Installation of the Constant Speed Motor/Generator (CSM/G)
TASK 24-24-51-400-001-A
Installation of the Constant Speed Motor/Generator (CSM/G)
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Expendable Parts
C. Referenced Information
3. Job Set-up
Subtask 24-24-51-860-052-A
Subtask 24-24-51-420-051-A
Subtask 24-24-51-410-052-A
[Rev.10 from 2021]
2026.03.31 23:22:42 UTC
Installation of the Constant Speed Motor/Generator (CSM/G)
WARNING:
OBEY THE HYDRAULIC SAFETY PROCEDURES.
WARNING:
DO NOT WALK ON A CLOSED LANDING GEAR DOOR.
CAUTION:
USE HIGH-PRESSURE SPRAYING EQUIPMENT FOR SPECIFIED AREAS ONLY.
DO NOT USE HIGH-PRESSURE SPRAYING EQUIPMENT TO CLEAN THE AREAS AROUND SENSORS, PROBES, ANTENNAS, ETC.
YOU MUST CLEAN THESE AREAS BY HAND.
MAKE SURE THAT YOU ADJUST THE HIGH-PRESSURE SPRAYING EQUIPMENT TO, AND USE IT AT, THE SPECIFIED VALUES.
IF YOU DO NOT OBEY THESE PRECAUTIONS, YOU CAN CAUSE DAMAGE TO THE SURFACE OR TO PARTS. HIGH-PRESSURE SPRAYING EQUIPMENT CAN PUSH LIQUIDS INTO BEARINGS, JOINTS, PROBES, BRAKES, ELECTRICAL CONNECTORS AND OTHER SEALED COMPONENTS.
LIQUIDS THAT GO INTO THESE AREAS CAN FREEZE DURING AIRCRAFT FLIGHT, REMOVE LUBRICANTS, CAUSE CORROSION AND ELECTRICAL FAULTS.
FIN: 8XE
1. Reason for the JobSelf explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Expendable Parts
| FIG.ITEM | DESIGNATION | IPC-CSN |
|---|---|---|
| 8 | LOCKWASHERS | AIPC 24-24-03-01-110 |
| 8 | LOCKWASHERS | AIPC 24-24-83-01-110 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 20-28-00-912-802-A | Electrical Bonding - General Maintenance Procedure |
| TASK 24-24-00-710-001-A | Operational Check of Emergency Generating System |
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 29-00-00-864-001-A | Put the Related Hydraulic System in the Depressurized Configuration before Maintenance Action |
| TASK 29-10-00-863-003-A | Pressurize the Blue Hydraulic System with a Hydraulic Ground Power-Cart |
| TASK 29-10-00-863-003-A-01 | Pressurize the Blue Hydraulic System with the Blue Electric Pump |
| TASK 29-10-00-864-003-A | Depressurize the Blue Hydraulic System |
| TASK 29-14-00-614-001-A | Depressurization of the Hydraulic Reservoirs |
| TASK 29-14-00-614-002-A | Pressurization of the Hydraulic Reservoirs through the Ground Connector |
| TASK 29-14-00-614-002-A-01 | Pressurization of the Hydraulic Reservoirs with the Auxiliary Power Unit (APU) |
| TASK 31-60-00-860-001-A | EIS Start Procedure |
| TASK 31-60-00-860-002-A | EIS Stop Procedure |
| TASK 32-12-00-010-001-A | Open the Main Gear Doors for Access |
| TASK 32-12-00-410-001-A | Close the Main Gear Doors after Access |
Subtask 24-24-51-860-052-A
A. Aircraft Maintenance Configuration
(1) Make sure that the blue hydraulic system is depressurized (Ref. AMM TASK 29-00-00-864-001).
(2) Make sure that the reservoir of the blue hydraulic system is depressurized (Ref. AMM TASK 29-14-00-614-001).
(3) Make sure that the LH and RH Main Landing Gear (MLG) is opened (Ref. AMM TASK 32-12-00-010-001).
(4) Make sure that the STEPLADDER 2.0 M (6.6 FT) is in position at the MLG bay.
Subtask 24-24-51-865-051-A (1) Make sure that the blue hydraulic system is depressurized (Ref. AMM TASK 29-00-00-864-001).
(2) Make sure that the reservoir of the blue hydraulic system is depressurized (Ref. AMM TASK 29-14-00-614-001).
(3) Make sure that the LH and RH Main Landing Gear (MLG) is opened (Ref. AMM TASK 32-12-00-010-001).
(4) Make sure that the STEPLADDER 2.0 M (6.6 FT) is in position at the MLG bay.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 105VU | ELEC/CSM/G /EV AUTO/SPLY | 7XE | C01 |
| 106VU | CSM/G /EV/MAN/SPLY | 6XE | B04 |
| 122VU | ELEC/EMER GEN AUTO/2 | 9XE | Z26 |
| 122VU | ELEC/EMER GEN AUTO/1 | 11XE | Z25 |
Subtask 24-24-51-420-051-A
A. Installation of the CSM/G
(1) Put the CSM/G (1) in position on the support mounts (9) on top of the keel beam.
(2) Attach the CSM/G (1) with new AIPC 24-24-03-01-110 LOCKWASHERS (8) or AIPC 24-24-83-01-110 LOCKWASHERS (8), the screws (5), the washer (6) and the bonding strap (7) on the support mounts (9) (Ref. AMM TASK 20-28-00-912-802).
(3) Tighten the screws (5).
