Removal of the Solenoid Valve


TASK 28-25-51-000-003-A
Removal of the Solenoid Valve


WARNING: PUT THE SAFETY DEVICES AND THE WARNING NOTICES IN POSITION BEFORE YOU START A TASK ON OR NEAR:
  • THE FLIGHT CONTROLS
  • THE FLIGHT CONTROL SURFACES
  • THE LANDING GEAR AND THE RELATED DOORS
  • COMPONENTS THAT MOVE.
MOVEMENT OF COMPONENTS CAN KILL OR CAUSE INJURY TO PERSONS AND/OR CAN CAUSE DAMAGE TO THE EQUIPMENT.
1. Reason for the Job
Self Explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
ACCESS PLATFORM 3M (10 FT)
No specific
AR
ACCESS PLATFORM 4M (13 FT)
No specific
AR
CAP - BLANKING
No specific
AR
CONTAINER 5 L (1.32 USGAL)
No specific
AR
SAFETY BARRIER(S)
No specific
AR
WARNING NOTICE(S)
 B. Referenced Information
REFERENCE
DESIGNATION
TASK 28-00-00-910-001-A
Fuel Safety Procedures
TASK 32-12-00-010-001-A
Open the Main Gear Doors for Access
TASK 57-17-11-000-003-A
Removal of the Protective Cover of the ACT-Equipment Support Door
3. Job Set-up
Subtask 28-25-51-941-056-A
A. Safety Precautions
WARNING: OBEY THE FUEL SAFETY PROCEDURES.
   (1) You must obey the fuel safety procedures when you do work on the fuel system (Ref. AMM TASK 28-00-00-910-001).
   (2) As necessary, use the applicable SAFETY BARRIERS, specified by the operator's instructions and your local regulations.
   (3) Put a WARNING NOTICE(S) in the cockpit to tell persons not to operate the slats.
   (4) Put a WARNING NOTICE(S) in position to tell persons not to operate the main gear doors.
Subtask 28-25-51-010-055-B ** ON A/C NOT FOR ALL
B. Get Access
   (1) For the solenoid valve of the refuel valve 10QU:
     (a) Open the main gear doors and install the safety devices (Ref. AMM TASK 32-12-00-010-001).
     (b) Put the ACCESS PLATFORM 4M (13 FT) in position below the refuel valve 10QU.
   (2) For the solenoid valve of the refuel valve 7QU (8QU):
     (a) Put the ACCESS PLATFORM 4M (13 FT) in position below the applicable access panel 522JB (622JB).
     (b) Remove the applicable access panel 522JB (622JB).
   (3) Put a CONTAINER 5 L (1.32 USGAL) below the refuel valve.
Subtask 28-25-51-010-055-C ** ON A/C NOT FOR ALL
B. Get Access
   (1) For the solenoid valve of refuel valve 41QU:
     (a) Open the MLG doors and install the safety devices (Ref. AMM TASK 32-12-00-010-001).
     (b) Put the ACCESS PLATFORM 3M (10 FT) in position at zone 148.
     (c) Remove the protective cover from the ACT-equipment support door (Ref. AMM TASK 57-17-11-000-003).
   (2) Put a CONTAINER 5 L (1.32 USGAL) below the refuel valve.
4. Procedure
Subtask 28-25-51-020-053-A
A. Removal of the Solenoid Valve
CAUTION: MAKE SURE THAT THE ELECTRICAL CONNECTORS ARE CLEAN BEFORE YOU DISCONNECT OR CONNECT THEM. CONTAMINATION ON THE ELECTRICAL CONNECTORS CAN CAUSE DAMAGE TO EQUIPMENT.
   (1) Disconnect the electrical connector (1).
   (2) Put the CAP-BLANKING on each disconnected electrical connector and receptacle.
   (3) Remove the bolts (2) and the washers (3).
   (4) Remove the solenoid valve (4) from the refuel valve (7).
   (5) Remove and discard the O-rings (5) and (6).