Bite Test of the Heated Floor Panel System
TASK 25-27-00-740-001-A
Bite Test of the Heated Floor Panel System
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
B. Referenced Information
3. Job Set-up
Subtask 25-27-00-861-051-A ** ON A/C NOT FOR ALL Subtask 25-27-00-010-050-A ** ON A/C NOT FOR ALL
Subtask 25-27-00-740-050-A ** ON A/C NOT FOR ALL
Subtask 25-27-00-410-050-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.03.31 23:32:52 UTC
Bite Test of the Heated Floor Panel System
FIN: 14DS ** ON A/C NOT FOR ALL
FIN: 4DS ** ON A/C NOT FOR ALL
FIN: 60DS ** ON A/C NOT FOR ALL
FIN: 66DS ** ON A/C NOT FOR ALL
1. Reason for the JobFIN: 4DS ** ON A/C NOT FOR ALL
FIN: 60DS ** ON A/C NOT FOR ALL
FIN: 66DS ** ON A/C NOT FOR ALL
Self explanatory
2. Job Set-up Information
A. Work Zones and Access Panels
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| FOR [14DS] (CTL UNIT-DOOR AREA HEATING) | |
| 152FW | |
| FOR [4DS] (CTL UNIT-DOOR AREA HEATING) | |
| 132JW | |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| FOR [14DS] (CTL UNIT-DOOR AREA HEATING) | |
| TASK 52-30-00-860-001-A | Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
| TASK 52-30-00-860-002-A | Close the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
| FOR [4DS] (CTL UNIT-DOOR AREA HEATING) | |
| TASK 52-30-00-860-001-A | Open the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
| TASK 52-30-00-860-002-A | Close the FWD or Aft Cargo-Compartment Door with the Yellow Electric Pump |
| FOR [60DS] (CTL UNIT-DOOR AREA HEATING) | |
| FOR [66DS] (CTL UNIT-DOOR AREA HEATING) | |
| TASK 52-41-00-010-002-A | Open the Avionics Compartment Doors for Access |
| TASK 52-41-00-410-002-A | Close the Avionics Compartment Doors after Access |
Subtask 25-27-00-861-051-A ** ON A/C NOT FOR ALL Subtask 25-27-00-010-050-A ** ON A/C NOT FOR ALL
B. Get Access
(1) FOR [4DS] (CTL UNIT-DOOR AREA HEATING)
(a) Open the FWD cargo compartment door (Ref. AMM TASK 52-30-00-860-001).
(b) Set the CARGO COMPT light switch 6LU to ON.
(c) Remove the sidewall lining 132JW.
(2) FOR [14DS] (CTL UNIT-DOOR AREA HEATING)
(a) Open the AFT cargo compartment door (Ref. AMM TASK 52-30-00-860-001).
(b) Set the CARGO COMPT light switch 8LU to ON.
(c) Remove the sidewall lining 152FW.
Subtask 25-27-00-010-050-B ** ON A/C NOT FOR ALL (1) FOR [4DS] (CTL UNIT-DOOR AREA HEATING)
(a) Open the FWD cargo compartment door (Ref. AMM TASK 52-30-00-860-001).
(b) Set the CARGO COMPT light switch 6LU to ON.
(c) Remove the sidewall lining 132JW.
(2) FOR [14DS] (CTL UNIT-DOOR AREA HEATING)
(a) Open the AFT cargo compartment door (Ref. AMM TASK 52-30-00-860-001).
(b) Set the CARGO COMPT light switch 8LU to ON.
(c) Remove the sidewall lining 152FW.
B. Get Access
(1) FOR [14DS] (CTL UNIT-DOOR AREA HEATING)
(a) Open the aft cargo compartment door (Ref. AMM TASK 52-30-00-860-001).
(b) Set the CARGO COMPT light switch 8LU to ON.
(c) Remove the sidewall lining 152FW.