(4) Safety the screws (5) with the lockwashers (8).
(5) Make sure that the hydraulic line end-fittings are serviceable.
(6) Remove the blanking plugs and loosely connect the hydraulic pipes (11), (12) and (15) to the CSM/G (1).
(7) TORQUE the hydraulic pipe (11) to between 5.9 and 5.4 m.daN (43.51 and 39.82 lbf.ft )
.
(8) TORQUE the hydraulic pipe (12) to between 8.3 and 7.5 m.daN (61.21 and 55.31 lbf.ft )
.
(9) TORQUE the hydraulic pipe (15) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
.
(10) Remove the blanking plugs and loosely connect the flexible drain hoses (4) and (10) to the CSM/G (1).
(11) TORQUE the flexible drain hose (4) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
.
(12) TORQUE the flexible drain hose (10) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
.
Subtask 24-24-51-865-055-A (1) Put the CSM/G (1) in position on the support mounts (9) on top of the keel beam.
(2) Attach the CSM/G (1) with new AIPC 24-24-03-01-110 LOCKWASHERS (8) or AIPC 24-24-83-01-110 LOCKWASHERS (8), the screws (5), the washer (6) and the bonding strap (7) on the support mounts (9) (Ref. AMM TASK 20-28-00-912-802).
(3) Tighten the screws (5).
(4) Safety the screws (5) with the lockwashers (8).
(5) Make sure that the hydraulic line end-fittings are serviceable.
(6) Remove the blanking plugs and loosely connect the hydraulic pipes (11), (12) and (15) to the CSM/G (1).
(7) TORQUE the hydraulic pipe (11) to between 5.9 and 5.4 m.daN (43.51 and 39.82 lbf.ft )
. (8) TORQUE the hydraulic pipe (12) to between 8.3 and 7.5 m.daN (61.21 and 55.31 lbf.ft )
. (9) TORQUE the hydraulic pipe (15) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
. (10) Remove the blanking plugs and loosely connect the flexible drain hoses (4) and (10) to the CSM/G (1).
(11) TORQUE the flexible drain hose (4) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
. (12) TORQUE the flexible drain hose (10) to between 1.7 and 1.5 m.daN (12.54 and 11.06 lbf.ft )
. CAUTION:
MAKE SURE THAT THE BONDING STRAP(S) IS(ARE) CONNECTED BEFORE YOU CONNECT THE ELECTRICAL WIRE(S).
(13) Remove the blanking caps and connect the electrical connectors (2), (3), (13) and (14) to the CSM/G (1). B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 24-24-51-860-051-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C ALL | |||
| 105VU | ELEC/CSM/G /EV AUTO/SPLY | 7XE | C01 |
| 106VU | CSM/G /EV/MAN/SPLY | 6XE | B04 |
| 122VU | ELEC/EMER GEN AUTO/2 | 9XE | Z26 |
| 122VU | ELEC/EMER GEN AUTO/1 | 11XE | Z25 |
C. Preparation for Test
(1) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
(2) Do the EIS start procedure (upper ECAM DU and lower ECAM DU only)
(Ref. AMM TASK 31-60-00-860-001).
(3) Pressurize the Blue Hydraulic System
(a) Pressurize the reservoir of the Blue hydraulic system (Ref. AMM TASK 29-14-00-614-002).
(b) Pressurize the Blue hydraulic system either with the electric pump or a ground hydraulic cart (Ref. AMM TASK 29-10-00-863-003).
Subtask 24-24-51-710-051-A (1) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
(2) Do the EIS start procedure (upper ECAM DU and lower ECAM DU only)
(Ref. AMM TASK 31-60-00-860-001).
(3) Pressurize the Blue Hydraulic System
(a) Pressurize the reservoir of the Blue hydraulic system (Ref. AMM TASK 29-14-00-614-002).
(b) Pressurize the Blue hydraulic system either with the electric pump or a ground hydraulic cart (Ref. AMM TASK 29-10-00-863-003).
D. Test
(1) Do the operational test of the Emergency Generation System (Ref. AMM TASK 24-24-00-710-001).
5. Close-up(1) Do the operational test of the Emergency Generation System (Ref. AMM TASK 24-24-00-710-001).
Subtask 24-24-51-410-052-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Remove the stepladder.
(3) Close the LH and RH MLG door (Ref. AMM TASK 32-12-00-410-001).
(4) Put the system back to a serviceable condition
(5) Remove the warning notices from the cockpit and from the ground service panel of the Blue hydraulic system.
(6) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
Subtask 24-24-51-860-053-A (1) Make sure that the work area is clean and clear of tools and other items.
(2) Remove the stepladder.
(3) Close the LH and RH MLG door (Ref. AMM TASK 32-12-00-410-001).
(4) Put the system back to a serviceable condition
(5) Remove the warning notices from the cockpit and from the ground service panel of the Blue hydraulic system.
(6) Remove the ground support and maintenance equipment, the special and standard tools and all other items.
B. Put the aircraft back to its initial configuration.
(1) De-pressurize the Blue hydraulic system (Ref. AMM TASK 29-10-00-864-003).
(2) Do the EIS stop procedure
(Ref. AMM TASK 31-60-00-860-002).
(3) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
(1) De-pressurize the Blue hydraulic system (Ref. AMM TASK 29-10-00-864-003).
(2) Do the EIS stop procedure
(Ref. AMM TASK 31-60-00-860-002).
(3) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
Constant Speed Motor/Generator - CSM/G