Installation of the EGIU-1(2)
TASK 24-22-33-400-002-A
Installation of the EGIU-1(2)
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 24-22-33-860-050-A ** ON A/C NOT FOR ALL
Subtask 24-22-33-420-051-A ** ON A/C NOT FOR ALL
Subtask 24-22-33-862-051-A ** ON A/C NOT FOR ALL
[Rev.10 from 2021]
2026.03.31 23:22:08 UTC
Installation of the EGIU-1(2)
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE |
| No specific | AR | WARNING NOTICE(S) |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 121 | AVIONICS COMPARTMENT |
| 122 | AVIONICS COMPARTMENT |
| 811 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 24-41-00-861-002-A | Energize the Aircraft Electrical Circuits from the External Power |
| TASK 24-41-00-861-002-A-01 | Energize the Aircraft Electrical Circuits from the APU |
| TASK 24-41-00-861-002-A-02 | Energize the Aircraft Electrical Circuits from Engine 1(2) |
| TASK 24-41-00-862-002-A | De-energize the Aircraft Electrical Circuits Supplied from the External Power |
| TASK 24-41-00-862-002-A-01 | De-energize the Aircraft Electrical Circuits Supplied from the APU |
| TASK 24-41-00-862-002-A-02 | De-energize the Aircraft Electrical Circuits Supplied from the Engine 1(2) |
| TASK 24-42-00-861-001-A | Energize the Ground Service Network from the External Power |
| TASK 24-42-00-862-001-A | De-energize the Ground Service Network Supplied from the External Power |
| TASK 31-60-00-860-001-A | EIS Start Procedure |
| TASK 31-60-00-860-002-A | EIS Stop Procedure |
Subtask 24-22-33-860-050-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
(1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
Subtask 24-22-33-865-053-A ** ON A/C NOT FOR ALL (1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
NOTE: When the circuit breakers 4XG and 12XG are open, the EXT PWR/AVAIL caution light and the AVAIL legend of the EXT PWR pusbutton switch are off.
(2) On the ENG panel 115VU: - make sure that the WARNING NOTICE(S) to tell persons not to start the engine, is in position.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
Subtask 24-22-33-010-051-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| FOR FIN: 22XU1 (EGIU1) | |||
| 122VU | ELEC/GCU/1 | 2XU1 | T26 |
| 122VU | ELEC/IDG1/DISC | 1XT | T24 |
| 122VU | ELEC/EXT PWR/LT CLT/AVAIL | 4XG | X31 |
| 122VU | ELEC/EXT PWR/CTL | 11XG | X29 |
| 122VU | ELEC/EXT PWR/COCKPIT/AVAIL/LT | 12XG | X28 |
| 122VU | ELEC/EXT PWR/EGIU1/28VDC | 26XU1 | Z31 |
| 123VU | EXT PWR/EGIU1/115VAC | 23XG | AA07 |
| 123VU | GEN1/EGIU1/115VAC | 23XU1 | AF12 |
| FOR FIN: 22XU2 (EGIU2) | |||
| 122VU | ELEC/GEN1/OFF/BTC2 SPLY | 14XU | T30 |
| 122VU | ELEC/GCU/2 | 2XU2 | T27 |
| 122VU | ELEC/IDG2/DISC | 2XT | T25 |
| 122VU | APU GEN/EGIU2/28VDC | 26XU2 | Y31 |
| 122VU | GEN2/EGIU2/28VDC | 24XU2 | Y30 |
| 123VU | APU GEN/EGIU2/115VAC | 23XS | AA08 |
| 123VU | GEN2/EGIU2/115VAC | 23XU2 | AF01 |
C. Get Access
(1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position at the access door 811.
(2) Make sure that the access door 811 is open.
4. Procedure(1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position at the access door 811.
(2) Make sure that the access door 811 is open.
Subtask 24-22-33-420-051-A ** ON A/C NOT FOR ALL
A. Installation of the EGIU
(1) Remove the CAP-BLANKING from each electrical connector and receptacle.
(2) Make sure that all the electrical connections are clean and in the correct condition.
(3) Clean the component interfaces and the adjacent area.
(4) Do an inspection of the component interfaces and the adjacent area.
(5) Put the EGIU in position in the rack (6).
(6) Carefully push the EGIU until it engages the rack receptacle (5).
(7) Put the knurled nut (1) on the stud (2) and tighten the knurled nut (1).
Subtask 24-22-33-865-054-A ** ON A/C NOT FOR ALL (1) Remove the CAP-BLANKING from each electrical connector and receptacle.
