W DOC AIRBUS | AMM A320F

Installation of the Wireless Access Point (WAP)


TASK 23-36-42-400-801-A
Installation of the Wireless Access Point (WAP)


ZONE: 230
ZONE: 240
ZONE: 250
FIN: 3010MH1 ** ON A/C NOT FOR ALL
FIN: 3010MH2 ** ON A/C NOT FOR ALL
FIN: 3010MH3 ** ON A/C NOT FOR ALL
FIN: 3010MH4 ** ON A/C NOT FOR ALL
1. Reason for the Job
Self explanatory
2. Job Set-up Information
 A. Fixtures, Tools, Test and Support Equipment
REFERENCE
QTY
DESIGNATION
No specific
1
STEPLADDER 1.0 M (3.3 FT)
No specific
AR
TIE WRAP(S)
No specific
Torque wrench: range to between 0.48 and 0.37 m.daN (42.48 and 32.74 lbf.in ) T
 B. Consumable Materials
REFERENCE
DESIGNATION
(Material No.05TKC1)
Adhesive Tape-Electrical Insulation Glass Cloth Silicone -
 C. Work Zones and Access Panels
ZONE/ACCESS
ZONE DESCRIPTION
230
FWD PASSENGER COMPARTMENT
240
MID PASSENGER COMPARTMENT
250
AFT PASSENGER COMPARTMENT
 D. Referenced Information
REFERENCE
DESIGNATION
TASK 20-28-00-912-802-A
Electrical Bonding - General Maintenance Procedure
TASK 23-33-00-710-005-A
Operational Test of the Integrated In-Flight Entertainment (IFE) System
TASK 23-73-00-861-001-A
Energize the Cabin Intercommunication Data System (CIDS)
TASK 23-73-00-862-001-A
De-energize the Cabin Intercommunication Data System (CIDS)
TASK 24-42-00-861-001-A
Energize the Ground Service Network from the External Power
TASK 24-42-00-862-001-A
De-energize the Ground Service Network Supplied from the External Power
TASK 25-23-41-000-001-A
Removal of the Ceiling Panels
TASK 25-23-41-400-001-A
Installation of the Ceiling Panels
F Wireless Access Point (WAP) ** ON A/C NOT FOR ALL
F Wireless Access Point (WAP) ** ON A/C NOT FOR ALL
3. Job Set-up
Subtask 23-36-42-860-051-A ** ON A/C NOT FOR ALL
A. Aircraft Maintenance Configuration
   (1) Make sure that the ground service network is energized
(Ref. AMM TASK 24-42-00-861-001).
   (2) Make sure that the STEPLADDER 1.0 M (3.3 FT) is below the related access panel.
   (3) Make sure that the related ceiling panels are removed (Ref. AMM TASK 25-23-41-000-001).
Subtask 23-36-42-865-051-A ** ON A/C NOT FOR ALL
B. Make sure that this(these) circuit breaker(s) is(are) open, safetied and tagged:
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
2000VUWAP27MHD07
4. Procedure
Subtask 23-36-42-420-050-A ** ON A/C NOT FOR ALL
A. Installation of the Wireless Access Point
F Wireless Access Point (WAP) ** ON A/C NOT FOR ALL
F Wireless Access Point (WAP) ** ON A/C NOT FOR ALL
   (1) Clean the component interfaces and the adjacent area.
   (2) Do an inspection of the component interfaces and the adjacent area.
   (3) Put the WAP (1) in position and install the washers (3) and the screws (2).
   (4) TORQUE the screws (2) to between 0.48 and 0.37 m.daN (42.48 and 32.74 lbf.in ) T.
   (5) Do the electrical bonding of the grounding point (
Ref. AMM TASK 20-28-00-912-802).
   (6) Put the cable brackets (9) in position and install the spacer (10), the washers (11), the screws (12) and (13).
   (7) Remove the CAP-BLANKING from each electrical connector and receptacle.
   (8) Make sure that all the electrical connections are clean and in the correct condition.
   (9) Install the cap (8).
   (10) Put the WAP adapter (5) in position on the receptacle (4) and tighten the screws (6).
   (11) Connect the electrical connectors (7) to the WAP (1).
WARNING: BE CAREFUL WHEN YOU USE CONSUMABLE MATERIALS. OBEY THE MATERIAL MANUFACTURER'S INSTRUCTIONS AND YOUR LOCAL REGULATIONS.
   (12) Apply Adhesive Tape-Electrical Insulation Glass Cloth Silicone - (Material No.05TKC1) to the cable (15).
   (13) Put the cable (15) in position on the cable brackets (9) and safety it with new TIE WRAP(S) (14).
Subtask 23-36-42-865-052-A ** ON A/C NOT FOR ALL
B. Remove the safety clip(s) and the tag(s) and close this(these) circuit breaker(s):
PANELDESIGNATIONFINLOCATION
** ON A/C NOT FOR ALL
2000VUWAP27MHD07
Subtask 23-36-42-860-052-A ** ON A/C NOT FOR ALL
C. Preparation for the Test
   (1) Energize the CIDS (Ref. AMM TASK 23-73-00-861-001).
Subtask 23-36-42-710-050-A ** ON A/C NOT FOR ALL
D. Operational Test
   (1) Do the operational test of the WAP (Ref. AMM TASK 23-33-00-710-005).
5. Close-up
Subtask 23-36-42-410-051-A ** ON A/C NOT FOR ALL
A. Close Access
   (1) Install the related ceiling panels (Ref. AMM TASK 25-23-41-400-001).
   (2) Remove the STEPLADDER 1.0 M (3.3 FT).
   (3) Make sure that the work area is clean and clear of tools and other items.
Subtask 23-36-42-862-050-A ** ON A/C NOT FOR ALL
B. Put the aircraft back to its initial configuration.
   (1) De-energize the CIDS (Ref. AMM TASK 23-73-00-862-001).
   (2) De-energize the ground service network (Ref. AMM TASK 24-42-00-862-001).
[Rev.10 from 2021] 2026.04.02 06:12:11 UTC