Subtask 25-27-00-010-052-A ** ON A/C NOT FOR ALL (1) FOR [14DS] (CTL UNIT-DOOR AREA HEATING)
(a) Open the aft cargo compartment door (Ref. AMM TASK 52-30-00-860-001).
(b) Set the CARGO COMPT light switch 8LU to ON.
(c) Remove the sidewall lining 152FW.
C. Get Access
(1) FOR [60DS] (CTL UNIT-DOOR AREA HEATING), [66DS] (CTL UNIT-DOOR AREA HEATING)
(a) In the cockpit on the panel 50VU:
Subtask 25-27-00-010-052-B ** ON A/C NOT FOR ALL (1) FOR [60DS] (CTL UNIT-DOOR AREA HEATING), [66DS] (CTL UNIT-DOOR AREA HEATING)
(a) In the cockpit on the panel 50VU:
- Push the P/B SW-AVIONICS/COMPT LT (23LS).
C. Get Access
(1) FOR [60DS] (CTL UNIT-DOOR AREA HEATING), [66DS] (CTL UNIT-DOOR AREA HEATING)
(a) In the cockpit on the panel 50VU:
(c) Open the avionics compartment door 811 (Ref. AMM TASK 52-41-00-010-002).
Subtask 25-27-00-865-058-A ** ON A/C NOT FOR ALL (1) FOR [60DS] (CTL UNIT-DOOR AREA HEATING), [66DS] (CTL UNIT-DOOR AREA HEATING)
(a) In the cockpit on the panel 50VU:
- Push the P/B SW-AVIONICS/COMPT LT (23LS).
(c) Open the avionics compartment door 811 (Ref. AMM TASK 52-41-00-010-002).
D. Make sure that this(these) circuit breaker(s) is(are) closed:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 122VU | ELEC/GALLEY/CNTOR | 7MC | S28 |
| ** ON A/C NOT FOR ALL | |||
| 2000VU | DOOR AREA HTG PANELS-CTL | 54DS | A07 |
| 2000VU | DR AREA HTG PNLS-DR1-FPH-RH | 52DS | A06 |
| 2000VU | DR AREA HTG PNLS-DR1-FPH-LH | 51DS | A05 |
| ** ON A/C NOT FOR ALL | |||
| 2000VU | DR AREA HTG PNLS-CTL | 3DS | F08 |
| 2000VU | DR AREA HTG PANELS-DR2-FPH | 1DS | F07 |
| ** ON A/C NOT FOR ALL | |||
| 2000VU | DR AREA HTG PNLS-DOOR1-FPH-RH | 52DS | F06 |
| 2000VU | DR AREA HTG PNLS-DOOR1-FPH LH | 51DS | F05 |
| ** ON A/C NOT FOR ALL | |||
| 2000VU | DR AREA HTG PANELS-DR2-HTR | 1DS | A08 |
| 2000VU | DR AREA HTG PANELS-DR2-CTL | 3DS | A06 |
| ** ON A/C NOT FOR ALL | |||
| 2001VU | DOOR AREA HTG PNL-DOOR3-HTR | 11DS | F05 |
| 2001VU | DR AREA HTG PNLS-DOOR 3-CTL | 13DS | F03 |
Subtask 25-27-00-740-050-A ** ON A/C NOT FOR ALL
A. Do this test:
5. Close-up| ACTION | RESULT |
|---|---|
1.On the related control unit:
| On the related control unit:
|
| 2.Release the pushbutton HEATER TEST. | The indicators go off. |
Subtask 25-27-00-410-050-A ** ON A/C NOT FOR ALL
A. Close Access
(1) Put all CB and switches to the initial configuration.
(2) Make sure that the work area is clean and clear of tools and other items.
(3) FOR [4DS] (CTL UNIT-DOOR AREA HEATING)
(a) Install the sidewall lining 132JW.
(b) Set the CARGO COMPT light switch 6LU to OFF.
(c) Close the FWD cargo compartment door (Ref. AMM TASK 52-30-00-860-002).
(4) FOR [14DS] (CTL UNIT-DOOR AREA HEATING)
(a) Install the sidewall lining 152FW.