(2) Make sure that all the electrical connections are clean and in the correct condition.
(3) Clean the component interfaces and the adjacent area.
(4) Do an inspection of the component interfaces and the adjacent area.
(5) Put the EGIU in position in the rack (6).
(6) Carefully push the EGIU until it engages the rack receptacle (5).
(7) Put the knurled nut (1) on the stud (2) and tighten the knurled nut (1).
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 24-22-33-860-051-A ** ON A/C NOT FOR ALL | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| FOR FIN: 22XU1 (EGIU1) | |||
| 122VU | ELEC/GCU/1 | 2XU1 | T26 |
| 122VU | ELEC/IDG1/DISC | 1XT | T24 |
| 122VU | ELEC/EXT PWR/LT CLT/AVAIL | 4XG | X31 |
| 122VU | ELEC/EXT PWR/CTL | 11XG | X29 |
| 122VU | ELEC/EXT PWR/COCKPIT/AVAIL/LT | 12XG | X28 |
| 122VU | ELEC/EXT PWR/EGIU1/28VDC | 26XU1 | Z31 |
| 122VU | ELEC/GEN1/EGIU1/28VDC | 24XU1 | Z30 |
| 123VU | EXT PWR/EGIU1/115VAC | 23XG | AA07 |
| 123VU | GEN1/EGIU1/115VAC | 23XU1 | AF12 |
| FOR FIN: 22XU2 (EGIU2) | |||
| 122VU | ELEC/GEN1/OFF/BTC2 SPLY | 14XU | T30 |
| 122VU | ELEC/GCU/2 | 2XU2 | T27 |
| 122VU | ELEC/IDG2/DISC | 2XT | T25 |
| 122VU | APU GEN/EGIU2/28VDC | 26XU2 | Y31 |
| 122VU | GEN2/EGIU2/28VDC | 24XU2 | Y30 |
| 123VU | APU GEN/EGIU2/115VAC | 23XS | AA08 |
| 123VU | GEN2/EGIU2/115VAC | 23XU2 | AF01 |
C. Aircraft Maintenance Configuration
(1) De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).
(2) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
Subtask 24-22-33-710-050-A ** ON A/C NOT FOR ALL (1) De-energize the ground service network
(Ref. AMM TASK 24-42-00-862-001).
(2) Energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-861-002).
D. Operational Test of the EGIU
(1) For 22XU1
(a) Do the EIS start procedure (upper ECAM DU and lower ECAM DU only)
(Ref. AMM TASK 31-60-00-860-001)
(b) On the ECAM control panel, push the ELEC key (on the lower ECAM DU, the ELEC page comes into view).
(c) On the ELEC page, make sure that the following EXT PWR parameters are correct:
(Ref. AMM TASK 31-60-00-860-002).
(2) For 22XU2
(a) Energize the aircraft electrical circuits from the APU (Ref. AMM TASK 24-41-00-861-002).
(b) On the ELEC page, make sure that the following APU GEN parameters are correct:
5. Close-up(1) For 22XU1
(a) Do the EIS start procedure (upper ECAM DU and lower ECAM DU only)
(Ref. AMM TASK 31-60-00-860-001)
(b) On the ECAM control panel, push the ELEC key (on the lower ECAM DU, the ELEC page comes into view).
(c) On the ELEC page, make sure that the following EXT PWR parameters are correct:
- AC V = 115 + or - 5V,
- FRQ HZ = 400 + or - 10HZ.
(Ref. AMM TASK 31-60-00-860-002).
(2) For 22XU2
(a) Energize the aircraft electrical circuits from the APU (Ref. AMM TASK 24-41-00-861-002).
(b) On the ELEC page, make sure that the following APU GEN parameters are correct:
- AC LOAD Percent shown in green,
- AC V = 115 + or - 5V,
- FRQ HZ = 400 + or - 10HZ.
Subtask 24-22-33-862-051-A ** ON A/C NOT FOR ALL
A. Put the aircraft back to its initial configuration.
(1) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
Subtask 24-22-33-410-051-A ** ON A/C NOT FOR ALL (1) De-energize the aircraft electrical circuits
(Ref. AMM TASK 24-41-00-862-002).
B. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access door 811.
(3) Remove the WARNING NOTICE(S).
(4) Remove the access platform(s).
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access door 811.
(3) Remove the WARNING NOTICE(S).
(4) Remove the access platform(s).
Electrical Generation Interface Unit 1(2)