1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
B. Work Zones and Access Panels
C. Referenced Information
3. Job Set-up
Subtask 23-51-34-860-050-A
Subtask 23-51-34-420-050-A
Subtask 23-51-34-410-050-A
[Rev.10 from 2021]
2026.04.02 06:12:17 UTC
Installation of the Audio Management Unit (AMU)
1. Reason for the Job
Self explanatory
2. Job Set-up Information
A. Fixtures, Tools, Test and Support Equipment
| REFERENCE | QTY | DESIGNATION |
|---|---|---|
| No specific | 1 | ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE |
| ZONE/ACCESS | ZONE DESCRIPTION |
|---|---|
| 127 | REAR AVIONIC COMPARTMENT |
| 824 |
| REFERENCE | DESIGNATION |
|---|---|
| TASK 23-51-00-710-001-A | Operational Test of the Audio Management Unit (AMU) |
| TASK 23-51-00-740-002-A | BITE Test of the Audio Management Unit (AMU) |
| TASK 52-41-00-410-002-A | Close the Avionics Compartment Doors after Access |
Subtask 23-51-34-860-050-A
A. Aircraft Maintenance Configuration
(1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position at the access door 824 in zone 128.
(2) Make sure that the access door 824 is open.
Subtask 23-51-34-865-052-A (1) Make sure that the ACCESS PLATFORM 2M (6 FT) - ADJUSTABLE is in position at the access door 824 in zone 128.
(2) Make sure that the access door 824 is open.
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
4. Procedure| PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | COM/AUDIO/ACP/F/O | 5RN | G07 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | COM/AUDIO/FLT/INTPH | 9RN | G08 |
| 49VU | COM/AUDIO/ACP/CAPT | 4RN | G06 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | COM/ACP F/O/BITE/ INT 2 AUDIO/3&5 OCCPNT | 5RN | G07 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | COM/INT/1+2 | 9RN | G08 |
| 49VU | COM/ACP CAPT/SELCAL/INT 1 AUDIO/AVNCS | 4RN | G06 |
| ** ON A/C ALL | |||
| 121VU | COM NAV/SELCAL | 8RN | M04 |
| 121VU | COM NAV/ACP/THIRD/OCCPNT | 6RN | M02 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | COM NAV/ACP/FOURTH/OCCPNT | 20RN | M01 |
Subtask 23-51-34-420-050-A
A. Installation of the Audio Management Unit (AMU)
(1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Remove the blanking caps from the electrical connectors (1).
(4) Make sure that the electrical connectors (1) are clean and in the correct condition.
(5) Install the AMU (5) in its rack (2).
(6) Push the AMU (5) on its rack (2) to connect the electrical connectors (1).
(7) Engage the nuts (3) on the lugs (4) and tighten.
Subtask 23-51-34-865-053-A (1) Clean the component interfaces and the adjacent area.
(2) Do an inspection of the component interfaces and the adjacent area.
(3) Remove the blanking caps from the electrical connectors (1).
(4) Make sure that the electrical connectors (1) are clean and in the correct condition.
(5) Install the AMU (5) in its rack (2).
(6) Push the AMU (5) on its rack (2) to connect the electrical connectors (1).
(7) Engage the nuts (3) on the lugs (4) and tighten.
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
Subtask 23-51-34-740-050-A | PANEL | DESIGNATION | FIN | LOCATION |
|---|---|---|---|
| ** ON A/C NOT FOR ALL | |||
| 49VU | COM/AUDIO/ACP/F/O | 5RN | G07 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | COM/AUDIO/FLT/INTPH | 9RN | G08 |
| 49VU | COM/AUDIO/ACP/CAPT | 4RN | G06 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | COM/ACP F/O/BITE/ INT 2 AUDIO/3&5 OCCPNT | 5RN | G07 |
| ** ON A/C NOT FOR ALL | |||
| 49VU | COM/INT/1+2 | 9RN | G08 |
| 49VU | COM/ACP CAPT/SELCAL/INT 1 AUDIO/AVNCS | 4RN | G06 |
| ** ON A/C ALL | |||
| 121VU | COM NAV/SELCAL | 8RN | M04 |
| 121VU | COM NAV/ACP/THIRD/OCCPNT | 6RN | M02 |
| ** ON A/C NOT FOR ALL | |||
| 121VU | COM NAV/ACP/FOURTH/OCCPNT | 20RN | M01 |
C. Do the BITE test of the AMU (Ref. AMM TASK 23-51-00-740-002).
5. Close-upNOTE: As an alternative procedure, you can do this operational test without the CFDS (Ref. AMM TASK 23-51-00-710-001).
Subtask 23-51-34-410-050-A
A. Close Access
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access door 824 (Ref. AMM TASK 52-41-00-410-002).
(3) Remove the access platform(s).
(1) Make sure that the work area is clean and clear of tools and other items.
(2) Close the access door 824 (Ref. AMM TASK 52-41-00-410-002).
(3) Remove the access platform(s).