(b) Set the CARGO COMPT light switch 8LU to OFF.
(c) Close the AFT cargo compartment door (Ref. AMM TASK 52-30-00-860-002).
Subtask 25-27-00-410-050-B ** ON A/C NOT FOR ALL (1) Put all CB and switches to the initial configuration.
(2) Make sure that the work area is clean and clear of tools and other items.
(3) FOR [4DS] (CTL UNIT-DOOR AREA HEATING)
(a) Install the sidewall lining 132JW.
(b) Set the CARGO COMPT light switch 6LU to OFF.
(c) Close the FWD cargo compartment door (Ref. AMM TASK 52-30-00-860-002).
(4) FOR [14DS] (CTL UNIT-DOOR AREA HEATING)
(a) Install the sidewall lining 152FW.
(b) Set the CARGO COMPT light switch 8LU to OFF.
(c) Close the AFT cargo compartment door (Ref. AMM TASK 52-30-00-860-002).
A. Close Access
(1) Put all CB and switches to the initial configuration.
(2) Make sure that the work area is clean and clear of tools and other items.
(3) FOR [14DS] (CTL UNIT-DOOR AREA HEATING)
(a) Install the sidewall lining 152FW.
(b) Set the CARGO COMPT light switch 8LU to OFF.
(c) Close the aft cargo compartment door (Ref. AMM TASK 52-30-00-860-002).
Subtask 25-27-00-410-052-A ** ON A/C NOT FOR ALL (1) Put all CB and switches to the initial configuration.
(2) Make sure that the work area is clean and clear of tools and other items.
(3) FOR [14DS] (CTL UNIT-DOOR AREA HEATING)
(a) Install the sidewall lining 152FW.
(b) Set the CARGO COMPT light switch 8LU to OFF.
(c) Close the aft cargo compartment door (Ref. AMM TASK 52-30-00-860-002).
B. Close Access
(1) FOR [60DS] (CTL UNIT-DOOR AREA HEATING), [66DS] (CTL UNIT-DOOR AREA HEATING)
(a) Put all CB and switches to the initial configuration.
(b) Make sure that the work area is clean and clear of tools and other items.
(c) Close the avionics compartment door 811 (Ref. AMM TASK 52-41-00-410-002).
(d) In the cockpit on the panel 50VU:
Subtask 25-27-00-410-052-B ** ON A/C NOT FOR ALL (1) FOR [60DS] (CTL UNIT-DOOR AREA HEATING), [66DS] (CTL UNIT-DOOR AREA HEATING)
(a) Put all CB and switches to the initial configuration.
(b) Make sure that the work area is clean and clear of tools and other items.
(c) Close the avionics compartment door 811 (Ref. AMM TASK 52-41-00-410-002).
(d) In the cockpit on the panel 50VU:
- Push the P/B SW-AVIONICS/COMPT LT (23LS).
B. Close Access
(1) FOR [60DS] (CTL UNIT-DOOR AREA HEATING), [66DS] (CTL UNIT-DOOR AREA HEATING)
(a) If applicable, put the ON/OFF touch button on the flight attendant panel in OFF position.
(b) Make sure that the work area is clean and clear of tools and other items.
(c) Close the avionics compartment door 811 (Ref. AMM TASK 52-41-00-410-002).
(d) In the cockpit on the panel 50VU:
Subtask 25-27-00-862-051-A ** ON A/C NOT FOR ALL (1) FOR [60DS] (CTL UNIT-DOOR AREA HEATING), [66DS] (CTL UNIT-DOOR AREA HEATING)
(a) If applicable, put the ON/OFF touch button on the flight attendant panel in OFF position.
(b) Make sure that the work area is clean and clear of tools and other items.
(c) Close the avionics compartment door 811 (Ref. AMM TASK 52-41-00-410-002).
(d) In the cockpit on the panel 50VU:
- Push the P/B SW-AVIONICS/COMPT LT (23LS).