Installation of the Captain/First Officer Emergency Descent Device
TASK 25-61-41-400-001-A
Installation of the Captain/First Officer Emergency Descent Device
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 25-61-41-860-051-A
Subtask 25-61-41-420-050-A
Subtask 25-61-41-942-050-A
[Rev.10 from 2021]
2026.03.31 23:39:44 UTC
Installation of the Captain/First Officer Emergency Descent Device
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | Torque wrench: range to between 0.40 and 0.35 m.daN (35.40 and 30.97 lbf.in ) ![]() |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 211 | COCKPIT |
| 212 | COCKPIT |
| REFERENCE | DESIGNATION |
|---|---|
Subtask 25-61-41-860-051-A
A. Not Applicable
4. ProcedureSubtask 25-61-41-420-050-A
A. Installation of the Captain and F/O Emergency Descent Device
(1) Engage the loop of the emergency descent device (6) in the attachment (5).
(2) Put the attachment (5) and the screws (4) in the correct position and then TORQUE the screws to between 0.40 and 0.35 m.daN (35.40 and 30.97 lbf.in )
.
(3) Install the emergency descent device (6) in its stowage compartment.
(4) Put the lining (2) in the correct position.
(5) Tighten the screws (1).
(6) Install the cover (3).
5. Close-up(1) Engage the loop of the emergency descent device (6) in the attachment (5).
(2) Put the attachment (5) and the screws (4) in the correct position and then TORQUE the screws to between 0.40 and 0.35 m.daN (35.40 and 30.97 lbf.in )
. (3) Install the emergency descent device (6) in its stowage compartment.
(4) Put the lining (2) in the correct position.
(5) Tighten the screws (1).
(6) Install the cover (3).
Subtask 25-61-41-942-050-A
A. Make sure that the work area is clean and clear of tools and other items.
Captain/First Officer Emergency Descent Device