Removal of the Accumulator-Gas Charging Valve
TASK 29-12-22-000-001-A
Removal of the Accumulator-Gas Charging Valve
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 29-12-22-865-050-A
Subtask 29-12-22-614-050-A
[Rev.10 from 2021]
2026.04.01 00:19:01 UTC
Removal of the Accumulator-Gas Charging Valve
WARNING:
MAKE SURE THAT THE GROUND SAFETY-LOCKS ARE IN POSITION ON THE LANDING GEAR. THIS WILL PREVENT UNWANTED MOVEMENT OF THE LANDING GEAR, AND THUS POSSIBLE INJURY TO PERSONS AND DAMAGE TO THE AIRCRAFT AND/OR EQUIPMENT.
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | CAP - BLANKING |
| No specific | 1 | PLUG - BLANKING |
| No specific | AR | SAFETY CLIP - CIRCUIT BREAKER |
| No specific | 1 | WARNING NOTICE(S) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 195 | HYDRAULIC COMPT AND FAIRINGS |
| 195BB |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 29-00-00-864-001-A | Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action |
| TASK 29-14-00-614-001-A | Depressurization of the Hydraulic Reservoirs |
Subtask 29-12-22-865-050-A
A. Open, safety and tag this(these) circuit breaker(s):
Subtask 29-12-22-860-050-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 49VU | HYD/HYD PWR/B WARN/& CTL | 2702GJ | C12 |
| 121VU | HYDRAULIC/SOL VALVES/G/Y/B/LEAK/TST | 1881GP | N35 |
| 123VU | B HYD/ELEC PUMP | 2701GJ | AB09 |
B. Aircraft Maintenance Configuration
(1) Put the WARNING NOTICE(S) in position to tell persons not to pressurize the Blue hydraulic system:
(Ref. AMM TASK 29-00-00-864-001).
(3) Depressurize the reservoir of the Blue hydraulic system (Ref. AMM TASK 29-14-00-614-001).
Subtask 29-12-22-010-050-A 4. Procedure(1) Put the WARNING NOTICE(S) in position to tell persons not to pressurize the Blue hydraulic system:
- In the cockpit on the hydraulic section 40VU of the overhead panel
- On the ground service panel of the Blue hydraulic system.
(Ref. AMM TASK 29-00-00-864-001).
(3) Depressurize the reservoir of the Blue hydraulic system (Ref. AMM TASK 29-14-00-614-001).
Subtask 29-12-22-614-050-A
A. Depressurize the Power Accumulator (2070GM) (1)
(1) Remove the endcap (6) from the charging-valve (4).
(2) Turn the nut (5) carefully to the OPEN position and release the nitrogen pressure.
Subtask 29-12-22-020-050-A (1) Remove the endcap (6) from the charging-valve (4).
(2) Turn the nut (5) carefully to the OPEN position and release the nitrogen pressure.
B. Removal of the Gas Charging-valve (2071GM)
(1) Cut, remove and discard the lockwire from the gas charging-valve (4).
(2) Remove the gas charging valve (4)
(3) Install the PLUG - BLANKING in the adapter (2).
(4) Install the CAP - BLANKING on the gas charging-valve (4).
(1) Cut, remove and discard the lockwire from the gas charging-valve (4).
(2) Remove the gas charging valve (4)
(3) Install the PLUG - BLANKING in the adapter (2).
(4) Install the CAP - BLANKING on the gas charging-valve (4).
Gas Charging Valve