W DOC AIRBUS | AMM A320F

Installation of the Additional Center Tank (ACT) Integrated Impact Wall


TASK 28-11-49-400-002-A
Installation of the Additional Center Tank (ACT) Integrated Impact Wall


WARNING: OBEY THE FUEL SAFETY PROCEDURES.
WARNING: MAKE SURE THAT THE SAFETY DEVICES AND THE WARNING NOTICES ARE IN POSITION BEFORE YOU START A TASK ON OR NEAR:
  • THE FLIGHT CONTROLS
  • THE FLIGHT CONTROL SURFACES
  • THE LANDING GEAR AND RELATED DOORS
  • COMPONENTS THAT MOVE.
MOVEMENT OF COMPONENTS CAN KILL OR CAUSE INJURY TO PERSONS AND/OR DAMAGE TO EQUIPMENT.
ZONE: 130
ZONE: 150
ZONE: 160
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
AR
ACCESS PLATFORM 2M (6 FT)
 B. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
130
FWD CARGO COMPT AFT BULKHEAD OF AVNCS COMPT TO FWD PRESSURE BULKHEAD OF WING CENTER BOX
150
AFT CARGO COMPARTMENT FWD PRESS BULKHEAD TO AFT BULKHEAD OF AFT CARGO COMPARTMENT
160
BULK CARGO COMPARTMENT AFT BULKHEAD OF AFT CARGO COMPARTMENT TO AFT BULKHEAD OF BULK CARGO COMPARTMENT
826
 C. Referenced Information
REFERENCE
DESIGNATION
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 24-42-00-862-001-A
De-energize the Ground Service Network Supplied from the External Power
TASK 52-30-00-860-001-A
Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump
TASK 52-30-00-860-002-A
Close the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump
3. Job Set-up
Subtask 28-11-49-860-053-B ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
   (1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
   (2) Make sure that an ACCESS PLATFORM 2M (6 FT) is in position below aft cargo-compartment door 826.
   (3) Make sure that aft cargo-compartment door 826 is open (Ref. AMM TASK 52-30-00-860-001).
   (4) Make sure that CARGO COMPT LIGHT switch 8LU is set to the ON position.
4. Procedure
Subtask 28-11-49-420-051-B ** ON A/C NOT FOR ALL
A. Installation of the Integrated Impact Wall
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) Make sure that the parts retained from the removed component are clean and in the correct condition.
   (4) Install the integrated impact-wall elements (2) and (3) with the lock washers (5), the washers (4) and the studs (6) and (7).
   (5) Tighten the studs (6) and (7).
5. Close-up
Subtask 28-11-49-410-051-B ** ON A/C NOT FOR ALL
A. Close Access
   (1) Make sure that the work area is clean and clear of tools and other items.
   (2) Set CARGO COMPT LIGHT switch 8LU to the OFF position.
   (3) Close aft cargo-compartment door 826 (Ref. AMM TASK 52-30-00-860-002).
   (4) Remove the access platform(s).
Subtask 28-11-49-942-051-A ** ON A/C NOT FOR ALL
B. Put the aircraft back to its initial configuration.
   (1) De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).
[Rev.10 from 2021] 2026.04.02 07:01:54 UTC