00-410-803-A
Closing of the Fan Cowl Doors
TASK 78-30-00-040-807-A
Deactivation of the Thrust Reverser System for Nacelle Maintenance (ICU)
TASK 78-30-00-440-807-A
Reactivation of the Thrust Reverser System after Nacelle Maintenance (ICU)
TASK 78-36-00-010-806-A
Opening of the Thrust Reverser Cowl Doors
TASK 78-36-00-410-806-A
Closing of the Thrust Reverser Cowl Doors
3. Job Set-up
Subtask 30-21-51-861-067-A
A. Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
Subtask 30-21-51-941-073-A
B. Safety Precautions
   (1) On the center pedestal, on ENG panel 115VU:
     (a) Make sure that the ENG/MODE selector switch is in the NORM position.
     (b) Make sure that the ENG/MASTER 1(2) control switch was in the OFF position not less than five minutes before you do this procedure.
     (c) Make sure that the WARNING NOTICE(S) is in position to tell persons not to operate:
  • The ENG/MODE selector switch, and
  • The ENG/MASTER 1(2) control switch.
   (2) On the ENG section of maintenance panel 50VU:
     (a) Make sure that the ON legend of the FADEC GND PWR/1(2) pushbutton switch is off.
     (b) Make sure that the WARNING NOTICE(S) is in position to tell persons not to energize FADEC 1(2).
Subtask 30-21-51-865-103-A
C. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
FOR FIN: 4020KM1 (POWER PLANTDEMOUNTABLE, ENGINE 1)
122VUANTI ICE/ENG/11DN1X10
FOR FIN: 4020KM2 (POWER PLANTDEMOUNTABLE, ENGINE 2)
122VUANTI ICE/ENG/21DN2W10
Subtask 30-21-51-010-104-A
D. Get Access
   (1) Make sure that the fan cowl doors are open (Ref. AMM TASK 71-13-00-010-803):
     (a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
437AL 438AR
     (b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
447AL 448AR
Subtask 30-21-51-040-067-A
E. Deactivation of the Thrust Reverser System for Ground Maintenance
WARNING: YOU MUST DEACTIVATE THE THRUST REVERSER BEFORE YOU DO WORK ON OR AROUND IT. IF YOU DO NOT, THE THRUST REVERSER CAN OPERATE ACCIDENTALLY AND CAUSE AN INJURY AND/OR DAMAGE.
   (1) Make sure that you did the deactivation of the thrust reverser system for nacelle maintenance (Ref. AMM TASK 78-30-00-040-807).
Subtask 30-21-51-010-106-A
F. Get Access
   (1) Make sure that the thrust reverser cowl-doors are open (Ref. AMM TASK 78-36-00-010-806):
     (a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
451AL 452AR
     (b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
461AL 462AR
   (2) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position.
4. Procedure
Subtask 30-21-51-420-063-A
A. Installation of the FWD Air-Intake Anti-Ice Valve Ventilation Lines
NOTE: If new hose clamps (2) are installed, trim the tail of the clamp to no longer than 0.5 inches (12.7 mm) beyond the torque screw housing.
   (1) Attach the Nacelle Anti-Icing (NAI) hose (2) to the NAI tube (4) with hose clamp (1).
   (2) TORQUE the hose clamp (1) to between 11 and 9 lbf.in (0.12 and 0.10 m.daN ) T.
   (3) Align the two holes at the aft end of the NAI tube (4) with the mating holes in the bracket on Pressure Regulating and Shut-Off Valve 2 (PRSOV2) (5).
   (4) Install the two bolts (3) that attach the NAI tube (4) to PRSOV2 (5).
   (5) TORQUE the two bolts (3) to between 124 and 106 lbf.in (1.40 and 1.20 m.daN )
T.
   (6) Connect the forward end of the NAI holes to the Variable Bleed Valve (VBV) exit duct (6) using the hose clamp (1).
   (7) TORQUE the hose clamp (1) to between 11 and 9 lbf.in (0.12 and 0.10 m.daN )
T.
Subtask 30-21-51-710-063-A 5. Close-up
Subtask 30-21-51-410-087-A
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Remove the access platform(s).
   (3) Close the thrust reverser cowl-doors (Ref. AMM TASK 78-36-00-410-806).
     (a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
451AL 452AR
     (b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
461AL 462AR
Subtask 30-21-51-440-062-A
B. Do the reactivation of the thrust reverser system after nacelle maintenance (Ref. AMM TASK 78-30-00-440-807).
Subtask 30-21-51-410-088-A
C. Close Access
   (1) Close the fan cowl doors (Ref. AMM TASK 71-13-00-410-803):
     (a) FOR [4020KM1] (POWER PLANT-DEMOUNTABLE, ENGINE 1)
437AL 438AR
     (b) FOR [4020KM2] (POWER PLANT-DEMOUNTABLE, ENGINE 2)
447AL 448AR
   (2) Remove the WARNING NOTICE(S).
Subtask 30-21-51-865-101-A
D. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C ALL
FOR FIN: 4020KM1 (POWER PLANTDEMOUNTABLE, ENGINE 1)
122VUANTI ICE/ENG/11DN1X10
FOR FIN: 4020KM2 (POWER PLANTDEMOUNTABLE, ENGINE 2)
122VUANTI ICE/ENG/21DN2W10
Subtask 30-21-51-862-061-A
E. De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).